  Toutes les notes concernant les Commissionning de ThomX, Page 13 of 62  Not logged in ThomX    logo
ID Date Author Status Typedown Category Important Subject Icon
  734   Thu Apr 13 08:16:42 2023 KD, ND, LisaUnder ProcessShift summaryLI | TL | LE | Diag shift du 13 avril 2023 

8h20 : mise en chauffe chiller/Frigo, Modulateur, Laser et PA.

9:30 Verification health check

- er/sy/rac.17-elr.01-rdp.03 ne demarre pas

9:50 Cyclage des aimants

10:30 Temperature chiller section > 31

11:00 Intervention vide:

- LI/VA/PEG.04 Tout semble normal malgr'e l' alarme sur l'atkpanel

- pour CFP: acces anneau, pas de fuite trouvee

11:17 Intervention MO+JNC pour probleme frigo => resolu.

11:45 Demarrage faisceau.

Charge 120pC => attenuation laser de 360 a 345 => charge 100pC

14:00 Transport faisceau.

Pb reglage en temps TL/DG/SST.01. Nouveau retard: 50e3us. Exposure: 0.04s

Phase section: 109

15:20 Sur EL/DG/SST.01 on voit que le faisceau est coupe pendant le transport... (cf copie d'ecran)

15:30 Reglage coupelle de Faraday EL/DG/FC.01.

Retard de ER/CA/WAC.03: -6.29us. Adaptation 50 ohm a faire.

Verifier qu'il ne se declenche que sur le canal exterieur et pas sur toutes les voies (par exemple apres coupure electrique).

16:15 Recette de transport jusqu'a EL/DG/FC sauvee dans TL+LE:Test recipes

16:30 Observation Cerenkov: Cf video sur https://photos.app.goo.gl/42HKzkkWm84QKhhEA

Passage a 5Hz.

Alignement OBL. Il reste du travail à faire (1/2 journée) pour atteindre la salle laser.

17:20 Arret ThomX

Attachment 1: health_check_2023_04_13_09_35.png
health_check_2023_04_13_09_35.png
Attachment 2: health_check_RF_Redpitaya_2023_04_13_09_46.png
health_check_RF_Redpitaya_2023_04_13_09_46.png
Attachment 3: Screenshot_from_2023-04-13_09-49-05.png
Screenshot_from_2023-04-13_09-49-05.png
Attachment 4: Screenshot_from_2023-04-13_09-57-41.png
Screenshot_from_2023-04-13_09-57-41.png
Attachment 5: scan_charge_phase_min_0.0_max_360.0_10_12_20.png
scan_charge_phase_min_0.0_max_360.0_10_12_20.png
Attachment 6: scan_charge_phase_min_30.0_max_70.0_10_13_4.png
scan_charge_phase_min_30.0_max_70.0_10_13_4.png
Attachment 7: Screenshot_from_2023-04-13_10-46-51.png
Screenshot_from_2023-04-13_10-46-51.png
Attachment 8: Screenshot_from_2023-04-13_11-20-45.png
Screenshot_from_2023-04-13_11-20-45.png
Attachment 9: EL_FC_01_retard_6_09us.png
EL_FC_01_retard_6_09us.png
Attachment 10: EL_FC_01_retard_6_29us.png
EL_FC_01_retard_6_29us.png
Attachment 11: 2023-04-13_15_49_56_el_dg_sst_01-ccd_01_log_scale_False_despeckle_False_min_scale_0_max_scale_1000.png
2023-04-13_15_49_56_el_dg_sst_01-ccd_01_log_scale_False_despeckle_False_min_scale_0_max_scale_1000.png
  736   Wed Apr 19 14:47:58 2023 KD/CB Shift summaryLinac Commissionning run du 19 avril 2023 

NB de Christelle : pendant toute la durée de la manipe, l'atténuateur section a été repris à plusieurs reprises. A noter que selon l'origine de la fluctuation puissance incidente section, ou phase section, ou effet thermique dans les guides, l'effet n'est pas le même sur la dynamique, et un rattrapage de l'atténuation ne semble pas suffisant pour recouvrir les paramètres faisceaux twiss, dispersion en énergie. En conséquence, le transport est modifié, le paramètre k des quads aussi....  On ne sait pas ce qu'on fait

Déroulement de la manipe :

modulateur 1090V, iris  1.3 mm, position laser initiale 4.90/2.42 mm

Dimensions laser 0.34/0.29mm

Moteur solenoides à ces valeurs : Z 3.3mm/-4.9mrad, et en X : 0.8mm/ 10,201mrad

Pb delay TLSST2

Objectif : test nouvelles position laser 4.4/2.1 mm afin de trouver un meilleure orbite globale à la machine, puisque aucun axe EM ne correspond (canon/section/ premier triplet)

réalignement du solénoide pour cette valeur : Translation X=0.543mm, Z 4.185 mm, rotation : 5.8288 mrad, -6.57mrad

Phase Qmax 337°, énergie mesurée 5MeV@285°, charge phase enregistré (ci-joint)

Solenoide à 238 pour reproduire la focalisation à LI SST1 (image enregistrée dans image ref)

Energie mesurée avec le steerer 48.5 MeV (avec 1.24 dB) , NB : ajouter mise à zero des quad en début de script

alignement avec steerer linac sur les quad 1 & 3

QP1 2 3 =[-3,4 5,2 -1,1] A, image enregistrée dans le dossier ref image pour chaque station LI SST1, TLSST1, TL SST2, Idip= 159,3A

quad 3 scan @238A, QP12=[-3.07 +3,16], image sauvée sur TL SST2 avec QP3 = 0.8A. Les conditions ont encore changées Idip = 158,6A.....

l'analyse indique que l'espread a varié entre deux mesures, impossible de joindre les images png sur le elog....

