  990   Thu Jan 9 08:35:10 2025 IC, VK, VM, NDUnder ProcessShift summaryRing   08h35 Start ThomX: Modulator, Frigo, All
magnets.

08h40 Cicling all magnets, Start
 15x 
  993   Fri Jan 10 08:24:25 2025 IC, VK, VM, NDUnder ProcessShift summaryRing Commissioning   08h25 Start ThomX: Modulator, Frigo, cycling
all magnets

08h30 Start chillers
 10x 
  997   Thu Jan 16 08:28:07 2025 VM, IC, VKUnder ProcessShift summaryRing Commissioning   08h25 Start ThomX: Modulator, frigo

08h35 Start chilers, laser, cycling
all magnets
 10x 
  999   Fri Jan 17 08:44:09 2025 MV, IC, VKUnder ProcessShift summaryRing Commissioning   08h43 Start ThomX: Modulator, frigo, laser,
cycling all magnets

08h50 Chillers started
 16x 
  1002   Wed Jan 22 13:32:43 2025 MJ HGFixedShift summaryTL | LE | Ring | Linac Commissionning   ** Alignement Q1Q3 du jour

str1H
0.69
 Q_vs_SolenoScan_at_17-21-28.png 
  Draft   Thu Jan 23 08:44:17 2025 MV, IC, VK, RCUnder ProcessShift summaryRing Commissioning   08h41 Start Thomx: Modulator, Frigo, Laser

08h46 Start chillers, all magnets
sycling
  
  1005   Fri Jan 24 08:45:26 2025 MV, IC, VK, RCUnder ProcessShift summaryRing Commissioning   08h45 Start Thomx: Modulator, frigo, laser

08h50 Start chillers, cycling all
magnets
  
  1006   Fri Jan 24 17:39:00 2025 MV, IC, VK, RCUnder ProcessShift summaryRing Commissioning   08h45 Start Thomx: Modulator, frigo, laser

08h50 Start chillers, cycling all
magnets
 Screenshot_from_2025-01-24_17-35-38_61p5MeV.pngScreenshot_from_2025-01-24_17-34-48_61p5MeV.pngScreenshot_from_2025-01-24_17-34-23_61p5MeV.png 
  Draft   Fri Feb 14 08:21:26 2025 Entered by Super Team from 134.158.195.141 on Fri Feb 14 08:21:09 2025Under ProcessShift summaryRing Commissioning   08h20 Start ThomX: modulator, laser, fridge,cycling
all magnets

08h25 chillers are started
  
  1014   Wed Feb 19 08:28:11 2025 Entered by Super Team from 134.158.195.141 on Wed Feb 19 08:27:57 2025Under ProcessShift summaryRing Commissioning   08h26 Start ThomX: Modulator, Fridge, Laser

08h32 Chillers were started, cycling
all magnets
  
  1016   Thu Feb 20 08:25:11 2025 Entered by Super Team from 134.158.195.141 on Thu Feb 20 08:24:55 2025Under ProcessShift summaryRing Commissioning   08h25 Start ThomX; Start ThomX: Modulator,
Fridge, Laser

08h32 Chillers were started, cycling
 6x 
  1028   Wed Mar 5 08:53:34 2025 VM, VC, RC, DNUnder ProcessShift summaryRing Commissioning   08h53 Start ThomX

11h10 The oscilloscope installed
in the bunker
 16x 
  1032   Tue Mar 11 14:31:06 2025 VMUnder ProcessShift summaryLinac Commissionning   14h31 Start ThomX/ Modulator, Frig, Laser

14h37 Cycling all magnets, Chillers
started
 9x 
  Draft   Thu Mar 13 08:29:34 2025 VM, VC, RC, ICUnder ProcessShift summaryRing Commissioning   08h27 Start ThomX: Modulator, Laser, Frig

08h34 Chillers were started, cycling
al magnets
 12x 
  1048   Mon Mar 31 09:53:26 2025 VM, IC, RCUnder ProcessShift summaryRing Commissioning   08h00 ThomX started by Maher

09h50 Problem with vacuum in the
septum. TL-V3 and EL-V1 are closed.
 Screenshot_from_2025-03-31_18-06-59.pngScreenshot_from_2025-03-31_17-52-04.pngScreenshot_from_2025-03-31_17-14-56.png2025-03-31_10_40_04_li_dg_sst_01-ccd_01_RAW.png 
  Draft   Tue Apr 1 08:43:53 2025 VM, IC, DNUnder ProcessShift summaryRing Commissioning   08h42 Start ThomX: Morulator, firg, laser

08h47 Chillers, cycling all magnets

10h40 HV is 'ON'
  
  1058   Thu Apr 17 08:16:04 2025 VM, RC, DN, NDUnder ProcessShift summaryRing Commissioning   08h15 Start Thomx: modulator, frig, laser

08h21 Chillers started, all magnets
cycling
 health_check_Vide_Jauge_2025_04_17_09_25.pnghealth_check_RF_Redpitaya_2025_04_17_09_27.pngbpm_1_vs_kicker_second.pngviewer_2025_04_17_12_44_06.png20250417_175615.jpg 
  Draft   Fri May 2 08:23:50 2025 VMUnder ProcessShift summaryRing Commissioning   08h22 ThomX was started: modulator, frig,
laser

08h28 Chillers was started, all
  
  Draft   Fri May 16 08:21:36 2025 VM, IC, DN Under ProcessShift summaryRing Commissioning   08h20 ThomX was started: Modulator, frig,
laser

08h27 Chillers were started, cycling
  
  Draft   Tue May 27 08:34:42 2025 VM, ICUnder ProcessShift summaryRing Commissioning   Goal:
Beam Loss Monitors and Ring injection at
high charge. Studies of the injector for
 9x 