  990   Thu Jan 9 08:35:10 2025 IC, VK, VM, NDUnder ProcessShift summaryRing   

08h35 Start ThomX: Modulator, Frigo, All magnets.

08h40 Cicling all magnets, Start Chillers 

10h00 HV is 'On'

Modulator Interlocks at HV=1215V

10h25 HV=1215 V

Rec. from 20241219 18:14

Linac Steerers: H [2.38 -4.16],  V [-1.70 2.15]

RF Gun Phase is 199.0 dg., RF Gun Att. is 0 dB, (Dark Current is 18 mV, too low), Sect. Att. 2.53 dB, Sect. Phase is 221 dg.

Charges: -106 pC, -107 pC, -116 pC

10h50 Beam is injected to the ring

Trying the LOCO

12h35 Modulator Interlocks at HV=1215V, Went to 1200 V. Did not help even at 1000V (Maher's intervention needed).

13h00 This is the problem with triggering. When triggered internally, the modulator is working.

13h07 OK at HV=1215 V (Unknown reason). Nikolas said miss triggering is less than 5%

13h20 Linac frequency was changed a little bit to diminish miss triggering

18h00 Stop ThomX

 

 

Attachment 1: Screenshot_from_2025-01-09_16-00-44.png
Screenshot_from_2025-01-09_16-00-44.png
Attachment 2: Screenshot_from_2025-01-09_14-24-06.png
Screenshot_from_2025-01-09_14-24-06.png
Attachment 3: Screenshot_from_2025-01-09_11-11-21Change_inRingChargedueLinacEnrgy.png
Screenshot_from_2025-01-09_11-11-21Change_inRingChargedueLinacEnrgy.png
Attachment 4: TL_SST01_Screenshot_from_2025-01-09_10-34-15.png
TL_SST01_Screenshot_from_2025-01-09_10-34-15.png
Attachment 5: Screenshot_from_2025-01-09_10-32-26.png
Screenshot_from_2025-01-09_10-32-26.png
Attachment 6: Screenshot_2025-01-09_10-30-03.png
Screenshot_2025-01-09_10-30-03.png
Attachment 7: Screenshot_from_2025-01-09_16-03-40.png
Screenshot_from_2025-01-09_16-03-40.png
Attachment 8: Screenshot_from_2025-01-09_16-31-08.png
Screenshot_from_2025-01-09_16-31-08.png
Attachment 9: Screenshot_from_2025-01-09_17-55-28.png
Screenshot_from_2025-01-09_17-55-28.png
Attachment 10: Screenshot_from_2025-01-09_17-52-20.png
Screenshot_from_2025-01-09_17-52-20.png
Attachment 11: Screenshot_from_2025-01-09_17-49-53.png
Screenshot_from_2025-01-09_17-49-53.png
Attachment 12: Screenshot_from_2025-01-09_17-39-00.png
Screenshot_from_2025-01-09_17-39-00.png
Attachment 13: Screenshot_from_2025-01-09_17-38-38.png
Screenshot_from_2025-01-09_17-38-38.png
Attachment 14: Screenshot_from_2025-01-09_17-38-03.png
Screenshot_from_2025-01-09_17-38-03.png
Attachment 15: TrendTBTSumScreenshot_from_2025-01-09_18-06-08.png
TrendTBTSumScreenshot_from_2025-01-09_18-06-08.png
  993   Fri Jan 10 08:24:25 2025 IC, VK, VM, NDUnder ProcessShift summaryRing Commissioning   

08h25 Start ThomX: Modulator, Frigo, cycling all magnets

08h30 Start chillers

10h00 HV is 'On'

10h25 RF Gun Phase is 193 dg., Sect. Att. is 2.46 dB, Phase is 218 dg. Charges:  -98 pC, -105 pC, -106 pC

Linac steerers: H [2.38 -4.16], V [-1.8 2.15]

Ring injection. After cycling Ri-C1 QP5 is out of order, fixed

10h30 Beam is in the ring, Rec. from 20250109_17_23, TL/BPM02 X=+3 mm

11h00 setings for ring without sextupoles for LOCO

11h04 setings for ring without sextupoles for LOCO (Matlab config file) is saved

The same with sextupoles.

Trying LOCO with sextupoles: LOCO inprove results on storage and tune. Tune changed from 0.15 to 0.17

13h30 HV is 'Off'.  Controled access to the bunker.

13h55 HV is 'On'

/tmp_mnt/data/shared/commissioning_scripts/MatLab/pilotage/libera_calctunesS_ThomxOperateur.m  to measure tune from operateut.thomx account

16h55 Stop ThomX

 

Attachment 1: Screenshot_from_2025-01-10_16-35-44.png
Screenshot_from_2025-01-10_16-35-44.png
Attachment 2: Screenshot_from_2025-01-10_16-03-43.png
Screenshot_from_2025-01-10_16-03-43.png
Attachment 3: Screenshot_from_2025-01-10_15-51-56.png
Screenshot_from_2025-01-10_15-51-56.png
Attachment 4: ChargeTransitionScreenshot_from_2025-01-10_14-51-56.png
ChargeTransitionScreenshot_from_2025-01-10_14-51-56.png
Attachment 5: Screenshot_from_2025-01-10_12-45-41.png
Screenshot_from_2025-01-10_12-45-41.png
Attachment 6: Screenshot_from_2025-01-10_12-03-50.png
Screenshot_from_2025-01-10_12-03-50.png
Attachment 7: Screenshot_from_2025-01-10_11-13-55.png
Screenshot_from_2025-01-10_11-13-55.png
Attachment 8: TBTSumScreenshot_from_2025-01-10_10-59-16.png
TBTSumScreenshot_from_2025-01-10_10-59-16.png
Attachment 9: Screenshot_from_2025-01-10_10-58-28.png
Screenshot_from_2025-01-10_10-58-28.png
Attachment 10: Screenshot_from_2025-01-10_10-58-14.png
Screenshot_from_2025-01-10_10-58-14.png
  997   Thu Jan 16 08:28:07 2025 VM, IC, VKUnder ProcessShift summaryRing Commissioning   