 

 

 

mesures sur TL SST1 et TL SST2

a remplir avec les notes

Attachment 1: charge_phase__at_19-04-2023__16-39-28.jpg
charge_phase__at_19-04-2023__16-39-28.jpg
Attachment 2: 2023-04-19_19_12_41_li_dg_sst_01-ccd_01_RAW.png
2023-04-19_19_12_41_li_dg_sst_01-ccd_01_RAW.png
  737   Thu Apr 20 10:36:19 2023 Entered by Super Team from 134.158.195.142 on Thu Apr 20 10:36:01 2023Reference SolutionShift summaryLI | TL | Aimants | Linac Commissionning référence axe mag Canon 

Voici la référence tete de machine pour l'axe mag canon :

Laser Iris position  [H;V] : [4.90/2.42mm]

Solénoides position : Z : 3.3mm, -4.9mrad

                                 X : 0.8mm, 10.201mrad

  Draft   Tue Apr 25 09:11:29 2023 ND,DN,SC,NE, EMNew SolutionShift summaryRing Quart collectif 25/4 

9h10 (ND): Mise en chauffe modulateur et laser

9h15 mise en chauffe Chiller (SC)

Démarrage MPS (DN,SC,NE) :

- Mode anneau sans FP impossible car les vannes cavités FP doivent être fermées pour tourner en mode anneau et on ne souhaite pas fermer ces vannes pour éviter de polluer les miroirs.

- Mode ThomX ie anneau avec FP : Le vide dans la cavité FP est en rouge ce qui empêche l'autorisation de tir. Forçage possible du tir cad si on considère que le vide cavité FP n'est pas un problème et si tout le monde est d'accord.

Seuil du vide modifié dans la cavité FP : tir ok si on allume tous les dipoles (LI, TL, Anneau + une valeur d'injection).

NB : Pour les tirs qui utiliseront la cavité FP dans le futur, il faudra que celle-ci soit démarrée avant la fermeture de la casemate.

 

 

 

 

  740   Tue Apr 25 13:53:05 2023 SC,ND,VK, VM, IC Shift summaryLinac Commissionning | Ring Commissioning Démarrage faisceau 

Point initial faisceau canon :

- soleno LI/AE/COL.01-MOT.02 = 3.3 mm, LI/AE/COL.01-MOT.01 = 0.8 mm, LI/AE/COL.02-MOT.01 = 10.201mrad, LI/AE/COL.02-MOT.02 = -4.9 mrad

- laser = Horizontal Iris Position = 4.9 et Vertical Iris Position = 2.42

14h00 : Faisceau linac

Recette Best_injection_20230301 chargée

Phase canon = 286 degres, phase section qui minimise la dispersion = 113 degres

Faisceau dans l'anneau

15h07 : Charge 85 pC

La laselock de la cavité se trouve sur jive : OC/OP/LAS.01-ECB.01-FBS.01 : A tester

17h40 No storage achieved. Only 1-2 turns after several attemption to optimize the injection. The reason is not clear. The BPM reading at first BPM after septum was at -1 mm while it should be +(2-4).

 

 

 

 

  741   Tue Apr 25 14:19:49 2023 CB Shift summaryLI | TL | Linac Commissionning run du 20 avril 2023 icon13.gif 

Suite du run du 19 avril : objectif mesure des twiss pour plusieurs valeur de solénoides à partir de 180A

NB : Problématique de dérive des paramètres rencontrés entre le temps de réglage, et le temps d'acquisition --> mesures non traitables

NB2 : dimensions sur TLSST1 en fonction du solenoide différent de l'autre point de fonctionnement (lien évident entre l'alignement de la machine et les twiss ...)

Alignement quad par Kevin

scan sur TLSST1 en fonction du solénoide avec le script matlab

- 180A 104°/2.03dB, image prise sur TLSST2 QP123 [-2 +3.9 -1.1]A, Idip 159.3A

quad scan QP3 à 180A [-1.81 2.23], puis [-1.72  2.15]A, les conditions ont bougées sur TLSST2 entre deux mesures...

