ID |
Date |
Author |
Status |
Type |
Category |
Important |
Subject |
Icon |
|
39
|
Mon Dec 5 10:05:11 2022 |
VK, IC, VM, JH, KD, ND | New Solution | Info | analyse |
|
Summary of the ring commissioning meeting | |
The ring orbit has been re-established despite some difficulties after the shutdown.
The ring cavity has been started. Whatever the phase it kills the beam.
Two hypothesis:
1) It can be a frequency problem
2) It can be a transverse kick given by the cavity
About 1:
- Magnet current and frequency have been scanned but no effect.
About 2:
- We see betatron oscillation.
We see the beam lost by steps, not a continuous decrease.
https://elog.lal.in2p3.fr/THOMX/Commissionning/221202_190728/Screenshot_from_2022-12-02_18-02-36.png shows betatron oscillation with cavity tuned.
Next steps:
- Mesure FFT of BPM signal (VM, VC)
- "Open the ring" (kick the beam out of the ring) and study the effect of the cavity (phase, power) on the BPMs. (VK, IC)
- Scan betatron oscillation vs phase, orbit, power and frequency
- Slava: To catch the beam you should think like a beam.
Actions:
- Try to get remote control of RF synthetizer (ND)
|
|
38
|
Mon Nov 7 23:53:29 2022 |
VK, IC, VM, JH, ND | New Solution | Info | resumes |
|
Summary of the ring commissioning meeting | |
Discussed recent orbit correction of the expanded orbit.
Need to make run with cavity detuning from its resonant conditions used in the conditioning.
Discussed measurement of tune, and possible origins of inconsistant/noisy measurements. Either BPMs signal processing or weak excitation. Beam size?
Need to do measurements with scope, to see if we can interpret TbT data in post-processing. Will ask Vincent to help with scope and measurements.
Need of RF cavity operation to continue ring commissioning.
|
|
37
|
Mon Oct 17 10:02:07 2022 |
VK, IC, VI, JH, SC, ND | Reference Solution | Info | resumes |
|
Summary of the ring commissioning meeting #5 | |
See slides attached to the indico page https://indico.ijclab.in2p3.fr/event/8885/
Pb with BPM => visual check of electrodes + hardware swap
Pb with steerer => Need to identify who will do the intervention and when
Nicolas will ask Kevin for support.
Suggestion: Since the magnetic field stability of the bending magnet which is being used to measure the beam energy is still questioned, it is suggested to wind a wire into a small, flat, electric coil and to place it in the magnet gap or close to it so that the field crosses orthogonally the coil plane, and to monitor the voltage across the coil with an oscilloscope (the e- beam being turned off and the bending magnet being powered, of course). Some dimensional calculation would be needed.
Alignement: Slava got the data from Denis. Alignment is close from nominal values.
The beam quality is good enough to start working with the RF cavity. Even with low power in RF cavity we would like to have a first control of voltage and phase from the control room (Thursday or Friday afternoon).
Some energy instabilities have been observed. Look at correlations (Vincent's measurements) + check that the current operating phase is optimal.
=> Check if position fluctuations are the same with one steerer on, TL/DP/PS.01 off + TL/SST1 and steerer off, TL/DP/PS.01 on + TL/SST2.
Optimum injection trajectory has been recorded on Friday.
