Entry   Kevin D.; Laser PC status 
mise à jours du post : https://elog.lal.in2p3.fr/THOMX/Commissionning/1188

** Laser PC ***

- Sortie Laser: 120 uJ 
Entry   Entered by Super Team from 127.0.0.1 on Tue Jun 9 10:13:08 2026;  
10h02 Start-up modulator, laser, fridge, chillers

The SF6 pressure is low. Magnet power supplies filed to start.

11h17 Stop ThomX
Entry   IC, VM; Restart of the accelerator GunCharge_vs_LaserAtt.pngGunDarkCurrent_vs_Att.png
08h45 Start-up modulator, laser, magnets

09h38 Shutter Laser Linac is yellow. Tuning off the gun operation key does not change it to the red. Need help.

09h55 HV is on
Entry   IC, HG, JNC; Restart of the accelerator 
02/06/2026

~15h30 Starting all system

16h Start up of the modulator, laser, magnets
Entry   Entered by Super Team from 127.0.0.1 on Wed May 13 08:35:01 2026; manip Gplast 
demarrage machine 8h30

faisceau ok vers 10H

14h mesure 50 MeV
Entry   Entered by Super Team from 127.0.0.1 on Tue May 12 08:42:31 2026; manip Gplast Screenshot_from_2026-05-12_10-33-26.png
Demarrage machine 8h40

pB reflechi canon... temp consigne 27.7C

10h50 redemarrage chiller gun ... 
Entry   Vincent; Manip Gplast 
9h30 test radioprotection OK (mesure en dessous du bruit de fond)

13h30 fenetre installée pompage en cours

14h fin de l'intervention
Entry   Entered by Super Team from 127.0.0.1 on Fri Apr 24 08:05:02 2026; , entered from 127.0.0.1 
8h00 : mise en chauffe en remote (frigo/chillers, laser, modulateur, cyclage)
Entry   IC, VM;  
9h00 : mise en chauffe en remote (frigo/chillers, laser, modulateur, cyclage)
Entry   IC,VM;  
Dalkia solved the problem with vooling circuit in the morning

10h15 mise en chauffe  (frigo/chillers, modulateur, laser, cyclage)

11h16 HV is ON
Entry   KD, VM; shift du 21 avril 2026 
7h30 : mise en chauffe en remote (frigo/chillers, laser, modulateur, cyclage) ==> dipôles non cyclé (en défaut) ==>
défaut acquité et cyclage fait.

8h20 : intervention sur le laser PC. Le shutter de la salle laser était resté bloqué. Le faisceau semble revenu à
Entry   IC;  
10h30 : mise en chauffe  (frigo/chillers, modulateur, laser, cyclage)

All rondes are broken, THOMX key is turned. What is the reason of this intervention?,  There is nobody around. Jean-Noel came and helped
to solve the problems.
Entry   IC,VM, HG, RC, DN; beam studies. FPC.  
7h30 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

08h45 HV is on

Laser camera does not work. Help!!!
Entry   Entered by Super Team from 127.0.0.1 on Thu Apr 16 07:32:14 2026; , entered from 127.0.0.1 Screenshot_from_2026-04-16_20-53-14.pngScreenshot_from_2026-04-16_20-53-34.png
7h30 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

9h00 HV is ON

10h33 Energy = 50 MeV, Laser Phase 77 dg., Sect. Phase 217 dg., Sect. Att. 2.546 dB, I_Gun -98.9021 pC, I_Linac -131.1291 pC, I_TL -120.2702
Entry   KD MJ RC DN VK; ENERGY/ANGLE 40 MeV - 15 avril 2026 
8h05: mise en chauffe à distance (frigo/chillers, modulateur, laser, cyclage)

*** Programme : Mesure spectre angulaire @40MeV

Matin : probleme de stockage faisceau 40 MeV
Entry   IC,VM; Beam studies. preparation for 40 MeV 
8h00 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

10h Problem with modulator; It went to OFF and it does not start. Need help;

12h40 Fixed by Maher
Entry   IC,VM;  
7h40 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

08h43 HV is ON

recipe_recipe_LI_TL_RI_all_20260409_17_07_05.txt loaded
Entry   IC,VM;  
8h10 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

09h12 HV is ON

recipe_recipe_TL_all_20260408_17_18_54.txt loaded
Entry   7h50 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage); , entered from 127.0.0.1 
7h30 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

8h30 HV is ON

recipe_recipe_LI_TL_RI_all_20260402_14_37_41.txt loaded
Entry   IC,VM, KD, DN, MJ; MONO 61.5 MeV - 07 avril 2026 
7h50 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)
09h30 HV is ON

10h23 Energy = 61.5 MeV, Laser Phase 39 dg., Sect. Phase 225 dg., Sect. Att. 0.952 dB, I_Gun -78.1953 pC, I_Linac -122.7687 pC, I_TL -102.6104