HOME SBOX THOMX MINICAV Utilities
MINICAV orders MINICAV installation MINICAV commissioning MINICAV control command
  Status of commissioning, report also here plots are reports., Page 1 of 5  Not logged in ELOG logo
Entry   Mirrors Mottors Connections , posted by Manar Amer at Other about mechanics 20210804_Motor_connections_with_mirrors_inside_cavity_box.jpg20210804_Mottor_cables_behind_cavity_box.jpg
* The connections to control the motors of the mirrors are connected in the order stated :

                 M1       
-      M2       -       M3     -   
    Reply   Mirrors Mottors Connections , posted by Manar Amer at Other about mechanics | cabling 
Added the cabling to the categories 




Manar
Amer wrote:



* The connections to control the motors of the mirrors are connected
Entry   Setting up the Motors, posted by Manar Amer at Other about mechanics | cabling | software setting_up_the_motors.docx
A document attached that describes the procedure needed to:

- connect the motors

- configure the Ethernet connection
Entry   Alignment using Helium Neon Laser , posted by Manar Amer at Other about lasers and optics 20210202__Helium_Neon_laser_parameters.jpg
05 April  2021 :  A rough alignment of the cavity was done using the Helium Neon Laser.
Entry   Distances between mirrors , posted by Manar Amer at Other about mechanics | software 20211604__Distances_Between_mirrors.pngstatus9nov2020.pptx

  At the reference zero the distance between the mirrors is (taken from a reference presentation "status9nov2020" attached):


                  
M1-M2 = 88.029 mm

                   M3-M4 = 84.6895 mm
Entry   Alignment using Koheras , posted by Manar Amer at Other about lasers and optics 6x
Following the Helium Neon Alignment + change in the distance between the mirrors to be; M3-M4 = 90.5 mm , M1-M2 = 80.2 mm  -→ The alignment
using the Koheras CW laser is done.


Additional components used:

for monitoring beam :  Photodiode (power of beam), Beam Profiler (shape, position, power
    Reply   Mode observed and cavity Lock , posted by Manar Amer at Other about lasers and optics 20212804_Fundamental_mode_in_cavity_2D_-_Position.png20212804_Cavity_Coupling_with_Koheras.jpg20212804_Temperature_Curve.jpg
** Following up from yesterday an observation about the TM00 mode : it has been seen with similar dimensions and its position is the same, this was before
restarting the temperature regulator. 

                 --> after restarting the temp. regulator 
    Reply   Distances between mirrors , posted by Manar Amer at Other about mechanics | lasers and optics | software 20210305_Distances_between_Mirrors_new_motor_set_point.png
New update on the position of the Motors for the cavity

***** we moved the motors to set the cavity at 876MHz, and checked it right after with the RF modulation at FSR.

       So compared to the expected setting we had to move inwards the two planar mirrors by 0.9 mm each.
    Reply   Mode observed and cavity Lock , posted by Manar Amer at Other about lasers and optics NF_Trans__2021-06-25__16-38-56.bmp
New configuration is made. The new mode observed in NF_Trans is the following :




Manar
Amer wrote:



** Following up from yesterday an observation about the TM00 mode :
Entry   Presentations, posted by Blanc at Other about utilities 2-Présentation_LAL_22_06_2020_Corrigée.pptx4-Présentation_LAL_29_06_2020_Corrigée.pptx5-Présentation_LAL_27_07_2020.pptx6-Présentation_LAL_30_11_2020.pptx7-Présentation_LAL_07_12_2020.pptx
Here the first part of all the presentations since the beginning of the project.
Entry   Presentations, posted by Blanc at Other about utilities 8-Présentation_LAL_15_04_2021_elog.pptx9-Présentation_LAL_10_05_2021_elog.pptx10-Présentation_LAL_28_06_2021.pptx
Here the second part of all the presentations since the beginning of the project.
Entry   Presentations, posted by Blanc at Other about utilities 12-Présentation_LAL_13_09_2021.pptx13-Présentation_LAL_27_09_2021.pptx14-Présentation_LAL_11_10_2021.pptxPrésentation_Amplitude_23_08_2021.pptx
Here the last part of all the presentations since the beginning of the project.
Entry   Phase noise measurement of the Amplitude MIKAN, posted by Ronic Chiche at Optical room about lasers and optics | detectors and electronics 
Installation of the MIKAN.
powermeter (with OD1) just after the oscillator shows 440mW for 4A of the MIKAN pump current.