- 200A, 4 quad scan QP3 [ -2.35 2 D] A ; [-2,95 2,35 D] A ; [4.1 -3,9 D] A ; quad scan QP1 : [ D 3,76 -3,86] A

- 220A [D 3,18 -3,58]A

phase réajustée à 93degrés pour Idip =157.9 A, TLSST2 enregistrée [1,37 3,18 -3,58]

Difficile de savoir ce qu'on fait avec tant de paramètres qui bougent

 

 

 

Attachment 1: coil2scan_11h46.png
coil2scan_11h46.png
Attachment 2: 20230420.pptx
  742   Wed Apr 26 19:03:56 2023 Entered by Marie Jacquet from 134.158.89.45 on Wed Apr 26 19:03:42 2023 Shift summaryLinac Commissionning shift du 26/04 - Quads scans + stabilite 

1) Quad scans Isol = 155, 175, 190, 200, 220 pris avec script classique ET avec script FWHM LIMA - Taille a comparer, pour voir ... A TRAITER, resultats a suivre

2) Mesure longue de stabilite  (c'etait tres stable comme ca a l'oeil) - A TRAITER, a quantifier avec plots a suivre.

  743   Thu Apr 27 09:24:26 2023 ND, LSNew SolutionShift summaryRing | Diag Prise de donnee 26/4/2023 

9:24 Mise en chauffe

9:30 Cyclage des aimants

11h44 Démarrage faisceau

Les positions laser sur le feedback ont changé : hor position = 4.950 et ver position = 2.351

Remise des paramètres de référence :

Laser Iris position  [H;V] : [4.90/2.42mm]

Solénoides position : Z : 3.3mm, -4.9mrad

                                 X : 0.8mm, 10.201mrad

 

Scan Charge Phase : Energie max = 286 degres

Solenoide : 225 A

Mesure Energie of the electron (MeV) = 50.0260 +/- 0.0027

Energy at the center of the screen (MeV) = 49.9967

Relative energy spread FWHM (%) : 0.1755

13:30 Problème allumage TL/DPi bloque le MPS

14:00 Faisceau dans EL

Sur EL/SST.01 le faisecau semble etre dans une boite qui est sensible au champ des steerers.

Deux images attachees avec EL/DPI=-6.8 et EL/DPI=-7.1

Meilleure recette pour entrer dans l'anneau :  recipe_recipe_LI_TL_RI_all_20230317_15_52_23.txt

Phase RF section 110deg

Attenuateur: 1.94dB

On a reussit a aller jusqu'a ri-C2/DG/BPM.05 mais pas BPM.06

17h32: Arret machine

Attachment 1: 2023-04-27_14_41_46_el_dg_sst_01-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png
2023-04-27_14_41_46_el_dg_sst_01-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png
Attachment 2: 2023-04-27_14_43_34_el_dg_sst_01-ccd_01_RAW.png
2023-04-27_14_43_34_el_dg_sst_01-ccd_01_RAW.png
  744   Fri Apr 28 09:20:00 2023 ND, LS, IC, VM, VKNew SolutionShift summaryRing Prise de donnee 27/4/2023 

9:19: Mise en chauffe

10:24 Cycling magnets

10:50 Demarrage faisceau

11:21 load recipe_recipe_LI_TL_RI_all_20230317_15_52_23.txt

Beam to RI-C2/BPM.05

Problem with injection kicker. Not triggering and DS says Charging power supply is OFF. Maher came to solve the problem (14h). Most probably this was a reason of only 1 turn during the last days.

15h Studies on the DPI and SEPT on the injection (1st BPM x-orbit). Compared to yesterday run, we see the good response on change of the DPI ans SEPT. The first BPM is at +(4-6) mm.

Without injection kicker, beam is lost after ~1 turn.

 

 

Attachment 1: scan_charge_phase_min_0.0_max_360.0_10_57_35.png
scan_charge_phase_min_0.0_max_360.0_10_57_35.png
Attachment 2: 2023-04-28_11_05_30_tl_dg_sst_02-ccd_01_RAW.png
2023-04-28_11_05_30_tl_dg_sst_02-ccd_01_RAW.png
Attachment 3: 2023-04-28_11_07_37_tl_dg_sst_03-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png
2023-04-28_11_07_37_tl_dg_sst_03-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png
Attachment 4: Screenshot_from_2023-04-28_15-10-52.png
Screenshot_from_2023-04-28_15-10-52.png
Attachment 5: Screenshot_from_2023-04-28_15-13-24.png
Screenshot_from_2023-04-28_15-13-24.png
Attachment 6: LiSST01_2023-04-28_15-29-59.png
LiSST01_2023-04-28_15-29-59.png
Attachment 7: SST01_2023-04-28_15-26-21.png
SST01_2023-04-28_15-26-21.png
Attachment 8: SST02_2023-04-28_15-18-42.png
SST02_2023-04-28_15-18-42.png
Attachment 9: SST_03_2023-04-28_15-15-46.png
SST_03_2023-04-28_15-15-46.png
Attachment 10: BLM_MIX_2023-04-28_15-38-57.png
BLM_MIX_2023-04-28_15-38-57.png
  745   Wed May 3 09:04:24 2023 KDNew SolutionShift summaryLI | TL | LE | Linac Commissionning shift du 03 mai 2023 

9h : Mise en chauffe machine (frigo, chiller, modulateur, PA, Laser)

13h30 : Démarrage Machine

- Quelqu'un a changé la valeur de conversion de l'iris (1.3E10 au lieu de 1E10) ce qui donné une mauvaise taille d'iris

- Redpitaya OFF. Redémarrage des redpi 1, 2 et 4 mais la 3 est toujours inaccessible via TANGO.

- max charge 336° à peine 60 pC pour atténuateur à 430mm et énergie sortie laser 214uJ ==> intervention laser necéssaire.

