  1127   Fri Sep 19 14:49:23 2025 DN, KD, NDUnder ProcessShift summaryRing | Diag Prises de données MRSV et Streak camera Matin: Alignement.

Apres midi tentative de voir du
faisceau en salle laser.
  
  1128   Thu Sep 25 08:17:57 2025 KD, VM, ICUnder ProcessShift summaryRing | Ring Commissioning shift du 25 septembre 2025 8h05: mise en chauffe en remote de la machine
(modulateur, frigo/chiller, laser)

==> cyclage aimant plante, donc
 Screenshot_from_2025-09-25_12-16-58.pngScreenshot_from_2025-09-25_17-43-12.pngScreenshot_from_2025-09-25_17-05-57.png 
  1130   Tue Sep 30 08:41:41 2025 KDUnder ProcessShift summaryOpt | Linac Commissionning | Ring Commissioning shift du 30 septembre 2025 8h40: mise en chauffe en remote (frigo/chiller,
modulateur, laser)

9h30: ajout de graisse sur le verrin
  
  Draft   Wed Oct 1 07:42:45 2025 KD, IC, VMUnder ProcessShift summaryRing Commissioning shift du 1e octobre 2025 7h40: mise en chauffe à distance
(modulateur, frigo/chiller, laser, cyclage)

==> IHM cyclage très longue
 Capture_d’écran_2025-10-01_074548_IHM_cyclage.png 
  1132   Thu Oct 2 08:32:08 2025 Entered by Super Team from 134.158.195.141 on Thu Oct 2 08:31:43 2025Under ProcessShift summaryLI  08h30 ThomX warm-up

08h37 Cycling all magnets

10h20 HV is ON
  
  1133   Fri Oct 3 09:08:29 2025 ND VCUnder ProcessShift summaryLinac Commissionning Shift summary Demarrage machine 9H

test cyclage: OK (relecture courant
parfois NAN)
  
  1134   Thu Oct 9 08:37:45 2025 Entered by Super Team from 134.158.195.141 on Thu Oct 9 08:37:29 2025Under ProcessShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning Shift "du Jeudi" : VM/HG/KD/DN/RC 09h35 Warmup ThomX

09h40 Cycling all magnets

09h50 Start Chillers
 Screenshot_from_2025-10-09_16-57-23.pngScreenshot_from_2025-10-09_16-50-25.pngScreenshot_from_2025-10-09_16-50-12.pngScreenshot_from_2025-10-09_17-17-57.png 
  1136   Mon Oct 13 13:40:05 2025 HaygUnder ProcessInfoLinac Commissionning Emittance QP3  QP3 scan

vary Soleno
Iris 1mm ATT 400 (150 pC)
  
  1137   Tue Oct 14 08:00:18 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 14 octobre 2025 7h55: mise en chauffe en remote (laser,
frigo/chiller, modulateur, cyclage)

==> Nouvelle interface de cyclage,
 8x 
  Draft   Thu Oct 16 07:37:52 2025 KD, IC, VMUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 16 octobre 2025 7h30: mise en chauffe en remote (chillers/frigo,
laser, cyclage)

==> impossible de passer en
 6x 
  1141   Thu Oct 23 07:45:25 2025 KD RC VC MJUnder ProcessShift summaryLI | TL | LE | Ring | Linac Commissionning | Ring Commissioning shift du 23 octobre 2025 7h45: mise en chauffe en remote (modulateur,
laser, frigo/chillers, cyclage)
8h45 : mise en route Modulateur
  
  Draft   Fri Oct 24 08:33:30 2025 Entered by Super Team from 134.158.195.141 on Fri Oct 24 08:33:07 2025Under ProcessShift summary    08h32 Warm-up ThomX: Modulator, Laser,
Fridge

08h37 Chilers were started, cycling
  
  Draft   Tue Oct 28 08:40:22 2025 Entered by Super Team from 134.158.195.141 on Tue Oct 28 08:40:06 2025Under ProcessShift summary    08h40 Warm-up ThomX: Modulator, Laser,
Fridge

08h45 Chillers were started, cycling
 Screenshot_from_2025-10-28_11-48-31.pngScreenshot_from_2025-10-28_11-47-12.pngScreenshot_from_2025-10-28_11-46-55.pngScreenshot_from_2025-10-28_15-34-03.png 
  Draft   Thu Oct 30 07:21:22 2025 Entered by Marie Jacquet from 134.158.205.9 on Thu Oct 30 07:21:05 2025Under ProcessShift summaryLI | TL | LE | Ring Programme shift (X-rays spectres vs atte & phases) 08h17 Warm-up ThomX: Modulator, Laser,
Fridge

08h24 Chillers were started, cycling
  
  Draft   Thu Nov 6 08:30:52 2025 Entered by Super Team from 134.158.195.141 on Thu Nov 6 08:30:37 2025Under ProcessUrgentTL | LE   08h30  Warm-up ThomX: Modulator,
Laser, Fridge

08h36 Chillers were started,
 SectOutput20251030.pngSectOutput20251106.png 
  1147   Fri Nov 7 18:45:54 2025 Entered by Super Team from 134.158.205.4 on Fri Nov 7 18:45:38 2025Under ProcessShift summaryLinac Commissionning   08h34  Warm-up ThomX: Modulator, Laser,
Fridge

08h40 Chillers were started,
 Screenshot_from_2025-11-07_16-24-10.pngScreenshot_from_2025-11-07_16-24-35.pngScreenshot_from_2025-11-07_16-23-58.png 
  1149   Wed Nov 12 10:29:49 2025 Entered by Super Team from 134.158.76.9 on Wed Nov 12 10:29:34 2025Under ProcessShift summaryLI | TL | Ring   15h09 Cycling all magnets

15h12 HV is ON

15h15 The modulator was set to
  
  1151   Tue Nov 18 07:56:42 2025 KDUnder ProcessShift summaryLinac Commissionning shift du 18 novembre 2025 7h50: mise en chauffe en remote de la machine
(laser, frigo/chiller, cyclage)

==> le modulateur ne répond
 2025-11-18_10_56_51_li_op_las_02_RAW.png 
  1152   Tue Nov 18 11:11:33 2025 HG, JM, NDUnder ProcessShift summaryLI Prise de données 18/11 9h Intervention laser

Intervention pour realignement
el/dg/sst.01
  
  1153   Wed Nov 19 10:43:41 2025 HG + JM + ND (aprem)Under ProcessInfoLI | TL | LE Shift mesure Twiss + Simu icon1.gif 8:30 : demarrage à distance 
 

12:10 : QP7 Scan 1 (Phase section
 7x 