Next meeting: 7th Novembre
|
|
36
|
Mon Oct 10 10:37:43 2022 |
IC, VK, VI, VC, JH, HG, ND | New Solution | Shift summary | Prise de donnees |
|
RE: RE: RE: Ring objectives | |
To do list:
(0) Re-establish beam transport to ring
(0bis) Check energy jitter in TL/BPM.02 and TL/SST.02
(0ter) Measure emittance on TL/SST.03
(1) Try to merge TL optimised transport with ring injection transport => record beam size on TL/SST3 and position on TL/BPM.03 and TL/BPM.04 for current ring transport
définir avec précision les caractéristiques du faisceau en fin de TL pour pouvoir passer au commissioning de l'anneau (et fournir les diagnostics nécessaires pour contrôler ces "bons" réglages de la TL, et savoir qui en est en charge de quoi)
(2) Improve charge transport at injection
(3) Measure and correct orbits
programmer des mesures sur l'anneau permettant d'établir des connexions entre le modèle d'Iryna et l'état actuel de l'anneau (il y a évidemment la mesure des nombres d'ondes
(4) Start MRSV
(5) Measure Tune
| Quote: |
|
New to do list:
(0) Re-establish beam transport to ring
(0bis) Check energy jitter in TL/BPM.02 and TL/SST.02
(1) Try to merge TL optimised transport with ring injection transport => record beam size on TL/SST3 and position on TL/BPM.03 and TL/BPM.04 for current ring transport
(2) Reduce betatron oscillations
(3) Measure and correct orbits
(4) Measure Tune
(5) BBA
(6) Improve charge transport at injection
(7) Start MRSV
| Quote: |
|
(1), (2), (4) and (5) from last week have been done other items in progress.
New to do list:
(0) Re-establish beam transport to ring
(1) Monitor incident power on RF Gun
(2) Check energy jitter in TL/BPM.02 and TL/SST.02
(3) Use TL optimised transport when available
(4) Compare single pass and TbT BPM signals
(5) Test Alexandre's feedback code.
(6) Scan correctors to increase current on RI-C1/BPM.01 and RI-C2/BPM.06
(7) Start align beam in quadrupoles
| Quote: |
|
This entry is to be updated as the work progresses.
1) Re-establish beam transport to ring
2) Scan in time the septum
see script git/panneaux/Synchro/scan_septum.py
3) Scan in voltage the septum
4) Adjust timing of kicker by looking at induced noise on ICTs
5) Scan in time the kicker
git/panneaux/Synchro/scan_kicker.py
6) Scan in voltage the kicker
7) Transport further in the ring by playing with correctors
Note: When possible Alexandre will test his feedback code.
|
|
|
|
|
35
|
Mon Oct 10 10:04:49 2022 |
VK, IC, VI, JH, ND | Under Process | Shift summary | resumes |
|
Summary of the ring commissioning meeting #4 | |
- 300 turns achieved.
- Probably more but limited by libera cut-off frequency.
- Need to measure the injection axis
- Need emittance measurement from the transfer line
- Several measurements are not possible because of lack of progress on the transfer line
|
|
34
|
Wed Oct 5 09:51:12 2022 |
IC, VK, VI, VC, JH, HG, ND | New Solution | Shift summary | Prise de donnees |
|
RE: RE: Ring objectives | |
New to do list:
(0) Re-establish beam transport to ring
(0bis) Check energy jitter in TL/BPM.02 and TL/SST.02
(1) Try to merge TL optimised transport with ring injection transport => record beam size on TL/SST3 and position on TL/BPM.03 and TL/BPM.04 for current ring transport
(2) Reduce betatron oscillations
(3) Measure and correct orbits
(4) Measure Tune
(5) BBA
(6) Improve charge transport at injection
(7) Start MRSV
| Quote: |
|
(1), (2), (4) and (5) from last week have been done other items in progress.
New to do list:
(0) Re-establish beam transport to ring
(1) Monitor incident power on RF Gun
(2) Check energy jitter in TL/BPM.02 and TL/SST.02
(3) Use TL optimised transport when available
(4) Compare single pass and TbT BPM signals
(5) Test Alexandre's feedback code.
(6) Scan correctors to increase current on RI-C1/BPM.01 and RI-C2/BPM.06
(7) Start align beam in quadrupoles
| Quote: |
|
This entry is to be updated as the work progresses.