- La phase Canon déconne : dérive permanente de l'IHM (actions menées : scan charge phase, utilisation de l'IHM phase ==> problème bouton scan ?) Impossible à stopper. En cliquant sur phase scan +10 ==> oscillations (-10, +10) permanente ==> Kill de la plateforme IHM est la seule solution trouvée pour stoper cela

*** Réglage machine ***

* Alignement axe mag Canon: iris [5.03mm, 2.4mm], position solénoide axe mag

* phase laser/Canon : Phase max -50° (287°)

* charge : 50pC

* Courant solénoide pour avoir min de taille sur LI/SST1 (cf. Images ==> manque une valeur intermédiaire entre 50% et 10%; ou réglage manuel) : 233A

* passage section : alignement steerer LI/STR.01 pour avoir le faisceau au milieu de l'écran TL/SST.01

==> utilisation Script alignement LI/STR.01 dans QP1 et LI/STR.02 dans QP3

* réglage énergie et mise à dispersion min en utilise le dipole (159.3A et taille min)
    - position 0mm TL/BPM.02
    - taille faisceau min avec solénoide à 220A (cf. Image)

phase section 115°, atténuation 2.05dB => image stable

* focalisation "douce" du faisceau sur TL/SST1 avec les QUAD 1 à 3 pour quad SCAN (pas de saturation) : [0, 3.3, -3.65]A (cf. image)

* comparaison taille faisceau TL/SST1 et TL/SST2 (modification du dipole pour avoir le faisceau au centre de l'écran : 159.7A soit : ~3mm) : cf. image

* Réajustement phase + atténuation section (116°, 2.08dB) : cf. Image avec solénoide 220A sans quad

* Mesure Quad Scan avec une autre valeur de solénoide (200A), réalignement steerer (axe QUAD) avec nouvelle valeur solenoide
    - cf. images TL/SST1 et TL/SST2 pour quad : [-0.6, 2.7, -3.0]A

* ratrappage attenuation et phase section (115°, 2.1dB) 

==> Saute de position du faisceau, cela n'est pas corrélé à une perte de puissance ou de changement de phase (phénomène impossible à reproduire avec l'atténuation section et/ou les phases canon et section) ==> E-log Marie pour visu saute

* On a essayer de voir jusqu'où on pouvez aller avec ces paramètres :

 - Allumage de QP4 à 7 avec les valeurs précédentes : [2 , 1.75, -4.20, 4.0] ==> faisceau visible sur TL/SST3 (gros faisceau environ au milieu), image non prise

- Allumage anneau (dipole, quad, sextu, septum, kicker inj) + steerer TL/STR.03; TL/STR.04 [-0.57, -5.14]A et [2.72, 5.14]A (ancienne valeur) + valeurs précédentes pour aimants anneau par exemple :

Kicker_inj à 9200V, et spetum à 105V ==> on fait 1 tour

Le dipole peut etre varié entre 159 et 161A sans modification significative.

RI-C1-C2/PS/SP.03/currentSetpointPM : <type 'float'> : 1.6
RI-C1/PS/QP.01/currentSetpointPM : <type 'float'> : 3.2645911407
RI-C1/PS/QP.02/currentSetpointPM : <type 'float'> : -1.67228104259
RI-C1/PS/QP.03/currentSetpointPM : <type 'float'> : -1.65228104259
RI-C1/PS/QP.04/currentSetpointPM : <type 'float'> : 3.2245911407
RI-C1/PS/QP.05/currentSetpointPM : <type 'float'> : -3.082482261
RI-C1/PS/QP.06/currentSetpointPM : <type 'float'> : 1.69918499819
RI-C1/PS/QP.07/currentSetpointPM : <type 'float'> : 5.75451558131
RI-C1/PS/QP.08/currentSetpointPM : <type 'float'> : -6.54936027749
RI-C1/PS/QP.09/currentSetpointPM : <type 'float'> : -6.50936027749
RI-C1/PS/QP.10/currentSetpointPM : <type 'float'> : 5.74451558131
RI-C1/PS/QP.11/currentSetpointPM : <type 'float'> : 1.71918499819
RI-C1/PS/QP.12/currentSetpointPM : <type 'float'> : -3.082482261
RI-C1-C2/PS/SP.01/currentSetpointPM : <type 'float'> : 2.77555756156e-17
RI-C2/PS/QP.01/currentSetpointPM : <type 'float'> : 3.2645911407
RI-C2/PS/QP.02/currentSetpointPM : <type 'float'> : -1.64228104259
RI-C2/PS/QP.03/currentSetpointPM : <type 'float'> : -1.65228104259
RI-C2/PS/QP.04/currentSetpointPM : <type 'float'> : 3.2745911407
RI-C2/PS/QP.05/currentSetpointPM : <type 'float'> : -3.102482261
RI-C2/PS/QP.06/currentSetpointPM : <type 'float'> : 1.72918499819
RI-C2/PS/QP.07/currentSetpointPM : <type 'float'> : 5.76451558131
RI-C2/PS/QP.08/currentSetpointPM : <type 'float'> : -6.51936027749
RI-C2/PS/QP.09/currentSetpointPM : <type 'float'> : -6.52936027749
RI-C2/PS/QP.10/currentSetpointPM : <type 'float'> : 5.75451558131
RI-C2/PS/QP.11/currentSetpointPM : <type 'float'> : 1.71918499819
RI-C2/PS/QP.12/currentSetpointPM : <type 'float'> : -3.092482261
RI-C1-C2/PS/SP.02/currentSetpointPM : <type 'float'> : -1.32

