770
|
Wed Jun 14 18:18:32 2023 |
VK, IC. VM | | Shift summary | Ring Commissioning |
|
Srart of the beam physics measurements | | The main idea fo this week is to
prepare the beam for the search of the first
X-rays. |
14x | |
771
|
Thu Jun 15 17:46:40 2023 |
VK, IC. VM | | Shift summary | Ring Commissioning |
|
Orbit correction, BLM in the Ring | | The BLM detector boxes were installed in
the ring. We connected 3 fibers and 2 scintillator
detectors in th ring to be able to observe |
7x | |
772
|
Fri Jun 16 09:36:07 2023 |
VK, IC. VM, AL, ND, LS | | Shift summary | Ring Commissioning |
|
Orbit correction, optimization of the storage, study of the RF frequency | | 9h30 Start of the modulator and lasser
(GATE is closed).
9h46 Data is taken as background. |
8x | |
Draft
|
Fri Jun 23 09:47:54 2023 |
VK, IC, DN, RC, JN | | Shift summary | Ring Commissioning |
|
search for X-rays | | 8h30 Start of the modumator, laser, magnet
cycling
9h45 Beam is ON. Scan charge vs. |
| |
786
|
Fri Jul 28 17:06:02 2023 |
VK, IC. VM, LS, JNC | | Shift summary | Ring Commissioning |
|
Test of the new optics (27-28 July) | | Start of the modulator and laser at ~9h
and hour later start the beam.
Working at 500.38 MHz to retrieve |
6x | |
787
|
Mon Jul 31 16:57:11 2023 |
VK, IC. VM, LS | | Shift summary | Ring Commissioning |
|
Work on the new optics | | 9h30 Start of the modulator and laser
Start of the beam. Problem with
charge, the max charge at the end of the |
| |
790
|
Thu Aug 10 15:52:24 2023 |
VK, VM, IC, LS | | Shift summary | Ring Commissioning |
|
Work on the new ring lattice (August, 2-4) | | Starting point nominal lattice D1Thomx_017_064_r56_02_chro00
with the MCF=0.014 chro=0/0
Goal: test the new lattice with MCF=0.0231 |
13x | |
836
|
Wed Jan 31 14:12:25 2024 |
RC VC MJ | Under Process | Other | Ring Commissioning |
|
commitionning | | Chauffage mod 11h
demarrage machine 14H
on suit le star faisceau step par |
 | |
847
|
Tue Feb 27 09:10:47 2024 |
KD, VK, VM | Under Process | Shift summary | Ring Commissioning |
|
run du 27 février 2024 | | 9h: mise en chauffe de la machine (chillers,
laser, aimants, modulateur)
Mohamed regle la cavité |
| |
854
|
Tue Mar 5 15:10:32 2024 |
IC, VM, VK | Under Process | Shift summary | Ring Commissioning |
|
Restart and tuning of the injector | | 10h Intervention to repair the water leakage.
It was repaired.
New problem with vacuum |
| |
855
|
Wed Mar 6 08:49:56 2024 |
IC, VM, VK | Under Process | Shift summary | Ring Commissioning |
|
X-ray generation | | 8h50 Warming up the machine
10h start the beam
Tuning the injector |
  | |
Draft
|
Thu Mar 7 08:58:28 2024 |
VK, VM, IC | Under Process | Shift summary | Ring Commissioning |
|
Recomissioning of the SR, search for the X-rays | | 8h50 Warming up the machine
Problem with the vaccum around
the RF cavity (see screenshot attached). |
| |
951
|
Thu Oct 31 08:19:25 2024 |
KDn Dupraz from 109.222.35.58 on Thu Oct 31 08:19:12 2024 | Under Process | Shift summary | Ring Commissioning |
|
shift du 31 octobre 2024 | | 8h15: mise en chauffe en remote (modulateur,
laser, chiller, Cycling)
Tuning of the linac and injection |
  | |
965
|
Thu Nov 21 08:27:15 2024 |
VM Entered by Super Team from 134.158.195.141 on Thu Nov 21 08:26:43 2024 | Under Process | Info | Ring Commissioning |
|
| | 08H25 Start ThomX
09H45 HV is 'ON'
09h49 Breakdown in the RF Gun |
| |
Draft
|
Thu Nov 28 08:19:05 2024 |
VM, IC, VK | Under Process | Info | Ring Commissioning |
|
| | 08h18 Start ThomX
10h00 HV is 'ON'
10h35 RF Gun phase is 174 dg. Section |
| |
974
|
Thu Dec 5 08:31:34 2024 |
VM Entered by Super Team from 134.158.195.141 on Thu Dec 5 08:31:12 2024 | Under Process | Shift summary | Ring Commissioning |
|
| | 08h28 Start ThomX
08h40 Some magnets remain switched
off. Cycling was not performed |
| |
975
|
Fri Dec 6 08:24:36 2024 |
VM, IC, VK, HG | Under Process | Shift summary | Ring Commissioning |
|
| | 08h25 Start ThomX
09h55 HV is 'ON'
10h18 RF Gun Phase is 159 dg. Sect. |
8x | |
980
|
Fri Dec 13 08:22:36 2024 |
VM, IC, VK | Under Process | Shift summary | Ring Commissioning |
|
| | 08h23 Start ThomX
09h40 HV is 'On'
10h24 RF Gun Phase 183 dg. Sect. |
  | |
Draft
|
Thu Dec 19 11:10:03 2024 |
IC, VK, VM | Under Process | Shift summary | Ring Commissioning |
|
| | 11h05 Start ThomX
11h50 BPM02-Libera04 wiring has
been checked: 'OK' |
| |
993
|
Fri Jan 10 08:24:25 2025 |
IC, VK, VM, ND | Under Process | Shift summary | Ring Commissioning |
|
| | 08h25 Start ThomX: Modulator, Frigo, cycling
all magnets
08h30 Start chillers |
10x |
|