icon3.gif   MJ VC KD RC DN; Shift summary 19/11/2024 YAG_TL3_beam.pnginjection_ring.pngFluo_det.png
Entry   VM Entered by Super Team from 134.158.195.141 on Thu Nov 21 08:26:43 2024;  
Entry   KD, RC; shift du 22 novembre 2024 TL_BPM4_locked.dat
Entry   MJ RC KD; shift du 26 novembre 2024 2024-11-26_12_22_06_el_dg_sst_01-ccd_01_RAW_1.png
Entry   VC; Shift summary 27/11 QP1_scan.pngQP2_scan.pngQP3_scan.png
Entry   VM, IC, VK ;  
Entry   VC, Carlos Buitrago, Sudhanshu Thakur, ND; TP 29-11--2024 
Entry   SC, HG, VM; Passage à 61.5MeV et 70 MeV screenshot_steerers_linac_findejournée.pngBeam_transmission_Sole.png
Entry   VM Entered by Super Team from 134.158.195.141 on Thu Dec 5 08:31:12 2024;  
Entry   VM, IC, VK, HG ;  8x
Entry   VM,HG,SC; 50 and 70 MeV Emittance, and transport  Q_vs_SolenoScan_at_16-52-02_Q1_Off.pngQ_vs_SolenoScan_at_16-39-39_recette_good_xrays.png
Entry   KD, VC, RC MJ; shift du 11 décembre 2024 Screenshot_2024-12-11_11-51-40_min_synchrotron_deb_aller_m1_2mmY.pngScreenshot_2024-12-11_11-51-40_min_synchrotron_fin_aller_m1_2mmY.pngScreenshot_2024-12-11_11-51-40_max_synchrotron_deb_aller_m1_2mmY.pngScreenshot_2024-12-11_12-39-36_min_synchrotron_deb_retour_0mmY.png
Entry   KD, RC, MJ, VM, IC, VK; shift du 12 décembre 2024 7x
Entry   VM, IC, VK;  Screenshot_from_2024-12-13_11-28-46.pngScreenshot_from_2024-12-13_14-44-28.pngScreenshot_from_2024-12-13_14-46-59.png
Entry   KD; shift du 17 décembre 2024 
Entry   VC; summary shift Dec 18  
Entry   IC, VK, VM;  
Entry   VC,ND; Shift summary 20/12 10x
Entry   VC MJ HG; Shift summary 07/01/25 
Entry   IC, VK, VM, ND;  15x