08h25 Start ThomX: Modulator, frigo

08h35 Start chilers, laser, cycling all magnets

10h05 HV is 'On'

RF gun phase is 161 dg., Dark current about 25 mV, Att. Sect. is 2.53 dB, phase is 213 dg., Charges: -101 pC, 99. pC, -109 pC

Linac steerers: H [2.63 -4.38], V [-2.03 2.47]

10h20 RF cavity; problem with amplifier: fixed

10h25 Beam injected to the ring without RF, RCDS on the transfer line

10h45 RF is 'On'  150kV, phase -58.5 dg. TL/BPM02 X=0 

10h55 Receipt saved (I dp in ring at 159.3 A)

LOCO

11h38 Jump in Vertical position at TL/BPM01 on +1mm. Storage drops

Change the linac steerer V1 to -2.23 TL/BPM01 Y=-0.5 mm

12h16 Start feedback on the TL/BPM.01 position X=0, Y=-0.5

14h30 Start cycling dipoles and quads of the ring

14h43 The receipt from 10h55 loaded. Storage restored

15h10 ring settings with I dp = 160.4 A loaded (from the receipt of 20250110_11_04)

18h05 Stop ThomX

 

 

 

 

 

 

Attachment 1: Screenshot_from_2025-01-16_17-16-28.png
Screenshot_from_2025-01-16_17-16-28.png
Attachment 2: Screenshot_from_2025-01-16_16-56-04.png
Screenshot_from_2025-01-16_16-56-04.png
Attachment 3: Screenshot_from_2025-01-16_11-33-59.png
Screenshot_from_2025-01-16_11-33-59.png
Attachment 4: Osc_StorageChargeCH4Screenshot_from_2025-01-16_11-27-32.png
Osc_StorageChargeCH4Screenshot_from_2025-01-16_11-27-32.png
Attachment 5: Screenshot_from_2025-01-16_11-10-02.png
Screenshot_from_2025-01-16_11-10-02.png
Attachment 6: Screenshot_from_2025-01-16_11-07-11.png
Screenshot_from_2025-01-16_11-07-11.png
Attachment 7: Screenshot_from_2025-01-16_11-04-28.png
Screenshot_from_2025-01-16_11-04-28.png
Attachment 8: Screenshot_from_2025-01-16_11-01-48.png
Screenshot_from_2025-01-16_11-01-48.png
Attachment 9: Screenshot_from_2025-01-16_10-46-29.png
Screenshot_from_2025-01-16_10-46-29.png
Attachment 10: Screenshot_from_2025-01-16_10-46-15.png
Screenshot_from_2025-01-16_10-46-15.png
  999   Fri Jan 17 08:44:09 2025 MV, IC, VKUnder ProcessShift summaryRing Commissioning   

08h43 Start ThomX: Modulator, frigo, laser, cycling all magnets

08h50 Chillers started

09h52 HV is 'On'

10h08 HV=1215V

10h25 RF Gun Phase is 153 dg., Sect Att. is 2.5 dB, Phase is 206 dg. Charges: -107 pC, -107 pC, -113 pC

10h30 Beam injected to the ring, Receipt from 16/01/2025  18:03 TL/BPM02 X=+2mm, without RF the ring orbit is low (all negative)

11h00 RF is 'On', 100kV

11h07 FR 150 kV; to minimize synchrotron oscillations TL/BPM02 X=+2 mm

11h33 Vacuum interlock, restarted

12h28 FPC table Scan

12h40 FPC table scan: sigma Y=171 um

13h33 FPC table scan: sigma Y=156 um

13h57 RF voltage set to 250kV

14h20 FPC table scan: sigma Y=179 um

14h25 The ring optics from 10-Jan-2025 11h03 loaded

Vertiacl tune studies. Steptune 0.05 several tilmes , vertical tune start to be pronounced; Tune correction towards the nominal one 0.64;

15h27 FPC table scan: sigma Y=126 um

16h00 FPC table scan: sigma Y=121 um

For all scans FPC power 90 kW, laser size was 70 um

17h35 Stop Thomx

 

Attachment 1: Screenshot_from_2025-01-17_17-26-25.png
Screenshot_from_2025-01-17_17-26-25.png
Attachment 2: Screenshot_from_2025-01-17_17-20-47.png
Screenshot_from_2025-01-17_17-20-47.png
Attachment 3: Screenshot_from_2025-01-17_16-06-37.png
Screenshot_from_2025-01-17_16-06-37.png
Attachment 4: Screenshot_from_2025-01-17_15-35-59.png
Screenshot_from_2025-01-17_15-35-59.png
Attachment 5: Screenshot_from_2025-01-17_15-06-53.png
Screenshot_from_2025-01-17_15-06-53.png
Attachment 6: Screenshot_from_2025-01-17_15-06-25.png
Screenshot_from_2025-01-17_15-06-25.png
Attachment 7: Screenshot_from_2025-01-17_14-35-44.png
Screenshot_from_2025-01-17_14-35-44.png
Attachment 8: Screenshot_from_2025-01-17_14-21-51.png
Screenshot_from_2025-01-17_14-21-51.png
Attachment 9: Screenshot_from_2025-01-17_14-20-32.png
Screenshot_from_2025-01-17_14-20-32.png
Attachment 10: FIRSTvertSCQN.png
FIRSTvertSCQN.png
Attachment 11: Screenshot_from_2025-01-17_13-44-48.png
Screenshot_from_2025-01-17_13-44-48.png
Attachment 12: Screenshot_from_2025-01-17_13-33-41.png
Screenshot_from_2025-01-17_13-33-41.png
Attachment 13: Screenshot_from_2025-01-17_13-33-32.png
Screenshot_from_2025-01-17_13-33-32.png
Attachment 14: Screenshot_from_2025-01-17_12-53-41.png
Screenshot_from_2025-01-17_12-53-41.png
Attachment 15: Screenshot_from_2025-01-17_12-36-29.png
Screenshot_from_2025-01-17_12-36-29.png
Attachment 16: Screenshot_from_2025-01-17_11-53-49.png
Screenshot_from_2025-01-17_11-53-49.png
  1002   Wed Jan 22 13:32:43 2025 MJ HGFixedShift summaryTL | LE | Ring | Linac Commissionning   

