HOME Prise de donnees MML Controle commande Simulations Notes Hardware Ligne X Laser Interaction Diagnostiques Synchronisation
Commissionning Commissionning Preparation Pannes ShiftCheck
  Toutes les notes concernant les Commissionning de ThomX, Page 27 of 62  Not logged in ThomX    logo
ID Date Author Statusdown Type Category Important Subject Icon Text Attachments
  1154   Thu Nov 20 09:26:33 2025 VM, ICUnder ProcessUrgentLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning BBA Ring Goal: Ring BBA

09h14 Unable to start thomx. Need
help. Probably problem with cooling water.
 Errors.jpegScreenshot_from_2025-11-20_14-04-53.png 
  1155   Fri Nov 21 08:02:04 2025 KD MJ DN StudentsUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 21 novembre 2025 8h: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)
9h: start 
 IMG-20251121-WA0003.jpgIMG-20251121-WA0005.jpg20251121_185206.JPG 
  1156   Mon Nov 24 13:22:59 2025 ND + JM + HGUnder ProcessShift summaryLI Prise de données 24/11  9:15 Mise en chauffe

9h30 Arrivée du SPR: testsSSI
ce matin => pas de faisceau avant midi
  
  1157   Tue Nov 25 09:32:03 2025 Entered by Super Team from 134.158.195.141 on Tue Nov 25 09:31:46 2025Under ProcessShift summaryDiag | Ring Commissioning   09h31 Warm-up ThomX: Modulator, Laser,
Fridge

09h36 Chillers were started,
  
  1158   Wed Nov 26 07:47:52 2025 KD MJ VM DN RCUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 26 novembre 2025 7h50: mise en chauffe à distance
(frigo/chiller, laser, modulateur, cyclage)

11h13 Beam is in the ring, 50 MeV,
 8x 
  1159   Thu Nov 27 08:01:20 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 27 novembre 2025 8h: mise en chauffe à distance (modulateur,
frigo/chiller, laser, cyclage)

9h30: Chargement de la recette
 multi_disps.txtrecipe_recipe_LI_TL_RI_all_20251126_09_35_14.txtBeam_no_opt.tifBeam_opt.tifBPM_jitters.png 
  1163   Fri Dec 5 08:31:59 2025 Entered by Super Team from 134.158.195.141 on Fri Dec 5 08:31:45 2025Under ProcessShift summaryRing Commissioning   08h31 Warm-up ThomX: Modulator, Laser,
Fridge

08h36 Chillers were started, cycling
  
  1165   Tue Dec 9 08:00:00 2025 KD MJ RC DNUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 09 décembre 2025 - 70 MeV et 40 MeV 8h : mise en chauffe en remote (modulateur,
cyclage, frigo/chillers, laser)

Stockage 70MeV ok, le faisceau 
 6x 
  1166   Wed Dec 10 10:45:33 2025 Entered by Super Team from 134.158.195.141 on Wed Dec 10 10:45:16 2025Under ProcessShift summaryLinac Commissionning   8h30 : machine started on remote
50 MeV operation.
Problem with Yag-TL camera
  
  1167   Thu Dec 11 08:38:30 2025 VM, ICUnder ProcessShift summaryDiag | Ring Commissioning 40 MeV operation 8h37 Warm-up ThomX: Modulator, Laser, Fridge

8h44 Chillers were started, cycling
all magnets.
 12x 
  1168   Fri Dec 12 08:40:50 2025 VM, ICUnder ProcessShift summaryRing Commissioning Check of the 70 MeV with MRSV, Ring studies 08h40 Warm-up ThomX: Modulator, Laser,
Fridge

8h45 Chillers were started, cycling
 Screenshot_from_2025-12-12_14-02-43.pngScreenshot_from_2025-12-12_14-02-27.pngScreenshot_from_2025-12-12_14-02-14.pngScreenshot_from_2025-12-12_14-02-02.pngScreenshot_from_2025-12-12_14-01-35.png 
  1169   Mon Dec 15 08:06:26 2025 KD MJUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 15 décembre 2025 8h: mise en chauffe en remote (chiller/frigo,
laser, modulateur, cyclage)

* cannot enter to the ring with
  
  1170   Tue Dec 16 07:18:46 2025 KD, IC, RC,VM Under ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 16 décembre 2025 7h10: mise en chauffe en remote (chiller/frigo,
laser, cyclage, modulateur).

à cause du faible flux d'hier
 2025-12-16_08_30_21_tl_dg_sst_02-ccd_01_RAW.png2025-12-16_08_35_25_tl_dg_sst_02-ccd_01_RAW.png 
  Draft   Wed Dec 17 07:17:06 2025 KD, IC, MV, DN,Under ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 17 décembre 2025 7h15: mise en chauffe en remote (chiller/frigo,
laser, modulateur, cyclage)

8h33 HV ON
  
  1173   Fri Dec 19 07:22:31 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 19 décembre 2025 7h20: mise en chauffe en remote (frigo/chiller,
laser, modulateur, cyclage)

 
  
  1175   Tue Jan 6 08:00:18 2026 KDUnder ProcessShift summaryLinac Commissionning shift du 06 janvier 2026 8h: mise en chauffe en remote (cyclage,
modulateur, frigo/chillers, laser)

problème lancement cyclage
 2026-01-06_19_17_58_tl_dg_sst_03-ccd_01_RAW.png2026-01-06_19_17_20_tl_dg_sst_03-ccd_01_RAW.png 
  1176   Wed Jan 7 07:55:45 2026 VM DN MJ KDUnder ProcessShift summaryLI | TL | LE | Ring | Linac Commissionning | Ring Commissioning shift du 07 janvier 2026 7h55: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)
11h25 HV is ON
 16x 
  1177   Thu Jan 8 09:07:08 2026 IC, HG, RC, DN, JMUnder ProcessShift summaryLI | TL | LE | Ring | Linac Commissionning | Ring Commissioning Test of the new receipt from BMAD Isol = 242 A 8h55: mise en chauffe (modulateur, frigo/chillers,
laser, cyclage)

10h20 HV ON
 13x 
  1178   Fri Jan 9 08:05:32 2026 KD, IC, VM, RCUnder ProcessShift summaryRF D1 | Linac Commissionning | Ring Commissioning shift du 9 janvier 2026 8h05: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)

09h06 HV is ON
 6x 
  1179   Mon Jan 12 13:51:05 2026 HaygUnder ProcessInfoLI | TL Monday Shift : Q-scan + Data (Active Learning) icon1.gif Mesures du jour : 


Quad scans à QP1
pour voir d'autres points de fonctionnement
  
ELOG V3.1.4-395e101