1) Re-establish beam transport to ring
2) Scan in time the septum
see script git/panneaux/Synchro/scan_septum.py
3) Scan in voltage the septum
4) Adjust timing of kicker by looking at induced noise on ICTs
5) Scan in time the kicker
git/panneaux/Synchro/scan_kicker.py
6) Scan in voltage the kicker
7) Transport further in the ring by playing with correctors
Note: When possible Alexandre will test his feedback code.
|
|
|
|
33
|
Mon Oct 3 17:29:53 2022 |
IC, VK, VI (ND) | New Solution | Info | resumes |
|
Summary of the ring commissioning meeting #3 | |
Shift summaries for the ring for last week are at
https://elog.lal.in2p3.fr/THOMX/Commissionning/568
https://elog.lal.in2p3.fr/THOMX/Commissionning/570
https://elog.lal.in2p3.fr/THOMX/Commissionning/571
The problem with the pulse jumpis with 12ns delays has been identified and fixed (it was related to the synchronisation system).
The main issue identified last week is a problem with RI-C2/PS/QP.09, RI-C2/PS/QP.10 and RI-C2/PS/QP.12 which has been addressed after the meeting (see https://elog.lal.in2p3.fr/THOMX/Commissionning/572).
It is important that the laser energy and linac beam charge are checked and optimised every week. |
|
32
|
Wed Sep 28 09:56:44 2022 |
ND, IC | Reference Solution | Info | docs |
|
Steerers and BPM map for the ring | |
See attached files. |
| Attachment 1: BPM_ring.png
|
 |
| Attachment 2: BPM_ring.pptx
|
|
31
|
Tue Sep 27 17:45:54 2022 |
ND | Under Process | Info | docs |
|
RE: Beam requirements for the ring | |
An IHM to check some of these parameters has been created (git/panneaux/StatusInfoIHM_ring_vars.py) and added to Plateforme_IHM...
| Quote: |
|
The following parameters are required for ring operations:
- At least 80pC on TL/DG/ICT.01 with std <20pC
- At least 20pC on TL/DG/ICT.02 with std <20pC
- Energy in the TL must be checked and must be 50 MeV => TL/BPM.02 SpX, SpY <1mm with Std(SpX, SpY) <1mm with nominal value for TL/PS/DP.01
- Beam position must be checked on TL/DG/SST.01, TL/DG/SST.02 and TL/DG/SST.03 and be within the acceptance (see tickbox acceptance on IHM_SST).
- Beam size must be measured on TL/DG/SST.03 and be < 2mm FWHM
- Beam recipes for the LI and for the TL must be saved.
- Health check must be checked (no red entry).
- Beam centered on the last quadrupole of the transfer line.
This list will evolve as we progress in the ring commissioning.
|
|
|
30
|
Mon Sep 26 10:21:20 2022 |
IC, VK, VI, VC, JH, HG, ND | New Solution | Shift summary | Prise de donnees |
|
RE: Ring objectives | |
(1), (2), (4) and (5) from last week have been done other items in progress.
New to do list:
(0) Re-establish beam transport to ring
(1) Monitor incident power on RF Gun
(2) Check energy jitter in TL/BPM.02 and TL/SST.02
(3) Use TL optimised transport when available
(4) Compare single pass and TbT BPM signals
(5) Test Alexandre's feedback code.
(6) Scan correctors to increase current on RI-C1/BPM.01 and RI-C2/BPM.06
(7) Start align beam in quadrupoles
| Quote: |
|
This entry is to be updated as the work progresses.
1) Re-establish beam transport to ring
2) Scan in time the septum
see script git/panneaux/Synchro/scan_septum.py
3) Scan in voltage the septum
4) Adjust timing of kicker by looking at induced noise on ICTs
5) Scan in time the kicker
git/panneaux/Synchro/scan_kicker.py
6) Scan in voltage the kicker
7) Transport further in the ring by playing with correctors
Note: When possible Alexandre will test his feedback code.
|
|
|
29
|
Mon Sep 26 09:39:15 2022 |
VK, IC, AM, ND | New Solution | Info | Prise de donnees |
|
Summary of the ring commissioning meeting #2 | |
Slides are at https://indico.ijclab.in2p3.fr/event/8750/
- There is a difference in BPM numbering in Tango and MML => we should stick to Tango names.