** Alignement Q1Q3 du jour

str1H 0.69
str1V -3.03
str2H -2.94
str2V 3.39

Passage TL min dispersion (phase sec 214 - att 2.56)

*** Alignement SECTION

str1H 1.64
str1V -1.94
str2H -3.77
str2V 2.87

Avec cet alignement, pour une excursion de phase de 180 a 250, le faisceau bouge seulement de 1 mm sur YagTL1
==> La section est alignee avec ce jeu de steerers
(aux kicks faisceau pres ...)

- Charge transmise vs soleno : ok de 190A a 240 A - cf screenshot
- Mesures d'emittance Q3 section alignee MAIS attention : PAS a la bonne phase section ! (254 au mieu de 214 .....)

** Mesures yagTL1 et bpmTL1 prises pour Alignement section et pour Alignement Q1Q3

*** Kicks faisceau bpmTL1 : Correles a Li/Vac 02 et Li/Vac 03 (screenshot dans data/shared)

20h20 fin de shift

 

Attachment 1: Q_vs_SolenoScan_at_17-21-28.png
Q_vs_SolenoScan_at_17-21-28.png
  Draft   Thu Jan 23 08:44:17 2025 MV, IC, VK, RCUnder ProcessShift summaryRing Commissioning   

08h41 Start Thomx: Modulator, Frigo, Laser

08h46 Start chillers, all magnets sycling

09h50 Start RF

10h55 Linac steerers are about from 22/01/2025: H [0.49 -2.94], V [-3.13 3.39] to align with QP1 - QP3

RF Gun phase is 164 dg., Sect. Att. is 2.64 dB, Sect. phase is 208 dg., Charges: -108 pC, -115 pC, -119 pC

if set QP5 through QP7 and all TL steerers 'Off' but TL/Str01-V1 (-1.6 A): TL/BPM02 X,Y 0,0; TL/BPM03 X,Y -6.0,+2.0, TL/BPM04 X,Y -6.0,+5.0

11h30 Beam is in the ring: TL/BPM02 X,Y 1.2,0.9; TL/BPM03 X,Y -4.6,+3.2, TL/BPM04 X,Y -2.7,+2.7

14h43 Good Receipt 50 MeV for X rays

14h55 FPC table scan: sigma y =140 um

15h16 FPC table scan: sigma y =124 um

16h25 X ray detector level 40000

16h57 RF 150 kV, X ray detector level 50000 (one point)

It seems that Ri-C1 STR06-V01 and  Ri-C2 STR02-V01 have wrong polarity

18h05 Breakdowns in the RF Gun, Vacuum interlock

18h10 Restored

18h20 Stop ThomX

  1005   Fri Jan 24 08:45:26 2025 MV, IC, VK, RCUnder ProcessShift summaryRing Commissioning   

08h45 Start Thomx: Modulator, frigo, laser

08h50 Start chillers, cycling all magnets

Vacuum intervention, beam pipe closed. Vacuum OK to start (11.23)

Vacuum MPS off (Kevin)

Polarity of 2 vertical steerers in the ring :! ric1/str.06-v.01 and

ric2/str.02-v.01 were changed by Jean Noel, according to our request. 

11h20 HV is 'On'

RF Gun phase is 162 dg. Att. is 0.04 dB, Sect Att. is 2.62 dB, Phase is 212 dg. Charges: -107 pC, -112 pC, -117 pC

14h12 FPC table scan. Sigma y = 140um (receipt from 14h14). RF 150 kV

Accelerating section phase often needs  adjasment (from 106 dg. to 112 dg. )

Trying LOCO. 

14h51 the receipt from 14h14 loaded (saved before LOCO). The FPC table at X ray max. (X photodiode reading of 470 pA ). Ramp the RF cavity to 250 kV

14h58 Slava made RCDS on X photodiode readings by adjusting vertical steerers of the ring.   X photodiode reading is 500 pA

15h04 Receipt seved. X photodiode readings reaches 522 pA.

15h15 FPC table scan. Sigma y = 128 um (receipt from 14h14). RF 250 kV

15h22 RF Gun phase is 166 dg. Att. is 0.04 dB, Sect Att. is 2.62 dB, Phase is 212 dg.

Beam position at TL/BPM02 unstable from the trigger to the trigger, so the ring storage.

16h00 Going to 61.5 MeV. Sect Att. at 1.1 dB, phase 228 dg. RF at 500.04545 MHz, 50 kV TL/BPM02 X=+4mm

16h38 receipt saved. There is some storage, but orbit is wide

17h30 Optimized configuration for 61.5 MeV very good storaga => Rceipt good_20250124_17_36_24

 

 

 

 

  1006   Fri Jan 24 17:39:00 2025 MV, IC, VK, RCUnder ProcessShift summaryRing Commissioning   

08h45 Start Thomx: Modulator, frigo, laser

08h50 Start chillers, cycling all magnets

Vacuum intervention, beam pipe closed. Vacuum OK to start (11.23)

Vacuum MPS off (Kevin)

Polarity of 2 vertical steerers in the ring :! ric1/str.06-v.01 and

ric2/str.02-v.01 were changed by Jean Noel, according to our request. 

