Entry   IC, VK, VI, VC, JH, HG, ND ; Ring objectives 
    Reply   IC, VK, VI, VC, JH, HG, ND ; RE: Ring objectives 
       Reply   IC, VK, VI, VC, JH, HG, ND ; RE: RE: Ring objectives 
          Reply   IC, VK, VI, VC, JH, HG, ND ; RE: RE: RE: Ring objectives 
Message ID: 27     Entry time: Mon Sep 19 16:29:06 2022     Reply to this: 30
 Author: IC, VK, VI, VC, JH, HG, ND  
 Status: New Solution 
 Type: Shift summary 
 Category: Prise de donnees 
 Important:
 Subject: Ring objectives 
 Icon:  

This entry is to be updated as the work progresses.

1) Re-establish beam transport to ring

2) Scan in time the septum

see script git/panneaux/Synchro/scan_septum.py

3) Scan in voltage the septum

4) Adjust timing of kicker by looking at induced noise on ICTs

5) Scan in time the kicker

git/panneaux/Synchro/scan_kicker.py

6) Scan in voltage the kicker

7) Transport further in the ring by playing with correctors

Note: When possible Alexandre will test his feedback code.

ELOG V3.1.4-395e101