ID Date Author Status Type Category Important Subjectdown Icon Text Attachments
  Draft   Wed Jun 17 08:36:20 2026 IC, VMUnder ProcessProblemVide Restart of the accelerator 08h35 Start-up modulator (it was already
on standby), laser, magnets, cycling.

As yesterday there is a problem
 Screenshot_from_2026-06-17_15-54-18.pngScreenshot_from_2026-06-17_15-50-21.png 
  854   Tue Mar 5 15:10:32 2024 IC, VM, VKUnder ProcessShift summaryRing Commissioning Restart and tuning of the injector 10h Intervention to repair the water leakage.
It was repaired.

New problem with vacuum
 Screenshot_from_2024-03-05_15-13-48.png 
  Draft   Mon Mar 9 12:55:30 2026 Entered by Super Team from 127.0.0.1 on Mon Mar 9 12:55:16 2026    Restart after strange last shift  12h55 : Vacuum level OK after TRIG ON
13h00 : Laser ON : no spot on screen
put last motor positions (2266 &&
  
  798   Fri Sep 29 10:19:52 2023 ND, Marie LabatUnder ProcessShift summaryDiag Reglage Cerenkov 29/9 9:07 Mise en chauffe

Verifucation Alignement laser

Maher: changement de dosimetres
 health_check_2023_09_29_11_58.pngscan_Laser_vs_RF_phase_2023_09_29_12_02.png 
  763   Mon Jun 12 14:52:39 2023 VK, IC. VM Shift summaryRing Commissioning Reestablishing running conditions at 500.38 MHz Goal of the shift: Reestablish the good
storage at 500.38 and then try to optimize
the storage and orbit.
 scan_charge_phase_min_0.0_max_360.0_14_32_59.pngScreenshot_from_2023-06-12_15-23-07.pngScreenshot_from_2023-06-12_15-40-14.pngScreenshot_from_2023-06-12_17-38-24.pngScreenshot_from_2023-06-12_17-32-48.png 
  76   Mon Sep 27 14:49:10 2021 Entered by Nicolas Delerue from 134.158.88.175 on Mon Sep 27 14:46:15 2021Under ProcessProblemLinac Commissionning Redémarrage suite coupure Électrique, entered from 134.158.88.175 Bonjour,

Selon Astor, il y a encore des problèmes
 Capture_2021-09-27_14.43.51.png 
  827   Thu Jan 11 14:47:37 2024 NDFixedInfoDiag Redémarrage diags + synchro Pour la synchro, les generateurs de
retard ont ete redemarres.

Pour les diags: redemarrage de
 health_check_Diag_2024_01_11_14_54.pnghealth_check_2024_01_11_14_55.png 
  658   Mon Jan 2 15:21:11 2023 ND/PG/JNC/MO/SC/VC/NEUnder ProcessLinacDiag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique Redémarrage ThomX Bonne Année à tous !

Redémarrage de ThomX

- Mise en route du CC (PG, JNC)
  
  Draft   Mon Sep 27 14:46:31 2021 Entered by Nicolas Delerue from 134.158.88.175 on Mon Sep 27 14:46:15 2021Under ProcessProblemLinac Commissionning Redémarrage suite coupure Électrique Bonjour,

Selon Astor, il y a encore des problèmes
  
  719   Fri Mar 24 08:52:49 2023 SC/JNC/VCUnder ProcessProblemCC Redémarrage ThomX 8h53 Serveur DNS et DHCP non redémarré,
ping ne fonctionne pas, en attente d'une
solution
 ping_automate.pngcamera_lidgsst.01.pngrf_gun_ihm.pngsrv4_astor.pngredpitaya_ihm.png 
  446   Mon May 2 14:02:58 2022 Entered by VC/SC from 134.158.195.141 on Mon May 2 14:02:42 2022Not FixedLinacLinac Commissionning Redpitaya et modulateur icon8.gif Remise en chauffe du modulateur

Reboot des redpitayas pour avoir
le signal HF sur l'IHM
  
  927   Fri Sep 27 17:03:34 2024 MJ HG Shift summaryLinac Commissionning Redemarrage machine apres probleme de synchro et/ou alim Apres un OFF/ON des baies alim et des transfo
+ baie synchro OFF/ON la synchro semble etre
de nouveau alive
 ICT.pngbpmLI.png 
  149   Fri Nov 5 09:35:19 2021 Entered by Super Team from 134.158.195.141 on Fri Nov 5 09:35:02 2021FixedInfoDiag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning Redemarrage 05/11 9h35 icon4.gif Après coupure électrique
de cette nuit. Rédemarrage de tous
les systèmes :
  
  853   Mon Mar 4 08:58:01 2024 Entered by Super Team from 134.158.195.141 on Mon Mar 4 08:57:45 2024Under ProcessShift summaryRing | Ring Commissioning Recomissioning of the SR, search for the revolution frequency  08h50 Start up of the machine

- Problem  with the vaccum,
the valves around the RF cavity are down.
  
  850   Fri Mar 1 10:30:38 2024 VK, VM, ICUnder ProcessShift summaryRing | Ring Commissioning Recomissioning of the SR, search for the revolution frequency  8h50 Start of the machine

Laser amplifier was somehow OFF.
Very strange situation and not clear why
 13x 
  851   Fri Mar 1 10:39:04 2024 VK, VM, IC on Thu Feb 29 Under ProcessShift summaryRing | Ring Commissioning Recomissioning of the SR, search for the revolution frequency  Start of the machine 9h

Optimization of the beam transport
to the Ring.
 Screenshot_from_2024-02-29_12-15-58.pngScreenshot_from_2024-02-29_14-27-36.pngScreenshot_from_2024-02-29_11-27-21.png 
  Draft   Thu Mar 7 08:58:28 2024 VK, VM, ICUnder ProcessShift summaryRing Commissioning Recomissioning of the SR, search for the X-rays 8h50 Warming up the machine

Problem with the vaccum around
the RF cavity (see screenshot attached).
 Screenshot_from_2024-03-07_09-02-36.png 
  1062   Wed Apr 30 08:51:08 2025 VC, DN, MJ, IC, VMUnder ProcessShift summaryLinac Commissionning | Ring Commissioning Recherche position image camera MRSV Start chauffage 9H

There were some problems: the phase
section motor was in the wrong position,
 2025-04-30_16-23-33_MRSV_fwhm_trends.png2025-04-30_17-14-26_total_beam.png2025-04-30_17-15-03_coupe_moitie_basse.png2025-04-30_17-15-54_coupe_moitie_haute.png 
  168   Wed Nov 17 14:00:28 2021 Entered by Super Team from 134.158.195.142 on Wed Nov 17 14:00:15 2021FixedFixDiag | Linac Commissionning Recherche du signal ICT après la section Alexandre Moutardier :

Signal ICT (ER/CA/RAC.05-ELR.01-WAC.02
channel CH3) pas visible après
 2021-11-17_14_19_8_scan_charge_phase_TL1.jpg2021-11-17_14_20_22_scan_charge_phase_Li.jpg 
  330   Mon Feb 14 10:12:10 2022 Entered by Moutardier Alexandre from 134.158.195.142 on Mon Feb 14 10:11:53 2022Under ProcessFixSY Recette synchro Nouvelle recette synchro par défault
enregistré : 20220201_reference.xml

A tester en faisceau dans la journée.
  