11h20 HV is 'On'

RF Gun phase is 162 dg. Att. is 0.04 dB, Sect Att. is 2.62 dB, Phase is 212 dg. Charges: -107 pC, -112 pC, -117 pC

14h12 FPC table scan. Sigma y = 140um (receipt from 14h14). RF 150 kV

Accelerating section phase often needs  adjasment (from 106 dg. to 112 dg. )

Trying LOCO. 

14h51 the receipt from 14h14 loaded (saved before LOCO). The FPC table at X ray max. (X photodiode reading of 470 pA ). Ramp the RF cavity to 250 kV

14h58 Slava made RCDS on X photodiode readings by adjusting vertical steerers of the ring.   X photodiode reading is 500 pA

15h04 Receipt seved. X photodiode readings reaches 522 pA.

15h15 FPC table scan. Sigma y = 128 um (receipt from 14h14). RF 250 kV

15h22 RF Gun phase is 166 dg. Att. is 0.04 dB, Sect Att. is 2.62 dB, Phase is 212 dg.

Beam position at TL/BPM02 unstable from the trigger to the trigger, so the ring storage.

16h00 Going to 61.5 MeV. Sect Att. at 1.1 dB, phase 228 dg. RF at 500.04545 MHz, 50 kV TL/BPM02 X=+4mm

16h38 receipt saved. There is some storage, but orbit is wide

17h30 Optimized configuration for 61.5 MeV very good storaga the RF cavity at 500.04545 MHz => Rceipt good_20250124_17_36_24

Orbits with and without RF are close

17h40 Stop thomx

 

 

 

 

Attachment 1: Screenshot_from_2025-01-24_17-35-38_61p5MeV.png
Screenshot_from_2025-01-24_17-35-38_61p5MeV.png
Attachment 2: Screenshot_from_2025-01-24_17-34-48_61p5MeV.png
Screenshot_from_2025-01-24_17-34-48_61p5MeV.png
Attachment 3: Screenshot_from_2025-01-24_17-34-23_61p5MeV.png
Screenshot_from_2025-01-24_17-34-23_61p5MeV.png
  Draft   Fri Feb 14 08:21:26 2025 Entered by Super Team from 134.158.195.141 on Fri Feb 14 08:21:09 2025Under ProcessShift summaryRing Commissioning   

08h20 Start ThomX: modulator, laser, fridge,cycling all magnets

08h25 chillers are started

09h50 Controlled access (Rhonic)

09h57 HV is 'On'

10h00 HV is at 1215 V

10h04 RF Gun phase is 136 dg.

10h10 Receipt from 13022025 15;05 loaded

Sect. Phase is 215 dg., Att. 2.48, TL /BPM02 X=0

The yesterday receipt does not provide yesterday storage. The ring was adjusted.

13h20 Vacuum interlock in the ring

13h40 Tthe linac waz reajusted after the interlock. RF Gun phase is 124 dg. Sect. Phase is 215 dg. TL /BPM02 X=3.5 mm

14h21 Scan FPC table. Vert. sigma 120um

Charge: -109; -104; -117 pC

15h00 61.5 MeV. Charges: -110, -107, -113 pC; F=500.04545, 100 kV, Manual phase shifter on 5254, RF phase is 23.5 dg. (the mixer phase shifter for amplitude 3562 )

15h34 Scan FPC table, so-so.

16h15 Scan FPC table 177 um.  Recipt All_202050217_16_22

16h59 70 MeV Sect. Att. 0.244 dB, Phase 238 dg. TL/BPM2 X=-0.5 mm. Linac steerers: H [0.19 -2.85], V [-3.63 3.49]

18h05 Can not store the beam

18h06 Stop ThomX

 

 

 

  1014   Wed Feb 19 08:28:11 2025 Entered by Super Team from 134.158.195.141 on Wed Feb 19 08:27:57 2025Under ProcessShift summaryRing Commissioning   

08h26 Start ThomX: Modulator, Fridge, Laser

08h32 Chillers were started, cycling all magnets

11H changement de la carte synchro... Carte synchro opérationnel

Impossible d'avoir un signal sur l'ICT1 qq soit la phase ==> synchro ??

Vincent est repasse c ok

13h20 Receipt from 202514_14_21_55 loaded (suitable for 50 MeV), injector adjusted, there is a beam in the ring without RF and with RF 50 kV, 36.5 dg. It is necessary to adjust the injection (storage is not too bad, but TL/BPM2 x=+7.5). The injection kicker affects the radio protection system, causing blocking.

13h55 the modulator is in the standby mode, the laser shutter is closed

 

 

  1016   Thu Feb 20 08:25:11 2025 Entered by Super Team from 134.158.195.141 on Thu Feb 20 08:24:55 2025Under ProcessShift summaryRing Commissioning   

08h25 Start ThomX; Start ThomX: Modulator, Fridge, Laser

08h32 Chillers were started, cycling all magnets

11h23 HV is 'On'

11h46 RF Gun Phase is 28 dg. Sect Att. is 2.54 dB, Phase is 209 dg. TL/BPM2 X=0, Charges: -88, -92, -96 pC

Linac correctors: H [0.59 -2.86], V [-3.23 3.47]

12h24 Beam in the ring RF 50 kV, Phase 44 dg.