RI-C1/PS/STR.01-V.01/currentSetpointPM : <type 'float'> : -0.8338653312
RI-C1/PS/STR.01-H.01/currentSetpointPM : <type 'float'> : -7.78395274185
RI-C1/PS/STR.02-V.01/currentSetpointPM : <type 'float'> : -1.446080688
RI-C1/PS/STR.02-H.01/currentSetpointPM : <type 'float'> : -6.92027020625
RI-C1/PS/STR.03-V.01/currentSetpointPM : <type 'float'> : -1.9470590688
RI-C1/PS/STR.03-H.01/currentSetpointPM : <type 'float'> : 4.76568657418
RI-C1/PS/STR.04-V.01/currentSetpointPM : <type 'float'> : -1.0806466224
RI-C1/PS/STR.04-H.01/currentSetpointPM : <type 'float'> : 2.18056669408
RI-C1/PS/STR.05-V.01/currentSetpointPM : <type 'float'> : 0.1573797216
RI-C1/PS/STR.05-H.01/currentSetpointPM : <type 'float'> : -0.0906906310341
RI-C1/PS/STR.06-V.01/currentSetpointPM : <type 'float'> : 3.528684072
RI-C1/PS/STR.06-H.01/currentSetpointPM : <type 'float'> : -7.92368919352

RI-C2/PS/STR.01-V.01/currentSetpointPM : <type 'float'> : -1.6450712784
RI-C2/PS/STR.01-H.01/currentSetpointPM : <type 'float'> : -9.04236623115
RI-C2/PS/STR.02-V.01/currentSetpointPM : <type 'float'> : -0.420228576
RI-C2/PS/STR.02-H.01/currentSetpointPM : <type 'float'> : -0.865464058682
RI-C2/PS/STR.03-V.01/currentSetpointPM : <type 'float'> : 5.730764208
RI-C2/PS/STR.03-H.01/currentSetpointPM : <type 'float'> : 2.0989665994
RI-C2/PS/STR.04-V.01/currentSetpointPM : <type 'float'> : -1.837470048
RI-C2/PS/STR.04-H.01/currentSetpointPM : <type 'float'> : 2.00755778176
RI-C2/PS/STR.05-V.01/currentSetpointPM : <type 'float'> : 0.045318768
RI-C2/PS/STR.05-H.01/currentSetpointPM : <type 'float'> : -0.137610988361
RI-C2/PS/STR.06-V.01/currentSetpointPM : <type 'float'> : -0.374909808
RI-C2/PS/STR.06-H.01/currentSetpointPM : <type 'float'> : -7.71986048002

*17h45 : Arret machine

 

**** Programme du shift ****

- Prise de données pour contraindre le model de la lattice TL
      -- pour différentes valeur solénoide
      -- Différents réglage du Quad SCAN

- Optimisation de la procédure de démarrage et des scripts d'alignement. 

- Mesure variation Pis en fonction de l'atténuateur

 

Attachment 1: 2023-05-03_14_17_56_li_dg_sst_01-ccd_01_RAW.png
2023-05-03_14_17_56_li_dg_sst_01-ccd_01_RAW.png
Attachment 2: 2023-05-03_14_17_30_li_dg_sst_01-ccd_01_RAW.png
2023-05-03_14_17_30_li_dg_sst_01-ccd_01_RAW.png
Attachment 3: 2023-05-03_15_00_05_tl_dg_sst_02-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png
2023-05-03_15_00_05_tl_dg_sst_02-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png
Attachment 4: 2023-05-03_15_09_10_tl_dg_sst_01-ccd_01_RAW.png
2023-05-03_15_09_10_tl_dg_sst_01-ccd_01_RAW.png
Attachment 5: 2023-05-03_15_29_59_tl_dg_sst_02-ccd_01_RAW.png
2023-05-03_15_29_59_tl_dg_sst_02-ccd_01_RAW.png
Attachment 6: 2023-05-03_15_34_32_tl_dg_sst_02-ccd_01_RAW.png
2023-05-03_15_34_32_tl_dg_sst_02-ccd_01_RAW.png
Attachment 7: 2023-05-03_16_25_17_tl_dg_sst_02-ccd_01_RAW.png
2023-05-03_16_25_17_tl_dg_sst_02-ccd_01_RAW.png
Attachment 8: 2023-05-03_16_22_47_tl_dg_sst_01-ccd_01_RAW.png
2023-05-03_16_22_47_tl_dg_sst_01-ccd_01_RAW.png
  746   Wed May 3 20:10:40 2023 Entered by Marie Jacquet from 134.158.89.45 on Wed May 3 20:10:26 2023 Shift summaryLinac Commissionning Stabilite LINAC 

Pour illustrer la fin de l'entree elog 745 d'aujourd'hui  :

