ND/VK/IC/KD/HG/MJ; Prise de donnee 13/01   
|
Mise en chauffe
9:45 Cyclage aimants
9:48 Demarrage |
IC, VM, ND, VK; Prise de donnee 10/3/2023 7x
|
9h20 Start modulator, cycle magnets
10h20 Intevention Vincent sur PA
10h40 Scan charge phase |
Entered by Super Team from 134.158.195.141 on Thu Dec 4 08:58:52 2025; Preparation/check of the 70 MeV WP for X-ray run  
|
Goal: preparation and checking the machine operation at 70 MeV and 40 MeV (ideally with X-rays)
8h54 Warming up
RF section 29.20 C -> 28.5 C |
Entered by Super Team from 134.158.195.141 on Fri Mar 28 14:26:38 2025; Prep faisceau pour lundi
|
12h47 Mise en chauffe modulateur
Zone de stockage en rouge
Mise en route frigo, chillers : ok |
Entered by Alexandre Moutardier from 134.158.195.142 on Fri Jan 14 15:44:40 2022; Premier faisceau OTR ! 
|
Première lumière OTR pris sur la station TL/DG/SST.01 !
Images are without and with background substraction.
AM. |
Entered by Viktor Soskov from 134.158.195.153 on Fri Feb 11 15:07:41 2022; Positions moteurs M4-1(2)
|
Positions moteurs
LI/OP/OPT.01-Mir.04-MOP.01 -> =190mm ???
LI/OP/OPT.01-Mir.04-MOP.01 -> =5410mm ??? |
KD MJ RC DN; Position Horiz FPC ("spectres dromadaires")
|
7h55: mise en chauffe en remote (modulateur, cyclage, laser, frigo/chillers)
==> plus de trig sur la machine (sur toute la plage de scan de la phase stab du laser PC). ==> OK, je suis une truffe le laser était
"off" |
Entered by sophie chance from 134.158.195.141 on Thu Oct 28 17:25:40 2021; Pompe PP1
|
Lorsqu'il y a une coupure de courant la pompe PP1 remet une valeur d'interlock par défaut qui n'avait pas été modifié
Jean-Noel et les personnes du vide ont modifié ce seuil
A 3 dB, 100A, passage à 10 Hz sans problèmes avec le changement de seuil d'interlock de PP1 |
Entered by IC/V/SC from 134.158.195.141 on Thu Apr 14 11:04:51 2022; Polarités des quadrupoles
|
Faisceau en route, visualisation sur TL/DG/SST.01
Bobine focalisation : 190 A, LI/PS/STR.01-H01 = -1A, LI/PS/STR01-V01 = 1A, Faisceau quasi au centre de l'écran.
Charge = environ 70 pC à énergie max (-40 degres de phase), phase = 113 degres |
Entered by Nicolas Delerue from 134.158.88.175 on Tue Oct 4 17:33:52 2022; Planning shift Thursday 6th October
|
- Study beam position on SST and BPM vs iris size / TL/BPM.01
- Start AcQAttrManager
- Study RDP vs TL/BPM.02 |
Entered by Super Team from 83.202.31.199 on Mon Jan 31 10:03:38 2022; Planning cette semaine
|
-----------------------------------------------------------------------------------
Planning de la semaine
Lundi |
Entered by Super Team from 83.202.31.199 on Mon Apr 4 10:50:04 2022; Planning cette semaine 
|
| |
Entered by Viktor Soskov from 134.158.195.153 on Thu Jul 7 11:13:10 2022; Phototube_Signal
|
| |
Entered by Aurélien Martens from 134.158.88.183 on Tue May 28 15:07:25 2019; Photocathode laser DS back operational
|
Following:
1) a crash on 4th of April and a violent reboot of the ELLiOOs embeded machine
2) the need to recover the whole database files in the ELLiOOs embeded machine |
Entered by Viktor Soskov from 134.158.195.153 on Tue Sep 13 11:49:29 2022; Phase Stability
|
Bonjour, voici la stabilité de phase laser(oscillateur)-horloge(500MHz). La phase commence à bouger quant linac fonctionne (se chauffe).
Viktor. |
Entered by Nicolas Delerue from 134.158.195.141 on Tue Jan 11 19:30:03 2022; Pb declenchement scope synchro
|
La frequence des diags etait reglee a 0.1Hz et le scope de la salle de controle se declenchait sur les diags. C'est pour cela que le scope se declenchait
toutes les 10s.
Les signaux en salle de controle ont une longueur de 10ms mais ceux distribues ont les largeurs demandees (20us et 10us respective,ent pour les |
Entered by Super Team from 134.158.195.142 on Fri Jan 14 12:35:01 2022; Pause déjeuner
|
| Ne pas toucher les réglages, merci |
Entered by sophie chance from 134.158.195.141 on Thu Oct 28 13:46:25 2021; Passage à énergie max
|
Solenoide à 140A , attenuateur canon 3 dB, difficile de passer les 150A
Passage à Energie max |
SC, HG, VM; Passage à 61.5MeV et 70 MeV 
|
9h14 Mise en chauffe
Pas de camera laser qui s'ouvre sur PlateformeIHM
9h19 cyclage aimants LI, TL sur interface |
Entered by sophie chance from 134.158.195.142 on Fri Oct 29 13:57:22 2021; Passage section
|
Le faisceau a passé la section
STR01-V01 = -1.10, STR01-H01 = -1.90
Ifoc = 150A, phase 263, 1.5 dB section, 0.25 dB canon |