12h35 RF 150kV, Phase 32 Kicker delay 7.3952 us,  9497 V

17h10 HV on 'Sttandby', the laser gate closed, injection kicker pulse correction

17h52 injection kicker pulse was corrected

HV is 'On'

18h39 The beam is in the ring. It is OK!

18h45 Stop ThomX

Attachment 1: Screenshot_from_2025-02-20_18-42-31.png
Screenshot_from_2025-02-20_18-42-31.png
Attachment 2: Screenshot_from_2025-02-20_18-42-20.png
Screenshot_from_2025-02-20_18-42-20.png
Attachment 3: Screenshot_from_2025-02-20_18-42-05.png
Screenshot_from_2025-02-20_18-42-05.png
Attachment 4: Screenshot_from_2025-02-20_18-41-25.png
Screenshot_from_2025-02-20_18-41-25.png
Attachment 5: Screenshot_from_2025-02-20_18-41-02.png
Screenshot_from_2025-02-20_18-41-02.png
Attachment 6: Screenshot_from_2025-02-20_18-40-47.png
Screenshot_from_2025-02-20_18-40-47.png
  1028   Wed Mar 5 08:53:34 2025 VM, VC, RC, DNUnder ProcessShift summaryRing Commissioning   

08h53 Start ThomX

11h10 The oscilloscope installed in the bunker

11h11 HV is 'On'

11h45 The beam is in the ring

12h10 The modulator set to the Standby mode. Access to the bunker

12h24 HV is 'On'

12h30 RF Gun Phase is 15 dg., Sect. phase is 204 dg., Att. is 2.503 dB, TL/BPM2 X= 4 mm, Charges: -108 pC, -108 pC, -120 pC  

12h35 Feedback on linac injection was started

13h00 Measurement of the stability of the temporal position of electron and photon bunches at the IP. RF Cav. at 200 kV, Phase 35 dg.

13h07 The linac was adjusted: RF Gun phase 10 dg., Sect phase 199 dg. Charges: -100 pC,-99 pC, -110 pC, Inj. qual. 0.965, Storage qual. 0.802

14h26 The linac was adjusted: RF Gun phase 11 dg., Sect phase 203 dg. Charges: -99 pC,-99 pC, -109 pC, Inj. qual. 0.984, Storage qual. 0.747, X ray flux I3=25000 pA

Phase between electron beam and FP photon have been done (attachements will come later) (Electron beam is a pickup (150ps fall time) at the IP and Photon beam  is a photo diode (300ps rise time) at the FP cavity output).

time jitter is measured as the time difference between the two ulses at a fixed treshhold of 10mV)

measurements show a 33ps FWHM jitter (15ps)   as long as the FPC is locked on the 500MHz . the jitter mainly come from FPC (see post FPC : https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/416)

15h35 The linac was adjusted: RF Gun phase 19 dg., Sect phase 212 dg. Charges: -105 pC,-104 pC, -115 pC, Inj. qual. 0.988, Storage qual. 0.786,

17h45 Stop ThomX

 

Attachment 1: JItter_laserFP-Ebeamring-4.png
JItter_laserFP-Ebeamring-4.png
Attachment 2: JItter_laserFP-Ebeamring.png
JItter_laserFP-Ebeamring.png
Attachment 3: 2025-03-05_15_11_40_li_dg_sst_01-ccd_01_RAW.png
2025-03-05_15_11_40_li_dg_sst_01-ccd_01_RAW.png
Attachment 4: 2025-03-05_14_17_36_tl_dg_sst_03-ccd_01_RAW.png
2025-03-05_14_17_36_tl_dg_sst_03-ccd_01_RAW.png
Attachment 5: 2025-03-05_14_14_49_tl_dg_sst_01-ccd_01_RAW.png
2025-03-05_14_14_49_tl_dg_sst_01-ccd_01_RAW.png
Attachment 6: 2025-03-05_14_14_19_tl_dg_sst_01-ccd_01_RAW.png
2025-03-05_14_14_19_tl_dg_sst_01-ccd_01_RAW.png
Attachment 7: 2025-03-05_14_13_20_tl_dg_sst_02-ccd_01_RAW.png
2025-03-05_14_13_20_tl_dg_sst_02-ccd_01_RAW.png
Attachment 8: 2025-03-05_14_13_01_tl_dg_sst_02-ccd_01_RAW.png
2025-03-05_14_13_01_tl_dg_sst_02-ccd_01_RAW.png
Attachment 9: 2025-03-05_11_31_26_tl_dg_sst_02-ccd_01_RAW.png
2025-03-05_11_31_26_tl_dg_sst_02-ccd_01_RAW.png
Attachment 10: 2025-03-05_11_18_31_li_dg_sst_01-ccd_01_RAW.png
2025-03-05_11_18_31_li_dg_sst_01-ccd_01_RAW.png
Attachment 11: Screenshot_from_2025-03-05_16-56-31.png
Screenshot_from_2025-03-05_16-56-31.png
Attachment 12: Screenshot_from_2025-03-05_16-55-08.png
Screenshot_from_2025-03-05_16-55-08.png
Attachment 13: Screenshot_from_2025-03-05_16-52-56.png
Screenshot_from_2025-03-05_16-52-56.png
Attachment 14: Screenshot_from_2025-03-05_16-52-45.png
Screenshot_from_2025-03-05_16-52-45.png
Attachment 15: Screenshot_from_2025-03-05_16-52-33.png
Screenshot_from_2025-03-05_16-52-33.png
Attachment 16: Screenshot_from_2025-03-05_16-52-19.png
Screenshot_from_2025-03-05_16-52-19.png
  1032   Tue Mar 11 14:31:06 2025 VMUnder ProcessShift summaryLinac Commissionning   

14h31 Start ThomX/ Modulator, Frig, Laser

14h37 Cycling all magnets, Chillers started

15h34 HV is 'On'

There are problems with the servers. Therefore, some tools are not working: Trends,  Camera Laser and so on.
Servers restarted, we also used script from Kevin to restart properly DSs.
Beam Charge : 70 pC !!! RF gun phase is set to 109 dg.