(==> Saute de position du faisceau, cela n'est pas corrélé à une perte de puissance ou de changement de phase (phénomène impossible à reproduire avec l'atténuation section et/ou les phases canon et section) ==> E-log Marie pour visu saute)

ci-joint le resume du traitement des donnees du 24 et 26 avril ( = donnees stabilite)

Attachment 1: 2023-05-03-traitement_Data20230424et26.pdf
  748   Thu May 4 11:41:53 2023 VK, VM, IC, LS Shift summaryRing Commissioning Restart storage in the Ring 

~9h Start of the modulator

10h Tuning of the injector with KD

11h Try to inject in the ring. Only 1-2 turns after optimization. We tried previous injector settings, the situation is the same. We retuned the injector based on our previous experience with

Isolenoid = 234 ->220 A,

Laser phase = 289 -> 288 

LIL phase = 114 -> 110 (Att = 2.04 dB)

Settings are saved.

We found that the injection kicker timing was not good (-7.19 us). We put the previous setting -7.23 us

Problem to start RF Cavity. IP adress problem . A lot of Debug with Jean Noel. Working when not connected to THomx network. Philip is informed.

Machine stay in standby till tomorrow. 

 

  749   Thu May 4 16:14:06 2023 Entered by Marie Jacquet from 134.158.89.45 on Wed May 3 20:10:26 2023 Shift summaryLinac Commissionning RE: Stabilite LINAC 

 

Entered by Marie Jacquet from 134.158.89.45 on Wed May 3 20:10:26 2023 wrote:

Pour illustrer la fin de l'entree elog 745 d'aujourd'hui  :

(==> Saute de position du faisceau, cela n'est pas corrélé à une perte de puissance ou de changement de phase (phénomène impossible à reproduire avec l'atténuation section et/ou les phases canon et section) ==> E-log Marie pour visu saute)

ci-joint le resume du traitement des donnees du 24 et 26 avril ( = donnees stabilite)

On a aussi testé en bougeant la position laser cela n'a pas le même effet (mouvement sur LI/BMP.01)

On a mis "OFF" les steerer du linac mais cela ne semble pas avoir eu d'effet nottable.

  750   Fri May 5 08:47:28 2023 KD VM VK JN SLUnder ProcessShift summaryRing Commissioning shift du 5 mai 2023 

8h30 : accès casemate controlé 

==> septum et kickers OFF et cavité RF OFF

==> problème cavité RF, mux 3 défaut de communication

==> impossible d'acquité les interlocks et redémarrer la cavité.

Morning restart of machine was easy for the same parameters from day before.

 

Problem with network was fixed by G. Philippon, it was due to the limited number of allowed ports in the new swith that was recently replaced.

Still we cannot start RF Cavity with Jean Noel. Ampli is working, but no communication of Consigne from Tango to LLRF hardware.

14.30 Cavity on, getting power.

Frequency 500.41->500.4094, and phase manual optimisation.

Power in cavity is changing from 60 kV to 80kV for  80kV setpoint.

Saving data for postprocess. Orbit correction.

Beam is stable and stored. Orbit is positive. energy is about 50.075MeV, ring dipoles 160A. Sextupoles on.

Extraction kicker started to extract just before injection.

 

 

 

 

 

 

 

 

 

 

Attachment 1: Screenshot_from_2023-05-05_17-25-28.png
Screenshot_from_2023-05-05_17-25-28.png
Attachment 2: Screenshot_from_2023-05-05_17-13-31.png
Screenshot_from_2023-05-05_17-13-31.png
Attachment 3: Screenshot_from_2023-05-05_17-13-41.png
Screenshot_from_2023-05-05_17-13-41.png
Attachment 4: Screenshot_from_2023-05-05_17-52-52.png
Screenshot_from_2023-05-05_17-52-52.png
Attachment 5: Screenshot_from_2023-05-05_17-50-31.png
Screenshot_from_2023-05-05_17-50-31.png
  751   Mon May 15 11:31:43 2023 ND, LS, IC, VK, VM, SWUnder ProcessShift summaryRing Commissioning Ring operation 15/5 

10:00 Machine warm up

Magnets cycling

11:00 Start machine

Health check: problems with Red Pitaya and Vacuum

11:30 Scan charge phase: Charge too high (-118pC).

Laser attenuator was at 300mm => 295mm (-95pC)

RF section phase 112°

Attenuator 1.98dB

12:10 load recipe good_20230504_13_46_27

13:00 Intervention by Mohamed to start the cavity and record data points

16:42 Some storage at 500.3600MHz, Phase -30

17:15 Some storage at 500.3072MHz at Phase -29

17:20 Stop beam

 

 