- Beam was very unstable during the past week
- Difficulties to have full current on RI-C1/BPM.01. Signal drops already significanty before RI-C2/BPM.06
- Fluctuations may have been observed on the RF Gun power => to be confirmed
- Fluctuations have been observed on the kicker => may be due to energy jitter
To do:
- Monitor incident power on RF Gun
- Re-establish transport
- Try to inject with optimised TL transport
- Compare single pass and TbT BPM signals
- Check energy jitter in TL/BPM.02 and TL/SST.02
- Scan correctors to increase current on RI-C1/BPM.01 and RI-C2/BPM.06
- Start align beam in quadrupoles |
|
28
|
Fri Sep 23 09:44:14 2022 |
IC, VK, AM, VC, ND | Under Process | Info | docs |
|
Beam requirements for the ring | |
The following parameters are required for ring operations:
- At least 50pC on TL/DG/ICT.01 with std <20pC
- At least 20pC on TL/DG/ICT.02 with std <20pC
- Energy in the TL must be checked and must be 50 MeV => TL/BPM.02 SpX, SpY <1mm with Std(SpX, SpY) <1mm with nominal value for TL/PS/DP.01
- Beam position must be checked on TL/DG/SST.01, TL/DG/SST.02 and TL/DG/SST.03 and be within the acceptance (see tickbox acceptance on IHM_SST).
- Beam size must be measured on TL/DG/SST.03 and be < 2mm FWHM
- Beam recipes for the LI and for the TL must be saved.
- Health check must be checked (no red entry).
- Beam centered on the last quadrupoles of the transfer line.
This list will evolve as we progress in the ring commissioning.
|
|
27
|
Mon Sep 19 16:29:06 2022 |
IC, VK, VI, VC, JH, HG, ND | New Solution | Shift summary | Prise de donnees |
|
Ring objectives | |
This entry is to be updated as the work progresses.
1) Re-establish beam transport to ring
2) Scan in time the septum
see script git/panneaux/Synchro/scan_septum.py
3) Scan in voltage the septum
4) Adjust timing of kicker by looking at induced noise on ICTs
5) Scan in time the kicker
git/panneaux/Synchro/scan_kicker.py
6) Scan in voltage the kicker
7) Transport further in the ring by playing with correctors
Note: When possible Alexandre will test his feedback code. |
|
26
|
Mon Sep 19 15:56:28 2022 |
IC, VK, VI, VC, JH, HG, ND | New Solution | Info | Prise de donnees |
|
Summary of the ring commissioning meeting #1 | |
Status slides presented by Iryna available on indico at https://indico.ijclab.in2p3.fr/event/8749/
The beam parameters required for a good injection in the ring were discussed.
The following required parameters were identified:
- At least 80pC on TL/DG/ICT.01
- At least 20pC on TL/DG/ICT.02
- Energy in the TL must be checked and must be 50 MeV.
- Beam position must be checked on TL/DG/SST.01, TL/DG/SST.02 and TL/DG/SST.03 and be within the acceptance (see tickbox acceptance on IHM_SST).
- Beam size must be measured on TL/DG/SST.03 and be < 2mm FWHM
- Beam recipes for the LI and for the TL must be saved.
- Health check must be checked (no red entry).
- Beam centered on the last quadrupole of the transfer line.
ACTION: Nicolas will create an interface that displays as many as possible of the required parameters.
Suggestion by Viktor: check phase noise at the gun entrance: there might a phase noise issue.
