Message ID: 970     Entry time: Thu Nov 28 08:19:05 2024
 Author: VM, IC, VK  
 Status: Under Process 
 Type: Info 
 Category: Ring Commissioning 
 Important:
 Subject:  
 Icon:  

08h18 Start ThomX

10h00 HV is 'ON'

10h35 RF Gun phase is 174 dg. Section Phase is  209 dg. Sect. Att. is 2.70 dB TL/BPM2 X=0, Charge is -127 pC

Linac steerers H [2.66 -4.46], V [-2.00 2.41]

10h40 Start Ring RF 100 kV, TL/BPM2 X=0,5 mm

Ring Studies

12h30 Stop HV and ring RF

12h40 Access: JN went to exchange the shunt resistors

13h26 HV iand ring RF are 'ON'

15h18 RF Gun phasee is 178 dg., Sect. phase is 215 dg.

18h10 Stop ThomX

 

 