  Toutes les notes concernant les Commissionning de ThomX, Page 32 of 62  Not logged in ThomX    logo
ID Date Author Status Type Category Important Subject Icondown Text Attachments
  613   Thu Oct 27 09:13:49 2022 MO/SC/MJ LinacLinac Commissionning mesure energie impossible (licence) MO : Mise en route modulateur et refroidissement

Pas possible de mesurer l energie
avec le scipt habituel . Message suivant
  
  Draft   Thu Oct 27 11:12:33 2022 Entered by Nicolas Delerue from 80.119.21.73 on Thu Oct 27 11:12:17 2022Under ProcessShift summary  Programme prise de donnée 28/10  

 

===
  
  615   Thu Oct 27 12:07:17 2022 MJ SC Shift summaryLinac Commissionning   Energie  53.4 MeV

Q1 a Q5 = 0   ;  
Idiopole 156.3  ;   STR2V -10   
 Screenshot_from_2022-10-27_12-06-10.png 
  616   Thu Oct 27 17:19:28 2022 Entered by Marie Jacquet from 134.158.89.45 on Thu Oct 27 17:19:13 2022 Shift summaryLinac Commissionning Alignement dans les quads Q1 a Q7 + prise de mesures dans les diag en meme temps Preambule : Le dipole a retrouve aujourd'hui
sa valeur ~ 155 (cette valeur de 144 d'hier
est incomprehensible ...)
 2022-10-27-Shift.pdf 
  617   Fri Oct 28 09:19:22 2022 SC/ND AnneauLinac Commissionning Démarrage faisceau et TP 9h19 : Mise en route modulateur et refroidissements

10h45: Start the Modulator

11h30 : Scan charge
 scan_charge_phase_min_200.0_max_280.0_12_4_46.png2022-10-28_12_39_29_tl_dg_sst_02-ccd_01_RAW.png 
  618   Fri Oct 28 18:16:43 2022 MJ JNCNot FixedShift summaryLinac Commissionning phase en delire Qund on lance l'ihm charge phase, le
plot charge phase arrive puis une routine
cointinue par pas de 1 degres, je crois,
  
  619   Fri Oct 28 18:31:14 2022 MJ KNCNot FixedShift summaryLinac Commissionning ecrans yag 1 et 2 desinchro yag1 et yag2 sont completement desynchro.de
la machine  il faut augmenter image
counter a environ 0.5 pour voir qq chose
  
  620   Mon Oct 31 23:09:07 2022 NDFixedShift summaryDiag | Linac Commissionning RE: ecrans yag 1 et 2 desinchro Je viens de regarder LI/SST.01 et TL/SST.01
étaient en attenuation maximale. Si
le problème se reproduit, il faut
  
  621   Mon Oct 31 23:11:47 2022 NDFixedShift summaryLinac Commissionning RE: phase en delire Après un premier scan sur 0-360
degres le script lance un second scan sur
la zone la plus probable de maximum de charge
  
  622   Thu Nov 3 09:18:49 2022 ND, IC, VK, VMNew SolutionShift summaryRing Shift àf 3/11/2022 9:10 Air pressure: 8 bars, water resistivity
6,33Mohm

9:15 Modulator warm-up
 9x 
  623   Fri Nov 4 11:56:48 2022 Entered by Marie Jacquet from 134.158.205.43 on Fri Nov 4 11:56:17 2022Not FixedShift summaryLinac Commissionning Mesures BPM et YAG vs Steerers - 17/10, 24/10 et 26/10 Ci-joint le bilan BPM
et YAG vs steerer de 3 jours differents :
le 17 le 24 et le 26 octobre
 2022-11-04-BPM-YAG-STR.pdf 
  624   Fri Nov 4 18:28:58 2022 VK, VM, IC, KD Shift summaryRing Commissioning Ring commissioning Start of the machine by KD

11h20 The beam is in the ring

Optimization of the injection with
 7x 
  625   Mon Nov 7 11:02:19 2022 NDUnder ProcessShift summaryDiag | Ring Commissioning Operations du 7/11/2022 10:50 Fin intervention CFP

Intervention laser photocathode
toujours en cours et prioritaire mais preparation
 Screenshot_from_2022-11-07_14-07-30.pngscan_charge_phase_min_0.0_max_360.0_14_5_57.pngscan_charge_phase_min_140.0_max_180.0_14_6_41.pngdispersion_figure.png 
  626   Wed Nov 16 16:33:33 2022 Entered by Viktor Soskov from 134.158.195.153 on Wed Nov 16 16:33:14 2022FixedInfoLinac Commissionning Laser status Bonjour, le phototube UV est installé
à la place du PD.

Viktor.
  
  627   Thu Nov 24 09:43:12 2022 Entered by Maher OMEICH from 134.158.91.212 on Thu Nov 24 09:42:54 2022 FixRF D1 pour info Démarrage de chauffage klystron
après mesure du filament kly. suite
à la coupure d'hier ( par eau
  
  628   Thu Nov 24 10:14:45 2022 Entered by Maher OMEICH from 134.158.91.212 on Thu Nov 24 10:14:31 2022 ProblemRF D1   J'ai un problème sur le frigo
des chillers section et canon qui ne refroidie
pas, je contacte la socièté
  
  629   Fri Nov 25 15:31:56 2022 Entered by Maher OMEICH from 134.158.91.212 on Fri Nov 25 09:58:16 2022 Shift summaryRF D1   Vendredi 25/11

Conditionnement Klystron: le conditionnement
du klystron avec RF progresse lentement au
  
  630   Mon Nov 28 08:54:20 2022 KD, VCUnder ProcessShift summaryLI shift du 28 Novembre 2022 8h45 -9h :  - Démarrage frigo
(pression entrée Frigo max ~ 5.5 bar).
Le Frigo semble tenir et jouer son role. 
  
  631   Mon Nov 28 14:25:46 2022 Entered by Marie Jacquet from 134.158.89.45 on Mon Nov 28 14:25:31 2022 Shift summaryLinac Commissionning Lmag STR 3 (steerer après la LIL) Nouvelle détermination
de Lmag du Steerer 3

Lmag
 2022-11-28-STEERER_3_Lmag.pdf 
  632   Mon Nov 28 18:11:56 2022 CB/HG/JNC Shift summaryLinac Commissionning run du 28 novembre 2022 Redémarrage faisceau avec le nouveau
klystron

charge phase enregistrée
 2022-11-28_18_42_14_li_dg_sst_01-ccd_01_Icol220_RAW_3.png2022-11-28_19_16_29_tl_dg_sst_02-ccd_01_Icol200_phase_101_Att_1.4_RAW_6.png2022-11-28_19_16_29_tl_dg_sst_02-ccd_01_Icol200_phase_101_Att_1.4_RAW_5.png 