=> Vincent (VC) is going to do that with Viktor (VI) during RF studies on 26th September
Planning for the coming week:
- Wednesday: Slava (+Iryna after the CoDEC)
- Thursday: Nicolas + all
- Friday: AG Pole. Alexandre and Vincent plus Slava
Current objectives:
1) Re-establish beam transport to ring
2) Scan in time the septum
3) Scan in voltage the septum
4) Adjust timing of kicker by looking at induced noise on ICTs
5) Scan in time the kicker
6) Scan in voltage the kicker
7) Transport further in the ring by playing with correctors
Note: When possible Alexandre will test his feedback code.
|
|
25
|
Fri Sep 2 08:51:46 2022 |
MO | | Shift summary | etc |
|
démarrage | |
8h35 mise sous tension: PSS, LB9000, modulateur, chillers |
|
24
|
Wed Aug 17 11:42:41 2022 |
MO HM | Under Process | Info | Prise de donnees |
|
test RF modulateur longue durée (journée) | |
but : test fonctionnement modulateur et RF sur la journée
8h55 démarrage modulateur et refroidissement
10h00 démarrage RF ( HV=1090V )
visualisation signaux RF avec taurus plot : Pic Prc Pis Prs et photodiode
--> taurus plot er/sy/rac.17-elr.01-rdp.03/waveform_cha er/sy/rac.17-elr.01-rdp.03/waveform_chb er/sy/rac.17-elr.01-rdp.01/waveform_cha er/sy/rac.17-elr.01-rdp.01/waveform er/sy/rac.17-elr.01-rdp.04/waveform_cha er/sy/rac.17-elr.01-rdp.04/waveform_chb
13h00 RF en fonctionnement depuis 10h00 ( pas d'interlocks )
14h00 RF ok - pas d'interlock modulateur
15h00 RF ok - pas d'interlock modulateur
16h00 RF ok - pas d'interlock modulateur
17h00 RF ok - pas d'interlock modulateur
17h15 arret
bilan : aucun interlock modulateur de 10h a 17h, tres peu de claquages , vide bon (1e-9 mbar), regulation temperature canon et section ok.
|
| Attachment 1: Screenshot_from_2022-08-18_15-56-17.png
|
 |
|
23
|
Wed Aug 17 09:48:31 2022 |
HM MO | Under Process | Info | Prise de donnees |
|
redemarrage 17 aout 2022 | |
9h30 redemarrage HM MO
- niveau 1 verifié (circuit eau, air comprimé, etat modulateur et SF6)
- ronde modulateur faite
- lancement IHM
lancement IHM modulateur : pas de reaction
accès à la casemate bloqué car sonde T3G est en défaut, redémarrage du système mesures radioprotection (LB 9000) ==> sonde T3G Ok
- ronde casemate faite
- démarrage modulateur en local
- utilisation de heath check pour redemarrer les servers
- demarrage modulateur HT = 1000 V et refroidissement a distance (sdc)
13h probleme de synchro : pas de synchro sur modulateur - a verifier
--> la notice synchro stipule de démarrer le laser photocathode en mode interne : mise sous tension du laser : ok
- la synchro externe modulateur fonctionne. HT = 1090 V , Frep = 10 Hz.
visualisation de PiC et Prc dans le hall D1 et salle de controle sur oscillo : ok
--> pas trouvé comment visualiser les signaux RF avec interface Taurus
visualisation Pis et Prs
--> sauvegarde signaux RF sur clef usb
bilan : 3h de RF dans la canon et la section LIL, vide correct
test longue durée demain
17h15 arret
|
|
22
|
Fri Mar 4 11:07:28 2022 |
CB/SC | | Problem | problemes |
|
liste des actions à menées | |
|
|
21
|
Thu Mar 4 17:07:32 2021 |
Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 17:07:19 2021 | Under Process | Shift summary | Prise de donnees |
|
Tests IHM RF | |
Les tests se sont bien déroulés, on observe bien les signaux correspondants au redpitayas demandés.
Il faudra faire une modification sur l'IHM car tango bloque par moment et cela "freeze" l'IHM que l'on doit complètement redémarrer. |
|
20
|
Thu Mar 4 16:59:43 2021 |
Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 16:59:30 2021 | Under Process | Shift summary | Prise de donnees |
|
tests redpitaya 4 | |
Tests des redpitaya 4 voie 1 (Photodiode) et voie 2 (Q section) |
| Attachment 1: RDP.04_voie1.png
|
 |
| Attachment 2: RDP.04_voie2.png
|
 |