1154
|
Thu Nov 20 09:26:33 2025 |
VM, IC | Under Process | Urgent | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
BBA Ring | | Goal: Ring BBA
09h14 Unable to start thomx. Need
help. Probably problem with cooling water. |
 |
|
1155
|
Fri Nov 21 08:02:04 2025 |
KD MJ DN Students | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 21 novembre 2025 | | 8h: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)
9h: start |
  |
|
1156
|
Mon Nov 24 13:22:59 2025 |
ND + JM + HG | Under Process | Shift summary | LI |
|
Prise de données 24/11 | | 9:15 Mise en chauffe
9h30 Arrivée du SPR: testsSSI
ce matin => pas de faisceau avant midi |
|
|
1157
|
Tue Nov 25 09:32:03 2025 |
Entered by Super Team from 134.158.195.141 on Tue Nov 25 09:31:46 2025 | Under Process | Shift summary | Diag | Ring Commissioning |
|
| | 09h31 Warm-up ThomX: Modulator, Laser,
Fridge
09h36 Chillers were started, |
|
|
1158
|
Wed Nov 26 07:47:52 2025 |
KD MJ VM DN RC | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 26 novembre 2025 | | 7h50: mise en chauffe à distance
(frigo/chiller, laser, modulateur, cyclage)
11h13 Beam is in the ring, 50 MeV, |
8x |
|
1159
|
Thu Nov 27 08:01:20 2025 |
KD | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 27 novembre 2025 | | 8h: mise en chauffe à distance (modulateur,
frigo/chiller, laser, cyclage)
9h30: Chargement de la recette |
    |
|
1163
|
Fri Dec 5 08:31:59 2025 |
Entered by Super Team from 134.158.195.141 on Fri Dec 5 08:31:45 2025 | Under Process | Shift summary | Ring Commissioning |
|
| | 08h31 Warm-up ThomX: Modulator, Laser,
Fridge
08h36 Chillers were started, cycling |
|
|
1165
|
Tue Dec 9 08:00:00 2025 |
KD MJ RC DN | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 09 décembre 2025 - 70 MeV et 40 MeV | | 8h : mise en chauffe en remote (modulateur,
cyclage, frigo/chillers, laser)
Stockage 70MeV ok, le faisceau |
6x |
|
1166
|
Wed Dec 10 10:45:33 2025 |
Entered by Super Team from 134.158.195.141 on Wed Dec 10 10:45:16 2025 | Under Process | Shift summary | Linac Commissionning |
|
| | 8h30 : machine started on remote
50 MeV operation.
Problem with Yag-TL camera |
|
|
1167
|
Thu Dec 11 08:38:30 2025 |
VM, IC | Under Process | Shift summary | Diag | Ring Commissioning |
|
40 MeV operation | | 8h37 Warm-up ThomX: Modulator, Laser, Fridge
8h44 Chillers were started, cycling
all magnets. |
12x |
|
1168
|
Fri Dec 12 08:40:50 2025 |
VM, IC | Under Process | Shift summary | Ring Commissioning |
|
Check of the 70 MeV with MRSV, Ring studies | | 08h40 Warm-up ThomX: Modulator, Laser,
Fridge
8h45 Chillers were started, cycling |
    |
|
1169
|
Mon Dec 15 08:06:26 2025 |
KD MJ | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 15 décembre 2025 | | 8h: mise en chauffe en remote (chiller/frigo,
laser, modulateur, cyclage)
* cannot enter to the ring with |
|
|
1170
|
Tue Dec 16 07:18:46 2025 |
KD, IC, RC,VM | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 16 décembre 2025 | | 7h10: mise en chauffe en remote (chiller/frigo,
laser, cyclage, modulateur).
à cause du faible flux d'hier |
 |
|
Draft
|
Wed Dec 17 07:17:06 2025 |
KD, IC, MV, DN, | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 17 décembre 2025 | | 7h15: mise en chauffe en remote (chiller/frigo,
laser, modulateur, cyclage)
8h33 HV ON |
|
|
1173
|
Fri Dec 19 07:22:31 2025 |
KD | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 19 décembre 2025 | | 7h20: mise en chauffe en remote (frigo/chiller,
laser, modulateur, cyclage)
|
|
|
1175
|
Tue Jan 6 08:00:18 2026 |
KD | Under Process | Shift summary | Linac Commissionning |
|
shift du 06 janvier 2026 | | 8h: mise en chauffe en remote (cyclage,
modulateur, frigo/chillers, laser)
problème lancement cyclage |
 |
|
1176
|
Wed Jan 7 07:55:45 2026 |
VM DN MJ KD | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
shift du 07 janvier 2026 | | 7h55: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)
11h25 HV is ON |
16x |
|
1177
|
Thu Jan 8 09:07:08 2026 |
IC, HG, RC, DN, JM | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
Test of the new receipt from BMAD Isol = 242 A | | 8h55: mise en chauffe (modulateur, frigo/chillers,
laser, cyclage)
10h20 HV ON |
13x |
|
1178
|
Fri Jan 9 08:05:32 2026 |
KD, IC, VM, RC | Under Process | Shift summary | RF D1 | Linac Commissionning | Ring Commissioning |
|
shift du 9 janvier 2026 | | 8h05: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)
09h06 HV is ON |
6x |
|
1179
|
Mon Jan 12 13:51:05 2026 |
Hayg | Under Process | Info | LI | TL |
|
Monday Shift : Q-scan + Data (Active Learning) |
| Mesures du jour :
Quad scans à QP1
pour voir d'autres points de fonctionnement |
|