17h30 Linac steerers H [0.67 -2.77], V [-2.95 3.19], RF Gun phase   214 dg. Att. 2.47 dB.

Measure dispersion in the TL

18h45 QP4 - QP7 set to 0

Screenshots of TL orbit for different Att.

18h53 HV is 'OFF', Stop thomX

 

Attachment 1: Screenshot_from_2025-03-11_15-45-29.png
Screenshot_from_2025-03-11_15-45-29.png
Attachment 2: Screenshot_from_2025-03-11_18-43-44.png
Screenshot_from_2025-03-11_18-43-44.png
Attachment 3: Screenshot_from_2025-03-11_18-42-52.png
Screenshot_from_2025-03-11_18-42-52.png
Attachment 4: Screenshot_from_2025-03-11_18-42-15.png
Screenshot_from_2025-03-11_18-42-15.png
Attachment 5: Screenshot_from_2025-03-11_18-41-47.png
Screenshot_from_2025-03-11_18-41-47.png
Attachment 6: Screenshot_from_2025-03-11_18-41-20.png
Screenshot_from_2025-03-11_18-41-20.png
Attachment 7: 2025-03-11_17_32_20_tl_dg_sst_01-ccd_01_RAW.png
2025-03-11_17_32_20_tl_dg_sst_01-ccd_01_RAW.png
Attachment 8: 2025-03-11_17_32_06_tl_dg_sst_01-ccd_01_RAW.png
2025-03-11_17_32_06_tl_dg_sst_01-ccd_01_RAW.png
Attachment 9: 2025-03-11_17_30_11_li_dg_sst_01-ccd_01_RAW.png
2025-03-11_17_30_11_li_dg_sst_01-ccd_01_RAW.png
  Draft   Thu Mar 13 08:29:34 2025 VM, VC, RC, ICUnder ProcessShift summaryRing Commissioning   

08h27 Start ThomX: Modulator, Laser, Frig

08h34 Chillers were started, cycling al magnets

12H ready to start beam ( 13H30)

alignement laser done (alignement to do)

13h20 HV is 'ON'

13h31 RF Gun phase is 95 dg. the laser iris is 1.3 mm, the laser att. 340, RF Gun charge is -120 pC (the laser spot position was Hor. 4.282 mm, Vert. 3.327 mm ), screenshots of Li/SST1

13h35 laser spot alighment started at RF gun phase of 145 dg.

13h36 New position of the laser spot is: Hor. 4.282 mm, Vert. 3.327 mm 

13h44 the modulator was put into standby mode, access to the bunker

14h13 HV is 'ON'

Two plots beam on LI STT 0.1

new receipe all 2025 03 13  14 46 52 

Charge 120pC

RF power 150KV

17h12 RF gun phase 92 dg., Sect. phase 211 dg. I TL DP =159.3 A, TL/BPM X=4 mm, RF cav. 150 kV, phase -15 dg. Sum of TBTSum =1.8e11, Charges: -142 pC,-140 pC, -152 pC, I3 25000 pA

17h31 Adjusting ring lattice to rise X rays. I3 max was 45000 pA

18h29 Stop thomX

 

 

 

 

Attachment 1: 2025-03-13_13_29_10_li_dg_sst_01-ccd_01_RAW.png
2025-03-13_13_29_10_li_dg_sst_01-ccd_01_RAW.png
Attachment 2: 2025-03-13_13_27_49_li_dg_sst_01-ccd_01_RAW.png
2025-03-13_13_27_49_li_dg_sst_01-ccd_01_RAW.png
Attachment 3: Screenshot_from_2025-03-13_18-06-54.png
Screenshot_from_2025-03-13_18-06-54.png
Attachment 4: Screenshot_from_2025-03-13_18-06-43.png
Screenshot_from_2025-03-13_18-06-43.png
Attachment 5: Screenshot_from_2025-03-13_18-06-32.png
Screenshot_from_2025-03-13_18-06-32.png
Attachment 6: Screenshot_from_2025-03-13_18-06-19.png
Screenshot_from_2025-03-13_18-06-19.png
Attachment 7: Screenshot_from_2025-03-13_18-06-05.png
Screenshot_from_2025-03-13_18-06-05.png
Attachment 8: Screenshot_from_2025-03-13_17-52-35.png
Screenshot_from_2025-03-13_17-52-35.png
Attachment 9: Screenshot_from_2025-03-13_17-49-56.png
Screenshot_from_2025-03-13_17-49-56.png
Attachment 10: Screenshot_from_2025-03-13_17-49-22.png
Screenshot_from_2025-03-13_17-49-22.png
Attachment 11: Screenshot_from_2025-03-13_17-49-09.png
Screenshot_from_2025-03-13_17-49-09.png
Attachment 12: Screenshot_from_2025-03-13_17-48-41.png
Screenshot_from_2025-03-13_17-48-41.png
  1048   Mon Mar 31 09:53:26 2025 VM, IC, RCUnder ProcessShift summaryRing Commissioning   

08h00 ThomX started by Maher

09h50 Problem with vacuum in the septum. TL-V3 and EL-V1 are closed.

ThomX configuration changed to 'Linac'.

0955 Laser is 'On'

10h03 Problem with vacuum was fixed. ThomX configuration changed to 'ThomX'.