    Reply   Phase noise measurement of the Amplitude MIKAN, posted by Ronic Chiche at Optical room about lasers and optics | detectors and electronics 
Coupling into a 50-50% fiber coupler using the Thorlabs XYZ table NanoMax TS.
We reached 117mW after the 50% arm which means we coupled about 230mW (the coupling better than 50%).




Ronic
Entry   Lock, cavity length and finesse estimate, posted by Aurélien Martens at Optical room about lasers and optics | detectors and electronics IMG_20210430_173331.jpg
Ronic just suceeded in obtaining a reasonably good lock on the cavity. Air flow is switched off.

We stopped all movements (closed loop, click STOP in the PTC interface) and saw immediately a fair but not excellent lock.

We then switched off the smaract motors and the obtained lock was good. Switching on again the smaract means tthat the references are lost.
Entry   Theoretical Finesse, Gain and Coupling, posted by Ronic Chiche at Optical room about lasers and optics 
For spherical mirrors M3 and M4 (batch C117I054) the reflectance (R) is around 99.9987% (if T+R=1 => T=13ppm)

For plan mirror M2 (batch C217G054) the reflectance (R) is around 99.9977% (if T+R=1 => T=23ppm)

(1) => For plan mirror M1 (batch C217H023) the reflectance (R) is around 98.96% and transmittance (T) is around 1.14% (T=11400 ppm)
Entry   Cameras Calibration, posted by Kevin Dupraz at Optical room about lasers and optics | detectors and electronics NF_Refl_calib_hex2mm__2021-06-23__16-59-26.bmpNF_Trans_calib_hex2mm__2021-06-23__17-06-49.bmpNF_Inj_calib_DIODE__2021-06-24__10-56-00.bmpNF_Inj_calib_DIODE__2021-06-24__10-42-00.bmpNF_Trans__2021-06-25__16-38-56.bmp
After installing cameras the actual calibration are :

NF_Refl: acA1920-40gm
    pixel size (real): 5.86um
Entry   Cavity lock and references, posted by Kevin Dupraz at Optical room about lasers and optics | detectors and electronics NF_Trans_2021-09-06__17-49-00.bmp
Cavity is lock and optimized with the NKT. Input power is maximized (10mW).

Cavity mode is in attachement. The reference on camera with BeamProfiler Matlab code is the following:

FF_refl: [2.0883    1.1606]
    Reply   Lock, cavity length and finesse estimate, posted by Aurélien Martens at Optical room about lasers and optics | detectors and electronics 
we observed that the transmitted light coming from the cavity is made of the cavity mode light and the scattered light on the borders of the mirrors.
the scattered light on the borders of the mirrors is triggered by the cavity mode itself when the cavity is locked.
we didn't put an iris to cut this scattered light coming from the cavity.
Entry   Polarisation Results of the NKT, posted by Blanc at Optical room about lasers and optics Ellipsicité_NKT.PNGPolar_horizontale_fonction_pussance_NKT.PNGPolar_verticale_fonction_pussance_NKT.PNGPolarisation_Ag_VS_Diélec.PNG
I made many tests about polarization and we can see some points thanks to the following figures :

1- The ellipsicity of the NKT is near to 0 (between -0,2 and 0,2) which means the polarization is rectilinear horizontale (attachement 1).

2- The power of the NKT has no influence on the polarization, verticale or horizontale (attachement 2 and 3).
ELOG V3.1.4-395e101