Attachment 1: Screenshot_from_2023-05-15_11-18-03.png
Screenshot_from_2023-05-15_11-18-03.png
Attachment 2: Screenshot_from_2023-05-15_11-27-46.png
Screenshot_from_2023-05-15_11-27-46.png
Attachment 3: health_check_Vide_Jauge_2023_05_15_11_27.png
health_check_Vide_Jauge_2023_05_15_11_27.png
Attachment 4: health_check_Vide_Pompe_2023_05_15_11_27.png
health_check_Vide_Pompe_2023_05_15_11_27.png
Attachment 5: health_check_RF_Redpitaya_2023_05_15_11_27.png
health_check_RF_Redpitaya_2023_05_15_11_27.png
Attachment 6: scan_charge_phase_min_0.0_max_360.0_11_33_34.png
scan_charge_phase_min_0.0_max_360.0_11_33_34.png
Attachment 7: ring_storage_quality__2023_05_15_17_14.png
ring_storage_quality__2023_05_15_17_14.png
  752   Tue May 16 10:28:43 2023 LS, ND, IC, VKUnder ProcessShift summaryRing Commissioning Ring operation 16/5 

9:33 Start warming up

9:45 Ducre is working on the plumbing but it shuld not affect operations

11:00 Intervention JNC pour problemes refroidissement

12:00 Start beam

12:30 Sweeping of frequencies on RF cavity in ring, found local maxima at:

-500.0441MHz

-500.0371MHz

-500.0186MHz

Ring optimisation at 500.0186MHz

Slits position: 10mm/31.5mm (no improvement) => removed


16:30 Beam stop (access by Ducre)

Modulator left on standby, laser Gated, Magnets ON

 

Summary of the search:

Recipe used: all_20230516_15_45_01 (LI+TL+RI, all_recipes)

Attached plot shows ring at f=500.0202MHz.

RF Cavity: 45kV, fundamental = 114276mm; Plunger 15.420mm.

We ramped the cavity up to 50kV. Going from 40kV to 50 kV decreases orbit quality => some parameters still to be optimised.

Effect seen for:

RI/PS/DP: +/- 1A kills the beam. Changes by 0.1A can improve the beam.

RF cavity phase: acceptable values are on a wide range (-20degrees => +40 degrees) still very wide. We should probably set the cavity around +10 degrees (center of the range) begore increasing the voltage

RF Frequency: we had more than 100 turns in a band of about 10kHz

No effect seeing for:

injection steerers (no change in stored beam orbit)

Suggestion:

Try to optimise the quadrupoles with current settings

Then optimise the RF cavity phase (check that manual changes and software changes have similar effects) and ramp slowly the voltage.

 

 

 

 

Attachment 1: health_check_2023_05_16_12_02.png
health_check_2023_05_16_12_02.png
Attachment 2: scan_charge_phase_min_0.0_max_360.0_12_8_7.png
scan_charge_phase_min_0.0_max_360.0_12_8_7.png
Attachment 3: 2023-05-16_12_13_52_tl_dg_sst_02-ccd_01_log_scale_False_despeckle_False_min_scale_0_max_scale_100.png
2023-05-16_12_13_52_tl_dg_sst_02-ccd_01_log_scale_False_despeckle_False_min_scale_0_max_scale_100.png
Attachment 4: ring_storage_quality__2023_05_16_16_06.png
ring_storage_quality__2023_05_16_16_06.png
  753   Wed May 17 09:16:47 2023 VK, IC. AL Shift summaryRing Commissioning Understanding of the shift in RF frequency 

8:40 Start warming up, problem with PSS. It was restarted.

Problems to start and tune the RF cavity. A clear working procedure and reliable tuning should b defined to optimize the Ring comissioning progress.

Feedback for teh RF has the suspicious behavior. At motor position close to the nominal, the feedback ofsets the motor in the negative direction for 100k steps and then, comes back from negative to the requested position.

Sometimes the we lost the power in the RF cavity.

Start of the ring. RF power is ~10-30 kV and freq = 500.0202 MHz. We loaded the machine with the yesterday's setting.  Optimizattion of the storage and orbit/tune. No stored beam achived. Only a few tens of turns achieved.

We decided to ramp the RF frequency up to 100 kV. We could not tune the RF cqvity to our previous value 500.41. We found the plunger position only for 500.38 MHz, so we started to work on this frequency.

After optimization work, we have achieved the storage (see the figs attached) with a reasonable orbit.

By setting the sextupoles and optimizing the quadrupoles we achived to have the kind of clean storage, stable orbit. 

By injector optimization we reduced the betattron oscilation at the injection. From time to time, the RF section phase ans power should be corrected. The further orbit correction should be done.

The estimated tunes are  (~0.19, ~0.66).

Then, we started to go back to the nominam RF freauency 500.0202 MHz.

Tuning of the cavity. Power is 40 kV.

The difference in orbit is attached in the scrennshot. Then, after the optimization it was almost the same as this morning.

By calculating the FFT on the mixed signal with the scope (see screenshot), we found the following frequency 16.68*30 = 500.4 MHz.

Without RF power, it was not possible to measure the revolution frequency as the FFT had two-peak strucutes, which is complicated to interpratate/understand.

At the nominal frequency, no storage is achieved. We wants to measure the revolution frequency operating at 500.4 MHz. Start of the ramping the power at this frequency. Big problem to tune the RF cavity. We can not inject the power in the cavity.

=> The clear observation that the ring is more stable and the storage is possible with the frequency around 500.4 MHz. it means that the circumference normally is shorter by ~ 10 mm. Investigations arer ongoing.