10h05 Cycling all magnets

10h10 HV is 'On'

10h20 From time to time TO-V3 and EL-V1 close. Septum vacuum is 2.6e-10

Septum power supply is interlocked

10h55 , RF gun phase is 235 dg., Sect. phase is 216 dg., Att. = 2.38 dB, TL/BPM2 X=0.2 mm , Charges: -91 pC, -90 pC, -98 pC, Linac steerers: H [0.84 -2.88], V [-2.47 2.8], receipt from 20250321 12:30:52

11h27 V6 interlocks

11h49 RF gun phase is 225 dg., Sect. phase is 209 dg., Att. = 2.46 dB, TL/BPM2 X=0.2 mm

12h46 to 13h10 Emittance measurements at 50 MeV

13h Problem with Pulsed Elements => fixed by Kevin and Maher

13h30 Tuning of the linac for 70 MeV, emittance measurements.

14h Check the machine at 50 MeV

15h25 The modulator at standby mode. Access to the bunker.

15h45 61.5 MeV receipt from 14/02/2025

Synchronization problem,

17h00 RCDS on injection

17h19 RF Gun phase is 224 dg., Sect. phase 221 dg. Att. 0.975 dB, Charges: -107 pC, -105 pC, -115 pC. TL/BPM2 X=1 mm, RF cav. 100 kV, phase -34 35 dg. manual phase sfifter 7809, phase shifter to measure amplitude 6759. Receipt 20250331 17:12:34

 

Attachment 1: Screenshot_from_2025-03-31_18-06-59.png
Screenshot_from_2025-03-31_18-06-59.png
Attachment 2: Screenshot_from_2025-03-31_17-52-04.png
Screenshot_from_2025-03-31_17-52-04.png
Attachment 3: Screenshot_from_2025-03-31_17-14-56.png
Screenshot_from_2025-03-31_17-14-56.png
Attachment 4: 2025-03-31_10_40_04_li_dg_sst_01-ccd_01_RAW.png
2025-03-31_10_40_04_li_dg_sst_01-ccd_01_RAW.png
  Draft   Tue Apr 1 08:43:53 2025 VM, IC, DNUnder ProcessShift summaryRing Commissioning   

08h42 Start ThomX: Morulator, firg, laser

08h47 Chillers, cycling all magnets

10h40 HV is 'ON'

10h58 RF Gun phase is 225 dg. Correctors H [0.82 -3.05]; V [-3.1 3.28], Sect phase is 220 dg., Att. 0.975 dB, Charges: -95 pC, -94 pC, -103 pC

11h12 Beam in the ring RF cav. at 50 kV, phase -34.5 dg.,  receipt from good 20250331 18:08:02

11h25 Interlock by Radioprotection in the laser room

11h48 Fixed by Atanas, HV is 'ON', RF gun phase is  220 dg., Sect. phase is 224 dg. Linac correctors H [0.82 -3.05]; V [-3.29 3.19],

12h06 emittance measurements by QP3, QP1 and QP2 at zero hor. 3.3 mm*mrad, vert. 2.9 mm*mrad

12h19 beam in the ring TL/BPM2 X=0 mm

13h20 Going to 40 MeV. Sect. Att. set to 4.095 dB, Sect. phase is 205 dg. TL/DP current set to 125.38 A, Linac steerers H [1.19 -3.25], V [-3.05 3.47]

RF cavity 50 kV, Freq=500.11896 MHz

16h42 RF cav. at 100 kV, Phase -7.5 dg. receipt 20250401 _15_25_35, RF Gun phase 219 dg. Sect. phase 201 dg. Att. 4.084 dB, TL/BPM2 X=4.5 mùm

17h16 Stop ThomX

Freq. for RF Cav. set to 500.10051 MHz (should be 500.10045 MHz)

  1058   Thu Apr 17 08:16:04 2025 VM, RC, DN, NDUnder ProcessShift summaryRing Commissioning   

08h15 Start Thomx: modulator, frig, laser

08h21 Chillers started, all magnets cycling

Filesystem very slow

Allarm vacuum valve are in alarm

RAC.17-RDP.01 still faulty

09h38 HV is 'ON'

10:15 Calc DS for attenuators was crashed. It restarted at 0dB attenuation...

12:43 SR on target with Iris closed

Alignemnt...

17:30 Measurement of the bunch length in the ring  ~140ps

Attachment 1: health_check_Vide_Jauge_2025_04_17_09_25.png
health_check_Vide_Jauge_2025_04_17_09_25.png
Attachment 2: health_check_RF_Redpitaya_2025_04_17_09_27.png
health_check_RF_Redpitaya_2025_04_17_09_27.png
Attachment 3: bpm_1_vs_kicker_second.png
bpm_1_vs_kicker_second.png
Attachment 4: viewer_2025_04_17_12_44_06.png
viewer_2025_04_17_12_44_06.png
Attachment 5: 20250417_175615.jpg
20250417_175615.jpg
  Draft   Fri May 2 08:23:50 2025 VMUnder ProcessShift summaryRing Commissioning   

08h22 ThomX was started: modulator, frig, laser

08h28 Chillers was started, all magnets cycling

09h45 HV is 'ON'

There was a problem with the section phase shifter motor. It was fixed by moving the motor a lot.

11h11 RF Gun phase is 149.6 dg., Sect. phase is 207 dg., Att. is 2.77 dB. TL/BPM2 X=0.9 mm. Linac steerers: H [0.54 -2.76], V [-2.29 2.61], -36 pC, -36 pC, -39 pC, RF cav. at 50 kV, phase 21.0 dg. TbTSum in the ring about 2e7

13h0.5 TL optics was set to MADX simulated one. After adjusting the DPI and the septum, charge in the ring and X ray flux did not change. (receipt 20250502_13_04) RF Cav. at 150kV, phase 13.5 dg

13h20 dispersion measurement in the TL

15h38 New lattice loaded, injection was adjusted as well as the ring elements a little bit.

