  Notes concernant la preparation du Commissionning  Not logged in ThomX    logo
Entry   IC, VK, AM, VC, ND; Beam requirements for the ring 
    Reply   ND; RE: Beam requirements for the ring 
Message ID: 31     Entry time: Tue Sep 27 17:45:54 2022     In reply to: 28
 Author: ND 
 Status: Under Process 
 Type: Info 
 Category: docs 
 Important:
 Subject: RE: Beam requirements for the ring 
 Icon:  

An IHM to check some of these parameters has been created (git/panneaux/StatusInfoIHM_ring_vars.py) and added to Plateforme_IHM...

Quote:

The following parameters are required for ring operations:

- At least 80pC on TL/DG/ICT.01 with std <20pC

- At least 20pC on TL/DG/ICT.02 with std <20pC

- Energy in the TL must be checked and must be 50 MeV =>  TL/BPM.02 SpX, SpY <1mm  with Std(SpX, SpY) <1mm with nominal value for TL/PS/DP.01

- Beam position must be checked on TL/DG/SST.01, TL/DG/SST.02 and TL/DG/SST.03 and be within the acceptance (see tickbox acceptance on IHM_SST).

- Beam size must be measured on TL/DG/SST.03 and be < 2mm FWHM

- Beam recipes for the LI and for the TL must be saved.

- Health check must be checked (no red entry).

- Beam centered on the last quadrupole of the transfer line.

This list will evolve as we progress in the ring commissioning.

 

 