 

Attachment 1: Screenshot_from_2023-05-17_14-51-18.png
Screenshot_from_2023-05-17_14-51-18.png
Attachment 2: Screenshot_from_2023-05-17_14-49-52.png
Screenshot_from_2023-05-17_14-49-52.png
Attachment 3: Screenshot_from_2023-05-17_14-48-39.png
Screenshot_from_2023-05-17_14-48-39.png
Attachment 4: Screenshot_from_2023-05-17_14-48-16.png
Screenshot_from_2023-05-17_14-48-16.png
Attachment 5: Screenshot_from_2023-05-17_14-47-56.png
Screenshot_from_2023-05-17_14-47-56.png
Attachment 6: Screenshot_from_2023-05-17_14-45-20.png
Screenshot_from_2023-05-17_14-45-20.png
Attachment 7: Screenshot_from_2023-05-17_14-33-57.png
Screenshot_from_2023-05-17_14-33-57.png
Attachment 8: Screenshot_from_2023-05-17_14-39-15.png
Screenshot_from_2023-05-17_14-39-15.png
Attachment 9: Screenshot_from_2023-05-17_14-36-23.png
Screenshot_from_2023-05-17_14-36-23.png
Attachment 10: Screenshot_from_2023-05-17_14-38-07.png
Screenshot_from_2023-05-17_14-38-07.png
Attachment 11: Screenshot_from_2023-05-17_14-30-55.png
Screenshot_from_2023-05-17_14-30-55.png
Attachment 12: anabpmnfirstturns0_17052023.png
anabpmnfirstturns0_17052023.png
Attachment 13: closed_orbit_17052023.png
closed_orbit_17052023.png
Attachment 14: anabpmnfirstturns01_17052023.png
anabpmnfirstturns01_17052023.png
Attachment 15: anabpmnfirstturns02_17052023.png
anabpmnfirstturns02_17052023.png
Attachment 16: Screenshot_from_2023-05-17_15-41-19.png
Screenshot_from_2023-05-17_15-41-19.png
Attachment 17: Screenshot_from_2023-05-17_16-17-01.png
Screenshot_from_2023-05-17_16-17-01.png
Attachment 18: Screenshot_from_2023-05-17_16-31-56.png
Screenshot_from_2023-05-17_16-31-56.png
  754   Fri May 19 18:05:29 2023 VK, IC Shift summaryRing Commissioning RF frequency of the Ring 

In the morning, after the start-up pf the machine, scan phase-charge and small tuning it was possible to store the beam with the settings from previous day.

The storage was optimize withthe dipole current of 159.9 (best storage up to now). RF cqvity voltqge 20-100 kV.

Work on the orbit correction and BPM.

The the dipole current was tuned to the nominal current 159.3 A with sufficient storage. AT ~18h the RF cavity went down.

To be continued.

Attachment 1: scan_charge_phase_min_0.0_max_360.0_10_43_35.png
scan_charge_phase_min_0.0_max_360.0_10_43_35.png
Attachment 2: Screenshot_from_2023-05-19_13-50-56.png
Screenshot_from_2023-05-19_13-50-56.png
Attachment 3: Screenshot_from_2023-05-19_13-56-41.png
Screenshot_from_2023-05-19_13-56-41.png
Attachment 4: Screenshot_from_2023-05-19_12-15-50.png
Screenshot_from_2023-05-19_12-15-50.png
  755   Fri May 19 20:22:42 2023 MJ, KDUnder ProcessShift summaryRF Anneau | Ring Commissioning RF et anneau 

Apres 18h30 : prise ne main de la machine pour aller dans la LE ==> le kicker d'extraction est interlocké (abdandon) 

Essaie avec la derniere recette de l'anneau : à 159.3A le stockage n'est pas tres bon (cavité OFF)

On essai de jouer sur le plongeur pour accorder la cavité à la fréquence de révolution du paquet (voir 2 screenshot de l'oscilloscope).

La cavité à une forte influence sur le stockage, mais la forme n'est pas la même

- au nominal (24.4mm) où le faisceau semble mieux "entrer" dans l'anneau mais "meurt" plus vite.

- à 22.4 mm le faisceau semble vivre dans l'anneau plus longtemps mais est moins bien stocké. Quelle est la fréquence associé à cette valeur de plongeur ?

 * Est ce qu'il n'y a pas à creuser sur l'accord de la cavité au faisceau ? 

 * La fréquence principale de la FFT (16.68MHz) ne semble pas bouger (que ce soit avec les dipôles ou avec la cavité RF). Que représente cette valeur ? 

20h30 : machine à l'arrêt

Attachment 1: 24_4mm.png
24_4mm.png
Attachment 2: 22_4mm.png
22_4mm.png
  756   Tue May 23 11:36:24 2023 LS, ND Shift summaryLI | Diag Prise de donnees 23/05 

9:30 Demarrage machine

Fin installation Cerenkov + tests MRSV

Laser alignement Cerenkov arrive jusqu'a la camera a balayage

11:00 Demarrage machine

13:30 Arret machine. On a vu du Cerenkov dans la boite du milieu du couloir mais pas au dela. Rien sur la camera en salle laser.

Attachment 1: IMG_20230523_110343_8_copy_780x1040-20230523-164911728-20230523-164911770.jpg
IMG_20230523_110343_8_copy_780x1040-20230523-164911728-20230523-164911770.jpg