17h00 ThomX was stopped

  Draft   Fri May 16 08:21:36 2025 VM, IC, DN Under ProcessShift summaryRing Commissioning   

08h20 ThomX was started: Modulator, frig, laser

08h27 Chillers were started, cycling all magnets

10h50 HV is 'ON'

12h38 RF Gun phase is 209 dg. Sect. phase is 207 dg. Charge from the RF gun is -70 pC. Laser Att. 260. 

The strange behavior of the ICT signals does not allow for phase charge scanning.

Laser Att.      Gun Charge pC

260                -70

270               -102

280               -157

290               -255

300              -320

310             -370

320             -400

400             -470

The receipt for MRSV --> for -440 pC Isol=240, adjasted phases (RF Gun 201 dg., Sect. 205 dg.).  RF Cav. at 150 kV, Phase 16 dg., More or less good storage. ri-c1/BPM.03- Lib.03 TbTSum 1.8e8

-58 pC -->ri-c1/BPM.03- Lib.03 TbTSum 4e7

Scaling of the charge, very roughly:

In the injector, the charge measured by BPM after the e- gun 440 pC/58 pC ~7.6

In the ring, the TbTSum @2000turns 1.8e8/4e7 ~4.5

So, the difference is 1.6. This can be explained: beam losses in the ring during the injection, transport efficiency from the gun to the ring

14h40 HV was off. Access to the bunker

14h56 HV is 'ON'

15h12 HV was off. Access to the bunker

15h20 HV is 'ON'

15h17 Series of breakdowns in the RF Gun without interlocking

15h31 HV was off. Access to the bunker

15h42 HV is 'ON', RF Cavity interlock, fixed . There is no image. MRSV camera needs to be checked

16h04 HV was off. Access to the bunker

Problem with the camera was fixed

16h27 HV is 'ON', Charges: -424 pC, -420 pC, -461 pC

16h39 RF Gun phase set to 203 dg. sect. phase 203 dg. HV was off. Access to the bunker

16h50 HV is 'ON'.  Charges: -423 pC, -420 pC, -461 pC, ri-c1/BPM.03- Lib.03 TbTSum 2e8

17h04 HV was off. Access to the bunker

17h13 HV is 'ON'. 

17h24 HV was off. Access to the bunker

17h41 HV is 'ON'. 

17h52 ThomX was stopped

  Draft   Tue May 27 08:34:42 2025 VM, ICUnder ProcessShift summaryRing Commissioning   

Goal: Beam Loss Monitors and Ring injection at high charge. Studies of the injector for high charge. Emittance measurements.

08h33 ThomX was started: modulator,frig, laser

08h40 Chilers were started, all magnets cycling

11h05 HV is 'ON'

11h15 RF Gun phase 194 dg. laser att. 280, Gun charge -100 pC.  Breakdowns in the RF gun

12h14 Breakdowns in the RF gun. Vacuum interlocks. Drop HV to 1210.

12h30 Restore HV

Increase of the charge from 100 pc to 450 pC. Tuning of the injector and ring injection. We suceeed to minilize the injection losses for the high chege. After our studies,  the charge in the ring incresed proportinally to the charge in the linac measured with the BPM.

The recettes were saved in the folder REFERENCES

50MeV_450pC_BLMRCDS_Ratio1_20250527_15_12_22 (best storage with min losses)

15h50 RF gun phase 190 dg., Sect. phase 206 dg., sect. Att. 2.61 dB, Laser Att. 420, Charges (BPMs): -451 pC, -451 pC, 437 pC, Sum(TBTSum = 5.4e11). Receipt: 50MeV_450pC_BLMRCDS_Ratio1_20250527_15_12_22

Emittanse mesurement with QP3 (Isol=235 A)

beta x = 5.0264 alpha x = -1.5425 Horizontal normalized emittance 11.6 mm*mrad

beta y = 7.8251 alpha y = -3.0341, Vertical normalized emittance 7.9 mm*mrad

16h35 RF gun phase 184 dg., Sect. phase 204 dg., sect. Att. 2.69 dB, Laser Att. 303, Charges (BPMs): -219 pC, -216 pC, 240 pC, Sum(TBTSum = 3e11). Receipt: 50MeV_450pC_BLMRCDS_Ratio1_20250527_15_12_22

Emittanse mesurement with QP3 (Isol=235 A)

beta x = 51.2017 alpha x = -15.6429, Horizontal normalized emittance 1.1 mm*mrad

beta y = 5.7487 alpha y = -2.2848, Vertical normalized emittance 4.5 mm*mrad

 

Attachment 1: EmittanceQP3ScanY.png
EmittanceQP3ScanY.png
Attachment 2: EmittanceQP3ScanX.png
EmittanceQP3ScanX.png
Attachment 3: QP3ScanXY.png
QP3ScanXY.png
Attachment 4: EmittanceQP3ScanY220pC.png
EmittanceQP3ScanY220pC.png
Attachment 5: EmittanceQP3ScanX220pC.png
EmittanceQP3ScanX220pC.png
Attachment 6: QP3ScanXY220pC.png
QP3ScanXY220pC.png
Attachment 7: Screenshot_from_2025-05-27_12-58-38.png
Screenshot_from_2025-05-27_12-58-38.png
Attachment 8: Screenshot_from_2025-05-27_15-15-52.png
Screenshot_from_2025-05-27_15-15-52.png
Attachment 9: Screenshot_from_2025-05-27_15-39-58.png
Screenshot_from_2025-05-27_15-39-58.png
ELOG V3.1.4-395e101