926
|
Fri Sep 27 10:52:33 2024 |
VC-MJ | Fixed | Shift summary | Linac Commissionning |
|
Demarrage faisceau | | faisceau... sur Li SST0.1
position laser était à
5.1 2.55 (on ne sait pas pourquoi) |
|
|
474
|
Thu Jun 9 10:51:08 2022 |
Entered by Super Team from 134.158.195.141 on Thu Jun 9 10:50:52 2022 | Under Process | Shift summary | Linac Commissionning |
|
Demarrage et faisceau (JN, HG) | | Matin :
- Laser alignement
- Obstacle qui coupait le faisceau |
|
|
Draft
|
Fri Jun 10 18:50:11 2022 |
Entered by Super Team from 134.158.195.141 on Fri Jun 10 18:49:53 2022 | Under Process | Linac | Linac Commissionning |
|
Demarrage et faisceau (JN, HG) | | |
|
|
Draft
|
Fri Jun 10 20:16:26 2022 |
Entered by Super Team from 134.158.195.141 on Fri Jun 10 18:49:53 2022 | Under Process | Linac | Linac Commissionning |
|
Demarrage et faisceau (JN, HG) | | |
|
|
482
|
Fri Jun 17 17:58:54 2022 |
Entered by Super Team from 134.158.195.141 on Fri Jun 17 17:58:38 2022 | Under Process | Linac | Linac Commissionning |
|
Demarrage et faisceau (JN, HG) | | Alignement laser :
Zone testée : [phase_Qmax
-10, phase_Qmax] |
  |
|
468
|
Tue May 31 09:21:02 2022 |
MO/SC/HG, JNC/CB | Fixed | Linac | Electronique |
|
Demarrage et faisceau | | 9h15 : Mise en chauffe modulateur et chiller
(SC/MO/HG)
Aujourd'hui : Alignement faisceau |
|
|
484
|
Tue Jun 21 09:58:30 2022 |
Entered by ND/SC from 134.158.195.141 on Tue Jun 21 09:58:15 2022 | Under Process | Linac | Aimants |
|
Demarrage et faisceau | | 9h45 Mise en chauffe modulateur. Test interface
générale Nicolas pour l'allumage
du modulateur. |
12x |
|
535
|
Tue Aug 30 10:27:31 2022 |
HM HG | Under Process | Linac | Linac Commissionning |
|
Demarrage et faisceau | | 10h10 modulateur ON , laser ON
Le client 5 est éteint (avec
les ds calc) !!!! (rallumé à |
 |
|
670
|
Wed Jan 25 09:58:17 2023 |
Entered by Viktor Soskov from 134.158.195.153 on Wed Jan 25 09:58:00 2023 | Fixed | Problem | Linac Commissionning |
|
Demarrage du laser | | Bonjour,
on n'arrive pas à démarrer
laser via réseau ni avec IHM ni avec |
|
|
1161
|
Wed Dec 3 11:09:12 2025 |
Entered by Super Team from 134.158.195.141 on Wed Dec 3 11:08:54 2025 | Not Fixed | Info | RF Anneau | Linac Commissionning | Ring Commissioning |
|
Demarrage ThomX |
| Soucis Septum : Maher
help |
|
|
471
|
Fri Jun 3 17:42:32 2022 |
Entered by Super Team from 134.158.195.142 on Fri Jun 3 17:42:15 2022 | Under Process | Info | Linac Commissionning |
|
Demarrage Linac | | le laser semble coupé. Image avec
Iris ouvert à 6mm.
|
  |
|
1190
|
Tue Feb 10 18:34:33 2026 |
Entered by Super Team from 127.0.0.1 on Tue Feb 10 18:34:13 2026 | Under Process | Shift summary | LI | RF D1 |
|
Demarrage Linac |
| Mesures après remontage de la cale
: 1215 V sur le modulateur.
ça tient mais |
|
|
435
|
Mon Apr 11 12:09:18 2022 |
Mo/JNC/CB | | Shift summary | Linac Commissionning |
|
Demarrage | | 12h00 démarrage modulateur et chillers,
fermeture casemate
15h : démarrage laser |
|
|
220
|
Thu Dec 16 09:53:38 2021 |
Entered by Super Team from 134.158.195.141 on Thu Dec 16 09:53:20 2021 | Under Process | Shift summary | SY | Linac Commissionning |
|
Demarage machine | | Les chillers sont démarrés
et le modulateur en chauffe
Test de l'influence sur les |
|
|
1061
|
Tue Apr 29 11:03:14 2025 |
Entered by Super Team from 134.158.195.141 on Tue Apr 29 11:02:38 2025 | Under Process | Info | LI | TL |
|
Data taking for ML | | Demarrage ACQ pour ML
Random : Phi_GUN, Phi_Section,
ST1, ST2, Solenoid, QP1, QP2, QP3 |
|
|
835
|
Fri Jan 26 09:36:01 2024 |
ND, Anna K, Elene K | | Shift summary | LI | TL | LE |
|
Data taking 26/01 | | 9:30 Warm-up
11:00 Modulator OFF => restart
warm-up |
7x |
|
1072
|
Mon May 19 17:57:15 2025 |
Entered by Super Team from 134.158.195.141 on Mon May 19 17:56:57 2025 | Under Process | Info | LI | TL |
|
Data : Sole scan, Q scan, random linac Yag_TL1 | | Today's data :
- coil scan (+ images)
- Q3 scan |
|
|
77
|
Wed Sep 29 17:03:32 2021 |
Entered by Super Team from 134.158.195.143 on Wed Sep 29 16:57:52 2021 | Under Process | Linac | Linac Commissionning |
|
Dark current | | Pemiere image du courant d'obscurité.
L'image
est prise sur la station SST01 du Linac. |
|
|
35
|
Fri Jun 11 18:47:23 2021 |
Hayg | Reference Solution | Linac | RF D1 |
|
DS pour les températures des chillers |
| Listes des Ds pour les températures
des chillers
GUN : ER/HF/RAC.17-API.AI1/ |
|
|
124
|
Wed Oct 27 16:48:50 2021 |
Entered by Super Team from 134.158.195.141 on Wed Oct 27 16:48:32 2021 | Not Fixed | Urgent | CC | Linac Commissionning |
|
DS calc en défaut | | Les DS CALC sont en défaut et impossible
de les relancer sur client3. Ils n'apparaissement
pas dans astor. |
|