Message ID: 899     Entry time: Thu Aug 8 10:12:35 2024
 Author: Entered by Super Team from 134.158.195.142 on Thu Aug 8 10:12:02 2024 
 Status:  
 Type: Linac 
 Category: LI | RF D1 
 Important:
 Subject: conditionnement section 
 Icon:  

Remplissage SF6 de 2.3 bar à 2.5 bar par Christopher

10h08 : augmentation progressive de la HT

10h13 : Att sec 10 dB

On descend progressivement jusqu'à 1dB

10h25 Att sec 1 dB

10h26 Att sec 0.9 dB vide in section = 6.9e-9   vide out section = 1.3e-9

10h30 Att sec 0.8 dB vide in section =  7.4e-9 vide out section = 2.5e-9

10h34 Att sec 0.7 dB vide in section = 7.6e-9  vide out section = 3.7e-9

10h38 Att sec 0.6 dB vide in section =  7.5e-9 vide out section = 4.3e-9

10h42 Att sec 0.5 dB vide in section =  7.1e-9 vide out section = 4.5e-9

10h46 Att sec 0.4 dB vide in section =  6.7e-9 vide out section = 4.6e-9

10h55 Att sec 0.3 dB vide in section =  5.6e-9 vide out section = 6.2e-9

13h58 Att sec 0.2 dB  vide in section =  4.9e-9 vide out section = 5.5e-9

14h20 Intervention LE dans la casemate

15h25 FIn d'intervention, reprise conditionnement

18h fin

 

 