  Toutes les notes concernant les Commissionning de ThomX, Page 20 of 63  Not logged in ThomX    logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Statusdown Type Category Important Subject Icon Text Attachments
  964   Tue Nov 19 08:20:29 2024 MJ VC KD RC DNUnder ProcessShift summaryLinac Commissionning Shift summary 19/11/2024 icon3.gif 8h20 demarrage machine

iris 1.3mm
att 440
 YAG_TL3_beam.pnginjection_ring.pngFluo_det.png 
  965   Thu Nov 21 08:27:15 2024 VM Entered by Super Team from 134.158.195.141 on Thu Nov 21 08:26:43 2024Under ProcessInfoRing Commissioning   08H25 Start ThomX

09H45 HV is 'ON'

09h49 Breakdown in the RF Gun
  
  967   Fri Nov 22 11:18:28 2024 KD, RCUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 22 novembre 2024 9h30 : mise en chauffe

intervention casemate pour alignement
laser et nettoyage optique.
 TL_BPM4_locked.dat 
  Draft   Tue Nov 26 07:53:39 2024 MJ RC KDUnder ProcessShift summaryLaser | Opt | Linac Commissionning | Ring Commissioning shift du 26 novembre 2024 8h : mise en chauffe en remote (laser,
modulateur, frigo, chiller, cyclage)

 2024-11-26_12_22_06_el_dg_sst_01-ccd_01_RAW_1.png 
  969   Wed Nov 27 08:04:44 2024 VCUnder ProcessShift summaryLinac Commissionning Shift summary 27/11 8h : mise en chauffe (laser, modulateur,
frigo, chiller, cyclage)

9H30 y'a eu une intervention
 QP1_scan.pngQP2_scan.pngQP3_scan.png 
  Draft   Thu Nov 28 08:19:05 2024 VM, IC, VK Under ProcessInfoRing Commissioning   08h18 Start ThomX

10h00 HV is 'ON'

10h35 RF Gun phase is 174 dg. Section
  
  971   Fri Nov 29 08:22:14 2024 VC, Carlos Buitrago, Sudhanshu Thakur, NDUnder ProcessShift summaryLinac Commissionning TP 29-11--2024 demarrage chauffage 8H20

test nouveau code synchro 50Hz
=> ne fonctionne pas
  
  972   Tue Dec 3 09:14:50 2024 SC, HG, VMUnder ProcessLinacLI | TL Passage à 61.5MeV et 70 MeV 9h14 Mise en chauffe

Pas de camera laser qui s'ouvre
sur PlateformeIHM
 screenshot_steerers_linac_findejournée.pngBeam_transmission_Sole.png 
  974   Thu Dec 5 08:31:34 2024 VM Entered by Super Team from 134.158.195.141 on Thu Dec 5 08:31:12 2024Under ProcessShift summaryRing Commissioning   08h28 Start ThomX

08h40 Some magnets remain switched
off. Cycling was not performed
  
  975   Fri Dec 6 08:24:36 2024 VM, IC, VK, HG Under ProcessShift summaryRing Commissioning   08h25 Start ThomX

09h55 HV is 'ON'

10h18 RF Gun Phase is 159 dg. Sect.
 8x 
  977   Tue Dec 10 11:35:16 2024 VM,HG,SCUnder ProcessShift summaryLI | TL | LE | Ring | Linac Commissionning | Ring Commissioning 50 and 70 MeV Emittance, and transport  Intervention chiller (Maher) : maintenance
nécessaire à prévoir
(clé outil clignote)
 Q_vs_SolenoScan_at_16-52-02_Q1_Off.pngQ_vs_SolenoScan_at_16-39-39_recette_good_xrays.png 
  978   Wed Dec 11 08:12:54 2024 KD, VC, RC MJUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 11 décembre 2024 8h10 : mise en chauffe à distance
de la machine (chiller, frigo, laser, modulateur).

/!\ La mesure SF6 faites
 Screenshot_2024-12-11_11-51-40_min_synchrotron_deb_aller_m1_2mmY.pngScreenshot_2024-12-11_11-51-40_min_synchrotron_fin_aller_m1_2mmY.pngScreenshot_2024-12-11_11-51-40_max_synchrotron_deb_aller_m1_2mmY.pngScreenshot_2024-12-11_12-39-36_min_synchrotron_deb_retour_0mmY.png 
  979   Thu Dec 12 07:54:45 2024 KD, RC, MJ, VM, IC, VKUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 12 décembre 2024 7h50: mise en chauffe en remote (chiller,
frigo, laser, modulateur)

Demarrage alignement sur l'axe
 7x 
  980   Fri Dec 13 08:22:36 2024 VM, IC, VKUnder ProcessShift summaryRing Commissioning   08h23 Start ThomX

09h40 HV is 'On'

10h24 RF Gun Phase 183 dg. Sect.
 Screenshot_from_2024-12-13_11-28-46.pngScreenshot_from_2024-12-13_14-44-28.pngScreenshot_from_2024-12-13_14-46-59.png 
  981   Tue Dec 17 08:09:41 2024 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 17 décembre 2024 8h10 : mise en chauffe de la machine (modulateur,
laser, frigo et chiller)

9h30: faisceau dans anneau avec
  
  983   Wed Dec 18 08:37:08 2024 VCUnder ProcessShift summaryLinac Commissionning summary shift Dec 18  demarrage chauffage 8h45

le modulateur refuse de passer
en mode standby
  
  Draft   Thu Dec 19 11:10:03 2024 IC, VK, VMUnder ProcessShift summaryRing Commissioning   11h05 Start ThomX

11h50 BPM02-Libera04 wiring has
been checked: 'OK' 
  
  986   Fri Dec 20 08:37:20 2024 VC,NDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning Shift summary 20/12 demarrage machine 8h40

Matin: travail sur la synchro,
creation du mode "diags only"
 10x 
  989   Tue Jan 7 08:40:58 2025 VC MJ HGUnder ProcessShift summaryLinac Commissionning Shift summary 07/01/25 demarrage machine 8h30
pB serveurs/IHMs
vide (peg) (pas de communication)
  
  990   Thu Jan 9 08:35:10 2025 IC, VK, VM, NDUnder ProcessShift summaryRing   08h35 Start ThomX: Modulator, Frigo, All
magnets.

08h40 Cicling all magnets, Start
 15x 