  Status of commissioning, report also here plots are reports., Page 20 of 24  Not logged in ELOG logo
ID Date Author Status Typedown Category Location Title Text Attachments
  342   Fri May 31 18:12:59 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronicsThomX iglooFP-cavity lock survey during the Linac section changing operationtoday with Daniele, we disconnected the
EOM to increase the injected power of the
amplifier, we were at 4.8mW but we still
  
  344   Wed Jun 19 09:07:56 2024 Ronic ChicheFixedinfosoftwareThomX iglooNew password for login on the ThomX computerthe previous password has expired.

the new access from the computer
:
  
  348   Tue Aug 27 09:59:18 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issuetemperature in the casemate ~ 19.5°C
stable

this morning, I measured the power
 Capture.JPGCapture2.JPG 
  349   Tue Aug 27 10:19:08 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issueI refilled the chiller and the stabilized
temperature is @ 25°C

we started the 3rd stage of the
 Capture.JPG 
  350   Tue Aug 27 11:33:24 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issuewe had to move the laser cavity motor to
find the resonances and change a lot the
CEP.
 Sans_titre.png 
  351   Tue Aug 27 12:31:19 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issueafter doing some alignment (walking procedure
on the Y axis), and CEP optimization, I got
83kW for 33% on the laser amplifier with
 Capture.JPG 
  352   Fri Aug 30 10:50:45 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issuethis morning with Daniele, we are measuring
the amplifier power just before the FP-cavity.
Casemate temperature @19.5°C
  
  353   Fri Aug 30 12:05:38 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issueAfter the summer power shutdown, I restarted
all the equipements and got quickly ~80kW
for 33% amplifier ratio with CEP optimization
  
  354   Fri Aug 30 17:59:01 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issueamplifier power measurement before the
compressor CVBG.
we used a mirror in between the amplifier
  
  358   Fri Sep 6 12:10:51 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issueafter redoing the alignment of the CVBG,
we got back the initial power in the FPC
(87kW)
  
  359   Fri Sep 6 15:20:20 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issuenow, the Ring RF frequency is set to 500.067MHz.

so the CFP/laser frequency should
be 500.067MHz/15 = 33.3378MHz.
  
  360   Fri Sep 6 17:21:51 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issueI changed a little bit the locking parameters
(see picture) for the RF/FPC loop and it
locked rapidely.
 20240906_161926.jpg 
  362   Mon Sep 9 11:00:43 2024 Ronic ChicheFixedinfolasers and optics | detectors and electronics | softwareThomX igloorestarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issuethis morning, with Vincent :

- we added the 10Hz trigger to
the CH2 on the remote scope (192.168.229.21)
  
  363   Mon Sep 16 12:03:30 2024 Ronic ChicheFixedinfomechanicsThomX iglooFinding correct motors position and parameters to keep the lock during a movethis morning, I try
to find a new region for MOT.03 and MOT.06
where we can move them without unlocking
  
  364   Tue Sep 17 12:48:13 2024 Ronic ChicheFixedinfomechanicsThomX iglooFinding correct motors position and parameters to keep the lock during a movethis morning with Daniele, we did a quite
long run with this motor position and it
seems we don't lose the lock too much.
  
  365   Tue Sep 17 13:04:32 2024 Ronic ChicheUnder Processinfolasers and optics | softwareThomX iglooOptimizing lock parameters for stable X-ray productionhere are the (good) lock parameters used
this morning.

for the RF/FPC lock, the 33MHz
 Capture.JPG 
  366   Thu Oct 3 16:38:03 2024 Ronic ChicheUnder Processinfolasers and optics | softwareThomX iglooOptimizing lock parameters for stable X-ray productionToday with Daniele and Alice, we operated
to cavity.
we obtained 84kW for 33% of amplifier
  
  368   Wed Oct 9 09:56:21 2024 Ronic ChicheUnder Processinfolasers and optics | softwareThomX iglooOptimizing lock parameters for stable X-ray productionThis morning, I wanted to test quickly
if the Smaract motors can be used in open
loop instead of closed loop or in piezo scan.
  
  369   Wed Oct 9 18:39:34 2024 Ronic ChicheUnder Processinfolasers and optics | softwareThomX iglooOptimizing lock parameters for stable X-ray productionThis afternoon, we scanned the optical
table vertically with the hexapod in asynchronous
mode to find its optimum position, looking
  
  374   Tue Oct 22 18:58:56 2024 Ronic ChicheUnder Processinfolasers and optics | softwareThomX iglooOptimizing lock parameters for stable X-ray productionToday, after setting the locking parameters,
I got 80kW in the FPC for 33% amplifier ratio
after CEP tuning (Smaract CH2 ~ -423.5µm)
  