Message ID: 1255     Entry time: Tue Jun 30 09:49:22 2026
 Author: Entered by Super Team from 127.0.0.1 on Tue Jun 30 09:48:28 2026 
 Status:  
 Type:  
 Category:  
 Important:
 Subject:  
 Icon:  

Maher started the modulator

9h50 HV is on

09h53 Beam is in the ring w/o RF

10h30 Beam is in the ring with RF

The network is extremly slow on client 1. Impossible to start terminal or execute the commands. Client 2 is slow but still works. 

11h15 Beam is in the ring with RF at good frequency. Rigol is working properly. Thanls to Nicolas.

 