  Toutes les notes concernant les Commissionning de ThomX, Page 60 of 63  Not logged in ThomX    logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Statusdown Type Category Important Subject Icon Text Attachments
  899   Thu Aug 8 10:12:35 2024 Entered by Super Team from 134.158.195.142 on Thu Aug 8 10:12:02 2024 LinacLI | RF D1 conditionnement section Remplissage SF6 de 2.3 bar à 2.5
bar par Christopher

10h08 : augmentation progressive
  
  900   Fri Aug 9 10:01:23 2024 Entered by Super Team from 134.158.195.142 on Fri Aug 9 10:01:08 2024 LinacLI | RF D1 conditionnement section Vide de démarrage apres l'allumage
des chillers : in section 6.4e-10 et out
section 8.3e-10
  
  906   Tue Sep 3 09:25:05 2024 SC, KD, HG MJ LinacLinac Commissionning Alignement laser et section + Mesures 9h Mise en chauffe modulateur et chiller,
reseau rf rempli de sf6 de 2.2 bar à
2.6bar
 cathod_align_dark_current.png 
  909   Tue Sep 10 08:47:55 2024 SC, HG, MJ LinacLinac Commissionning Alignements : LASER - SOLENO - SECTION 8h47 Mise en chauffe modulateur et chillers

- Phase Q max : 161 deg

 
 2024-09-10-alignement-section.pdfprochain_alignement_section.xlsx 
  911   Wed Sep 11 12:30:52 2024 Entered by Marie Jacquet from 134.158.89.45 on Wed Sep 11 12:30:36 2024 Shift summaryLinac Commissionning tableau alignement section - v2    2024-09-11_alignement_section-v2_1.xlsx 
  915   Mon Sep 16 23:59:24 2024 Entered by Marie Jacquet from 134.158.205.56 on Mon Sep 16 23:59:00 2024 Shift summaryLinac Commissionning alignement section de lundi 16/09 Alignement section, bilan du jour :

En partant de 
Li/STR1 [H,V] : [0.93 , -0.9]  
  
  918   Thu Sep 19 17:37:48 2024 MJ ProblemLinac Commissionning Diags completement instables SUBITEMENT il y a 10 minutes.  Diags completement instables SUBITEMENT
il y a 10 minutes. Plus possible de continuer
le shift. QQun  a-t-il fait qqchose
  
  Draft   Fri Sep 27 10:44:50 2024 MJ VC  Linac Commissionning       
  927   Fri Sep 27 17:03:34 2024 MJ HG Shift summaryLinac Commissionning Redemarrage machine apres probleme de synchro et/ou alim Apres un OFF/ON des baies alim et des transfo
+ baie synchro OFF/ON la synchro semble etre
de nouveau alive
 ICT.pngbpmLI.png 
  929   Tue Oct 1 08:45:59 2024 SC-VC-HG-ND-IC-VM-VK LinacLI | Ring | Linac Commissionning Beam transport up to the ring 8h45 Mise en chauffe refroidissement et
modulateur

9h visite
 8x 
  934   Fri Oct 4 12:26:21 2024 MJ Shift summaryLinac Commissionning Charge vs soleno : OK ce matin Ce matin la charge est parfaitement
transmise de soleno 210 a 250, et decroit
tranquillment ensuite. Je n'ai
 charge_vs_soleno_screenshot.png 
  Draft   Fri Nov 15 07:56:03 2024 IC, VK, VM, ND Shift summary  Ring studies, MRSV 07h50 Start ThomX

09h20 HV is 'ON'

09h25 HV  1215 V
 36x 
  Draft   Thu Jan 23 17:03:45 2025 Ring team AnneauRing Commissioning Ring Working Points 50 MeV/ 61.5 MeV / 70 MeV 50 MeV

Configuration:
 8x 
  1015   Wed Feb 19 17:32:30 2025 shift screw Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Rustine pour le probleme CEM kicker - ring storage - Xrays Cable ventilo kicker debranche ==> aucun
effet
Cable balise blinde ==>
 storage_et_Xrays_2025-02-19_19-01-58.pngdet2diodes_pb_voie4_2025-02-19_19-16-07.png 
  1020   Tue Feb 25 22:59:57 2025 Entered by Marie Jacquet from 88.165.97.136 on Tue Feb 25 22:59:29 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 24 -25 fevrier (visite Alberto Paola Luca) - Detecteur Photonic Science Commissioning det Photonic Science

** Depose
Dectris, mise en place Photonic, alignement
  
  1022   Wed Feb 26 22:52:03 2025 Entered by Marie Jacquet from 88.165.97.136 on Wed Feb 26 22:50:49 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 26 fevrier (visite Alberto Paola Luca) - Detecteur Photonic Science  Suite du commissioning
det Photonic Science

**
  
  1024   Fri Feb 28 00:32:21 2025 Entered by Marie Jacquet from 134.158.205.38 on Thu Feb 27 23:45:19 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 27 fevrier (visite Alberto Paola Luca)  ** Nouvelle
prise d'images pour determiner les distortions
du det :
  
  1030   Thu Mar 6 10:38:31 2025 Entered by Marie Jacquet from 134.158.205.25 on Thu Mar 6 10:37:50 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Programme de la journee : preparation des valeurs a remplir  1 : Alignement Axe
Q1-Q3 avec SCRIPT - Conditions
 Compare_Align_ALL.pngTrend_Position_Yag_Sautes.pngJauges_2025-03-06_18-47-14.png2025-03-06-Q1Q3_Q4Q5.pdf 
  1034   Wed Mar 12 16:50:29 2025 Entered by Super Team from 134.158.195.143 on Wed Mar 12 16:50:08 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Spectres X (positions fentes 2 et temps d'extraction) IP-Fente2 : 8835 mm
IP-capteur_CdTe: 10460

Calib ouverture Fentes2 : +0.1
  
  1042   Thu Mar 20 18:41:55 2025 Entered by Marie Jacquet from 134.158.205.16 on Thu Mar 20 18:41:39 2025 Shift summaryLI | Ring | Linac Commissionning | Ring Commissioning 19 et 20 mars - Mesures X-rays - Bravin & co 19
mars 2025

 spectre_42keV.png 