Shift summaries for the ring for last week are at https://elog.lal.in2p3.fr/THOMX/Commissionning/568 https://elog.lal.in2p3.fr/THOMX/Commissionning/570 https://elog.lal.in2p3.fr/THOMX/Commissionning/571 The problem with the pulse jumpis with 12ns delays has been identified and fixed (it was related to the synchronisation system). The main issue identified last week is a problem with RI-C2/PS/QP.09, RI-C2/PS/QP.10 and RI-C2/PS/QP.12 which has been addressed after the meeting (see https://elog.lal.in2p3.fr/THOMX/Commissionning/572). It is important that the laser energy and linac beam charge are checked and optimised every week.