Message ID: 898     Entry time: Tue Aug 6 09:57:48 2024
 Author: Entered by Super Team from 134.158.195.142 on Tue Aug 6 09:57:28 2024 
 Status:  
 Type: Linac 
 Category: LI | RF D1 
 Important:
 Subject: Commissioning section accélératrice 
 Icon:  

9h58 Démarrage Att sec 10dB 3us 25Hz HT = 1200V

On augmente progressivement la HT

10h03 HT = 1215V att sec 10dB

10h04 On descend progressivement de 10dB à 1dB

10h28 passage à 1 dB vide in section = 6.9e-9  vide out section = 1.5e-9

10h33 passage à 0.9 dB vide in section = 7.5e-9  vide out section = 2.6e-9

10h36 passage à 0.8 dB vide in section = 8e-9  vide out section = 3.8e-9

10h40 passage à 0.7 dB vide in section = 8e-9  vide out section = 4.8e-9

10h44 passage à 0.6 dB vide in section = 7.7e-9  vide out section = 5.2e-9

10h47 passage à 0.5 dB vide in section = 7.4e-9  vide out section = 5.5e-9

10h55 passage à 0.4 dB

13h50 interlock à 0.4dB

13h53 interlock à 0.4dB

13h56 interlock à 0.4dB

Pause

14h42 reprise à 0.4dB

15h42 Interlock machine

18:40 FIN 

 

 

 

 

 

 