ID Date Author Status Type Categorydown Important Subject Icon Text Attachments
  1087   Wed Jun 11 08:46:58 2025 Entered by Marie Jacquet from 134.158.205.17 on Wed Jun 11 08:46:44 2025 Shift summaryLI | Ring 2025-06-04 Fluo-spectro : Spectre du 2025-06-04    spectres_20250604.pdf 
  1066   Mon May 12 07:58:58 2025 Entered by Kevin Dupraz from 109.222.35.58 on Mon May 12 07:58:41 2025Under ProcessShift summaryLI | RF D1 | Vide | Linac Commissionning shift du 12 mai 2025 : conditionnement GUN 8h: mise en chauffe modulateur et frigo/chiller

- problème de lecture de
vide (visible sur toute les jauges LINAC)
 Screenshot_from_2025-05-12_08-02-15_vacuum_problem.pngScreenshot_from_2025-05-12_14-36-54.png 
  880   Thu Jun 27 16:14:38 2024 Entered by Super Team from 134.158.195.141 on Thu Jun 27 16:14:24 2024 LinacLI | RF D1 Tests reseau RF Charge en sortie diviseur cote section

HT = 1220V (35MW), 10Hz , 3us

Attenuateur cote canon 30 dB
 test_sur_charge_config.1.pptx 
  881   Fri Jun 28 14:37:19 2024 Entered by Super Team from 134.158.195.141 on Fri Jun 28 14:37:07 2024 LinacLI | RF D1 Tests reseau RF : branche attenuateur charge en position après atténuateur,
10Hz, 3us, 1220V

Ca claque à 15dB et 10dB,
 test_sur_charge_config.2.pptx 
  893   Tue Jul 30 10:17:06 2024 M.O, M ELK, Hayg, SlavaUnder ProcessShift summaryLI | RF D1 Conditionnement section SC/ME/MO/VK/HG  signaux RF mesurés :

avec Oscillo :

orange
 Vide_Screenshot_2024-07-30_17-13-24.png 
  897   Mon Aug 5 10:50:06 2024 Entered by Super Team from 134.158.195.141 on Mon Aug 5 10:49:42 2024 LinacLI | RF D1 Suite conditionnement section 10h50 Mise en route à 10dB, HT =
1000V

11h04 HT = 1215V, Att sec 3 dB
  
  898   Tue Aug 6 09:57:48 2024 Entered by Super Team from 134.158.195.142 on Tue Aug 6 09:57:28 2024 LinacLI | RF D1 Commissioning section accélératrice 9h58 Démarrage Att sec 10dB 3us
25Hz HT = 1200V

On augmente progressivement la
  
  899   Thu Aug 8 10:12:35 2024 Entered by Super Team from 134.158.195.142 on Thu Aug 8 10:12:02 2024 LinacLI | RF D1 conditionnement section Remplissage SF6 de 2.3 bar à 2.5
bar par Christopher

10h08 : augmentation progressive
  
  900   Fri Aug 9 10:01:23 2024 Entered by Super Team from 134.158.195.142 on Fri Aug 9 10:01:08 2024 LinacLI | RF D1 conditionnement section Vide de démarrage apres l'allumage
des chillers : in section 6.4e-10 et out
section 8.3e-10
  
  1044   Fri Mar 21 08:37:09 2025 VMNot FixedProblemLI | RF D1 Modulador problem 08h38 There is problem with the Linac modulator

08h55 Fixed with Maher help
  
  1190   Tue Feb 10 18:34:33 2026 Entered by Super Team from 127.0.0.1 on Tue Feb 10 18:34:13 2026Under ProcessShift summaryLI | RF D1 Demarrage Linac icon1.gif Mesures après remontage de la cale
: 1215 V sur le modulateur.
ça tient mais
  
  782   Tue Jul 4 08:56:04 2023 SC/CB/ME LinacLI | RF Anneau | Linac Commissionning Faisceau linac et cavite RF 8h55 Démarrage modulateur et refroidissements

Intervention SPR terminé

Solenoide = 190A, pas de quadrupoles,
  
  Draft   Wed Jun 3 08:54:55 2026 IC, VMUnder ProcessUrgentLI | RF Anneau Restart of the accelerator 08h45 Start-up modulator, laser, magnets

09h38 Shutter Laser Linac is yellow.
Tuning off the gun operation key does not
 GunCharge_vs_LaserAtt.pngGunDarkCurrent_vs_Att.png 
  1069   Wed May 14 08:07:26 2025 KD, HGUnder ProcessShift summaryLI | Opt | Linac Commissionning shift du 14 mai 2025 8h: mise en chauffe à distance (modulateur,
frigo/chiller, laser)

10h30: on a du faisceau atténuateur
 9x 
  995   Tue Jan 14 10:42:56 2025 KDNew SolutionInfoLI | Opt alignement laser PhotoCathode Mesure de ce matin et changement point
cathode [H,V] = [4.29,3.49]:

sortie laser : 275 - 280uJ
  
  1055   Fri Apr 11 08:52:07 2025 VC SC HGUnder ProcessShift summaryLI | Linac Commissionning | Ring Commissioning shift du 11 avril  demarrage chauffage 8hh50

faisceau sur Yag 1 depuis 1heure....

le script d'alignement solenoide
 align_soir.png 
  566   Mon Sep 26 16:30:56 2022 Vincent ChaumatUnder ProcessLinacLI | Linac Commissionning Mesure puissance Canon et section Mesure de la puissance dans la bouble (cristal
+ redpitaya)

mesure sur les 20 derniers points
 pBoucle.pngPisection.png 
  567   Tue Sep 27 08:40:33 2022 VC SC CBUnder ProcessShift summaryLI | Linac Commissionning Shift du jour Summary:

- Mesure du jitter et de la position
relative de pulse laser PC avec la RF canon
  
  636   Wed Nov 30 11:44:22 2022 HG/CB/KDUnder ProcessLinacLI | Linac Commissionning Twiss = F(Solé) Phase de Q max : 195, on decale de -50
degrés

IRIS :0.7 mm, att  400, charge
  
  642   Wed Dec 7 09:07:27 2022 KDUnder ProcessShift summaryLI | Linac Commissionning shift du 7 decembre 2022 9h : Mise en chauffe 
ajout d'eau dans la boucle principale
(3 bars --> 4bars)
  