  Notes concernant la preparation du Commissionning  Not logged in ThomX    logo
Message ID: 38     Entry time: Mon Nov 7 23:53:29 2022
 Author: VK, IC, VM, JH, ND 
 Status: New Solution 
 Type: Info 
 Category: resumes 
 Important:
 Subject: Summary of the ring commissioning meeting 
 Icon:  
Discussed recent orbit correction of the expanded orbit. 
Need to make run with  cavity detuning from its resonant conditions used in the conditioning. 
 
Discussed measurement of tune, and possible origins of inconsistant/noisy measurements.  Either BPMs signal processing or  weak excitation. Beam size?
Need to do measurements with scope, to see if we can interpret TbT data in post-processing. Will ask Vincent to help with scope and measurements.
 
Need of RF cavity operation to continue ring commissioning.
 