Entry   Entered by Super Team from 127.0.0.1 on Wed Jul 8 07:49:04 2026;  
07h50 Start-up modulator, laser, fridge, chillers, cycling remotly
Entry   Entered by Super Team from 127.0.0.1 on Wed Jul 1 11:24:31 2026;  
 

 

 
Entry   Entered by Super Team from 127.0.0.1 on Tue Jun 30 09:48:28 2026;  
Maher started the modulator

9h50 HV is on

09h53 Beam is in the ring w/o RF
Entry   VC; redpitaya 
Les redpitaya baie 17 'RF" ne "communiquent" plus avec JIVE.

IL faut les redémarrer... je ne sais pas faire!

Nicolas passe en fin de matinée pour essayer de les redémarrer
Entry   IC, VM; Restart of the accelerator 
07h30 Start-up modulator, laser, fridge, chillers, cycling remotly

Vacuum in the FPC is still ~1e-7 (sometimes goes to ~7-8e-8);

No RF signals. The same problem.
Entry   IC, VM; Restart of the accelerator Screenshot_from_2026-06-26_15-41-00.pngIMG-20260626-WA0001.jpgScreenshot_from_2026-06-26_16-07-50.pngScreenshot_from_2026-06-26_17-17-00.png
08h26 Start-up modulator, laser, fridge, chillers, cycling

09h31 Low SF6 pressure => JN helped

11h HV ON. We do not see the RF signals, even  the baselines (RedPitaya).
Entry   Entered by Super Team from 127.0.0.1 on Tue Jun 23 09:43:18 2026; Vaccum in the FPC 
09h00 Start-up modulator, laser, fridge, chillers

After discussion with Daniele

Goal/Priority: Check for leakage in the FPC
Entry   IC, VM; Restart of the accelerator 
09h35 Start-up modulator

09h52 Start the fridge

09h55 Start chillers
Entry   IC, VM; Ring working point studies 
07h35 Start-up modulator (does not go to standby), laser, magnets, cycling.

9h50 HT ON

~10h30 Electricity cut
Entry   IC, VM; Restart of the accelerator Screenshot_from_2026-06-17_15-54-18.pngScreenshot_from_2026-06-17_15-50-21.png
08h35 Start-up modulator (it was already on standby), laser, magnets, cycling.

As yesterday there is a problem with the MPS to start the machine. We are trying to investigate whether it is related to the vacuum or something
else.
Entry   Entered by Super Team from 127.0.0.1 on Tue Jun 16 13:43:02 2026;  
Hello,

I short-circuit the MPS input to modulator, we can trig modulator, the klystron filmant time goes to full time   , need 45 min, you can start at 14:35
Entry   IC, VM; Restart of the accelerator 
11h20 Try to restart the accelerator. Start-up modulator, laser, fridge, chillers

Problem, with all magnets control All DS are in FAULT state. Help is needed.

It is solved.
Entry   Kevin D.; Laser PC status 
mise à jours du post : https://elog.lal.in2p3.fr/THOMX/Commissionning/1188

** Laser PC ***

- Sortie Laser: 120 uJ 
Entry   Entered by Super Team from 127.0.0.1 on Tue Jun 9 10:13:08 2026;  
10h02 Start-up modulator, laser, fridge, chillers

The SF6 pressure is low. Magnet power supplies filed to start.

11h17 Stop ThomX
Entry   IC, VM; Restart of the accelerator GunCharge_vs_LaserAtt.pngGunDarkCurrent_vs_Att.png
08h45 Start-up modulator, laser, magnets

09h38 Shutter Laser Linac is yellow. Tuning off the gun operation key does not change it to the red. Need help.

09h55 HV is on
Entry   IC, HG, JNC; Restart of the accelerator 
02/06/2026

~15h30 Starting all system

16h Start up of the modulator, laser, magnets
Entry   Entered by Super Team from 127.0.0.1 on Wed May 13 08:35:01 2026; manip Gplast 
demarrage machine 8h30

faisceau ok vers 10H

14h mesure 50 MeV
Entry   Entered by Super Team from 127.0.0.1 on Tue May 12 08:42:31 2026; manip Gplast Screenshot_from_2026-05-12_10-33-26.png
Demarrage machine 8h40

pB reflechi canon... temp consigne 27.7C

10h50 redemarrage chiller gun ... 
Entry   Vincent; Manip Gplast 
9h30 test radioprotection OK (mesure en dessous du bruit de fond)

13h30 fenetre installée pompage en cours

14h fin de l'intervention
Entry   Entered by Super Team from 127.0.0.1 on Fri Apr 24 08:05:02 2026; , entered from 127.0.0.1 
8h00 : mise en chauffe en remote (frigo/chillers, laser, modulateur, cyclage)