| ID |
Date |
Author |
Status |
Type |
Category |
Important |
Subject |
Icon |
Text |
 |
|
990
|
Thu Jan 9 08:35:10 2025 |
IC, VK, VM, ND | Under Process | Shift summary | Ring |
|
| | 08h35 Start ThomX: Modulator, Frigo, All
magnets.
08h40 Cicling all magnets, Start |
15x | |
993
|
Fri Jan 10 08:24:25 2025 |
IC, VK, VM, ND | Under Process | Shift summary | Ring Commissioning |
|
| | 08h25 Start ThomX: Modulator, Frigo, cycling
all magnets
08h30 Start chillers |
10x | |
997
|
Thu Jan 16 08:28:07 2025 |
VM, IC, VK | Under Process | Shift summary | Ring Commissioning |
|
| | 08h25 Start ThomX: Modulator, frigo
08h35 Start chilers, laser, cycling
all magnets |
10x | |
999
|
Fri Jan 17 08:44:09 2025 |
MV, IC, VK | Under Process | Shift summary | Ring Commissioning |
|
| | 08h43 Start ThomX: Modulator, frigo, laser,
cycling all magnets
08h50 Chillers started |
16x | |
1002
|
Wed Jan 22 13:32:43 2025 |
MJ HG | Fixed | Shift summary | TL | LE | Ring | Linac Commissionning |
|
| | ** Alignement Q1Q3 du jour
str1H
0.69 |
| |
Draft
|
Thu Jan 23 08:44:17 2025 |
MV, IC, VK, RC | Under Process | Shift summary | Ring Commissioning |
|
| | 08h41 Start Thomx: Modulator, Frigo, Laser
08h46 Start chillers, all magnets
sycling |
| |
1005
|
Fri Jan 24 08:45:26 2025 |
MV, IC, VK, RC | Under Process | Shift summary | Ring Commissioning |
|
| | 08h45 Start Thomx: Modulator, frigo, laser
08h50 Start chillers, cycling all
magnets |
| |
1006
|
Fri Jan 24 17:39:00 2025 |
MV, IC, VK, RC | Under Process | Shift summary | Ring Commissioning |
|
| | 08h45 Start Thomx: Modulator, frigo, laser
08h50 Start chillers, cycling all
magnets |
  | |
Draft
|
Fri Feb 14 08:21:26 2025 |
Entered by Super Team from 134.158.195.141 on Fri Feb 14 08:21:09 2025 | Under Process | Shift summary | Ring Commissioning |
|
| | 08h20 Start ThomX: modulator, laser, fridge,cycling
all magnets
08h25 chillers are started |
| |
1014
|
Wed Feb 19 08:28:11 2025 |
Entered by Super Team from 134.158.195.141 on Wed Feb 19 08:27:57 2025 | Under Process | Shift summary | Ring Commissioning |
|
| | 08h26 Start ThomX: Modulator, Fridge, Laser
08h32 Chillers were started, cycling
all magnets |
| |
1016
|
Thu Feb 20 08:25:11 2025 |
Entered by Super Team from 134.158.195.141 on Thu Feb 20 08:24:55 2025 | Under Process | Shift summary | Ring Commissioning |
|
| | 08h25 Start ThomX; Start ThomX: Modulator,
Fridge, Laser
08h32 Chillers were started, cycling |
6x | |
1028
|
Wed Mar 5 08:53:34 2025 |
VM, VC, RC, DN | Under Process | Shift summary | Ring Commissioning |
|
| | 08h53 Start ThomX
11h10 The oscilloscope installed
in the bunker |
16x | |
1032
|
Tue Mar 11 14:31:06 2025 |
VM | Under Process | Shift summary | Linac Commissionning |
|
| | 14h31 Start ThomX/ Modulator, Frig, Laser
14h37 Cycling all magnets, Chillers
started |
9x | |
Draft
|
Thu Mar 13 08:29:34 2025 |
VM, VC, RC, IC | Under Process | Shift summary | Ring Commissioning |
|
| | 08h27 Start ThomX: Modulator, Laser, Frig
08h34 Chillers were started, cycling
al magnets |
12x | |
1048
|
Mon Mar 31 09:53:26 2025 |
VM, IC, RC | Under Process | Shift summary | Ring Commissioning |
|
| | 08h00 ThomX started by Maher
09h50 Problem with vacuum in the
septum. TL-V3 and EL-V1 are closed. |
   | |
Draft
|
Tue Apr 1 08:43:53 2025 |
VM, IC, DN | Under Process | Shift summary | Ring Commissioning |
|
| | 08h42 Start ThomX: Morulator, firg, laser
08h47 Chillers, cycling all magnets
10h40 HV is 'ON' |
| |
1058
|
Thu Apr 17 08:16:04 2025 |
VM, RC, DN, ND | Under Process | Shift summary | Ring Commissioning |
|
| | 08h15 Start Thomx: modulator, frig, laser
08h21 Chillers started, all magnets
cycling |
    | |
Draft
|
Fri May 2 08:23:50 2025 |
VM | Under Process | Shift summary | Ring Commissioning |
|
| | 08h22 ThomX was started: modulator, frig,
laser
08h28 Chillers was started, all |
| |
Draft
|
Fri May 16 08:21:36 2025 |
VM, IC, DN | Under Process | Shift summary | Ring Commissioning |
|
| | 08h20 ThomX was started: Modulator, frig,
laser
08h27 Chillers were started, cycling |
| |
Draft
|
Tue May 27 08:34:42 2025 |
VM, IC | Under Process | Shift summary | Ring Commissioning |
|
| | Goal:
Beam Loss Monitors and Ring injection at
high charge. Studies of the injector for |
9x |
|