  Toutes les notes concernant les Commissionning de ThomX, Page 34 of 62  Not logged in ThomX    logo
Entry   ND/VK/IC/KD/HG/MJ; Prise de donnee 13/01 scan_charge_phase_min_0.0_max_360.0_9_54_10.pngscan_charge_phase_min_190.0_max_230.0_9_54_54.png2023-01-13_09_58_47_li_dg_sst_01-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png2023-01-13_10_01_07_tl_dg_sst_01-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png
Mise en chauffe

9:45 Cyclage aimants

9:48 Demarrage
Entry   IC, VM, ND, VK; Prise de donnee 10/3/2023 7x
9h20 Start modulator, cycle magnets

10h20 Intevention Vincent sur PA

10h40 Scan charge phase
Entry   Entered by Super Team from 134.158.195.141 on Thu Dec 4 08:58:52 2025; Preparation/check of the 70 MeV WP for X-ray run Screenshot_from_2025-12-04_16-10-14.pngScreenshot_from_2025-12-04_17-38-20.pngScreenshot_from_2025-12-04_18-01-39_WITH_EL.png
Goal: preparation and checking the machine operation at 70 MeV and 40 MeV (ideally with X-rays)

8h54 Warming up
RF section 29.20 C -> 28.5 C
Entry   Entered by Super Team from 134.158.195.141 on Fri Mar 28 14:26:38 2025; Prep faisceau pour lundi 
12h47 Mise en chauffe modulateur

Zone de stockage en rouge

Mise en route frigo, chillers : ok
Entry   Entered by Alexandre Moutardier from 134.158.195.142 on Fri Jan 14 15:44:40 2022; Premier faisceau OTR ! 2022-01-14_15_42_03_tl_dg_sst_01-ccd_01_first_otr_light_kane_panchal_log_scale_True_despeckle_False_min_scale_0_max_scale_100.png2022-01-14_15_46_00_tl_dg_sst_01-ccd_01_first_otr_light_kane_panchal_with__bkg_subtraction_log_scale_True_despeckle_False_min_scale_0_max_scale_100.png
Première lumière OTR pris sur la station TL/DG/SST.01 !

Images are without and with background substraction.

AM.
Entry   Entered by Viktor Soskov from 134.158.195.153 on Fri Feb 11 15:07:41 2022; Positions moteurs M4-1(2) 
Positions moteurs

LI/OP/OPT.01-Mir.04-MOP.01   -> =190mm  ???

LI/OP/OPT.01-Mir.04-MOP.01   -> =5410mm   ???
Entry   KD MJ RC DN; Position Horiz FPC ("spectres dromadaires") 
7h55: mise en chauffe en remote (modulateur, cyclage, laser, frigo/chillers)
==> plus de trig sur la machine (sur toute la plage de scan de la phase stab du laser PC). ==> OK, je suis une truffe le laser était
"off"
Entry   Entered by sophie chance from 134.158.195.141 on Thu Oct 28 17:25:40 2021; Pompe PP1 
Lorsqu'il y a une coupure de courant la pompe PP1 remet une valeur d'interlock par défaut qui n'avait pas été modifié

Jean-Noel et les personnes du vide ont modifié ce seuil

A 3 dB, 100A, passage à 10 Hz sans problèmes avec le changement de seuil d'interlock de PP1
Entry   Entered by IC/V/SC from 134.158.195.141 on Thu Apr 14 11:04:51 2022; Polarités des quadrupoles Screenshot_2022-04-14_11-10-59.png
Faisceau en route, visualisation sur TL/DG/SST.01

Bobine focalisation : 190 A, LI/PS/STR.01-H01 = -1A, LI/PS/STR01-V01 = 1A, Faisceau quasi au centre de l'écran.

Charge = environ 70 pC à énergie max (-40 degres de phase), phase = 113 degres
Entry   Entered by Nicolas Delerue from 134.158.88.175 on Tue Oct 4 17:33:52 2022; Planning shift Thursday 6th October 
- Study beam position on SST and BPM vs iris size / TL/BPM.01

- Start AcQAttrManager

- Study RDP vs TL/BPM.02
Entry   Entered by Super Team from 83.202.31.199 on Mon Jan 31 10:03:38 2022; Planning cette semaine 
-----------------------------------------------------------------------------------

Planning de la semaine

Lundi
Entry   Entered by Super Team from 83.202.31.199 on Mon Apr 4 10:50:04 2022; Planning cette semaine Planning_linac_semaine_du_4_avril.pptxsemaine_4_avril.PNG
 
Entry   Entered by Viktor Soskov from 134.158.195.153 on Thu Jul 7 11:13:10 2022; Phototube_Signal Phototube_2022_07_07.png
 
icon7.gif   Entered by Aurélien Martens from 134.158.88.183 on Tue May 28 15:07:25 2019; Photocathode laser DS back operational 
Following:

1) a crash on 4th of April and a violent reboot of the ELLiOOs embeded machine

2) the need to recover the whole database files in the ELLiOOs embeded machine
Entry   Entered by Viktor Soskov from 134.158.195.153 on Tue Sep 13 11:49:29 2022; Phase Stability 13_09_2022_12H00.pdf
Bonjour, voici la stabilité de phase laser(oscillateur)-horloge(500MHz). La phase commence à bouger quant  linac fonctionne (se chauffe).

Viktor.
Entry   Entered by Nicolas Delerue from 134.158.195.141 on Tue Jan 11 19:30:03 2022; Pb declenchement scope synchro 
La frequence des diags etait reglee a 0.1Hz et le scope de la salle de controle se declenchait sur les diags. C'est pour cela que le scope se declenchait
toutes les 10s.

Les signaux en salle de controle ont une longueur de 10ms mais ceux distribues ont les largeurs demandees (20us et 10us respective,ent pour les
Entry   Entered by Super Team from 134.158.195.142 on Fri Jan 14 12:35:01 2022; Pause déjeuner 
Ne pas toucher les réglages, merci
Entry   Entered by sophie chance from 134.158.195.141 on Thu Oct 28 13:46:25 2021; Passage à énergie max 
Solenoide à 140A , attenuateur canon 3 dB, difficile de passer les 150A

Passage à Energie max
Entry   SC, HG, VM; Passage à 61.5MeV et 70 MeV screenshot_steerers_linac_findejournée.pngBeam_transmission_Sole.png
9h14 Mise en chauffe

Pas de camera laser qui s'ouvre sur PlateformeIHM

9h19 cyclage aimants LI, TL sur interface
Entry   Entered by sophie chance from 134.158.195.142 on Fri Oct 29 13:57:22 2021; Passage section Passage_section_291021.png
Le faisceau a passé la section

STR01-V01 = -1.10, STR01-H01 = -1.90

Ifoc = 150A, phase 263, 1.5 dB section, 0.25 dB canon