HOME SBOX THOMX MINICAV Utilities
THOMX orders THOMX installation THOMX commissioning THOMX control command
  Status of commissioning, report also here plots are reports., Page 8 of 24  Not logged in ELOG logo
    Reply   Restarting equipements after Christmas shutdown, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
this morning, I set the Ring frequency at 500.25MHz and after switching ON the power supply of the amplifiers for the RF signal coming from the laser,
I saw the beating frequency  (between ring RF and laser harmonic frerquencies at 500.25MHz) that I canceled, playing with the Smaract motor.

Now, I need to adjust the FP-cavity length to follow the laser cavity length but the IcePap DS (controlling the FP-cavity motor) freezes too
    Reply   Restarting equipements after Christmas shutdown, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
on last friday (12/01/2024), the IcePap DS issue was solved and I was able to control the FP-cavity motors properly.
I was able to quickly lock either the laser on the FP-cavity and the FP-cavity on the RF reference as before.

then, we can close these posts on restarting the equipments after the Christmas shutdown
Entry   Removing high order modes, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | detectors and electronics 
this morning we locked the laser and the FP-cavity with ~ 40kW => some HOM appeared "randomly" depending on the power.

we tried to play manually on the L-shape arm :
- first, we moved horizontally to put the L-shape in the beam axis
    Reply   Removing high order modes, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | detectors and electronics Capture.PNG
here is the picture of the L-shape arm and the inside of the vessel.

this image corresponds to the "zero" position on each positionner.




Ronic
    Reply   Removing high order modes, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | detectors and electronics 
yesterday with Daniele, we tried again to move the arm horizontally and vertically from the "zero position" to have a better understanding
of the beahvior,
but it is roughly the same :
Entry   Remontage mécanique, posted by Ronic Chiche at Optical room about mechanics 
Mail de Yann du 12/10/2018 :

Je vous fais le bilan des actions effectuées :

1/ La mécanique a été remontée avec changement des billes céramiques, soufflet défectueux, ect...
Entry   Remontage des vérins, posted by Ronic Chiche at Optical room about mechanics 
Mail de Yann du 8/10/2018 :

Bonjour,
Tous les vérins sont maintenant OK ! Merci Ronic.
Entry   Recipies for different FPC power, posted by Ronic Chiche at ThomX igloo about lasers and optics 
For ~ 46kW power in the FP-cavity:


Alplhanov amplifier ratio : 20%
 
Axis 18 position : -0004710 steps
    Reply   Recipies for different FPC power, posted by Ronic Chiche at ThomX igloo about lasers and optics 
For ~ 23kW power in the FP-cavity:


Alplhanov amplifier ratio : 15%
 
Axis 18 position : -0016014 steps
    Reply   Recipies for different FPC power, posted by Ronic Chiche at ThomX igloo about lasers and optics 


For ~ 66kW power in the FP-cavity:


Alplhanov amplifier ratio : 25%
Entry   Primary vacuum to check dust, posted by Loïc Amoudry at Optical room about mechanics | vacuum Image3.jpgImage6.jpg
The cavity has been cleaned then put under primary vacuum (primary pump without vacuum flow control). Dusts presence was checked at air and no significant
changes have been observed.

1ST image before cleaning
Entry   Powerup with 2.5ps pulses, posted by Loïc Amoudry at Optical room about lasers and optics report.PNGtek00004.png4A.PNG
A power up has been performed on ThomX until 65kW intracavity power. We didn't see any modes but stored power was really unstable since ~60kW (see
image tek00004.png).

Measurement report is shown in the table below. Gain seems to decrease against intracavity power.
Entry   Power shut down on September 23th, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | utilities 
to anticipate the power shut down on next tuesday 23/09,
this afternoon, I switched off all the equipments except the oscillator connected on the UPS.
    Reply   Power shut down on September 23th, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | utilities 
this morning, I restarted all the equipments of the FPC.

everything was fine after being able to get back the correct PDH phase between modulation and demodulation...I got 88kW with 33% amplifier ratio
after basic alignment and CEP tuning.
    Reply   Power shut down on September 23th, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | utilities 
the 33MHz/500MHz RF frequencies from the Ring seems different from the previous state (maybe working at an energy of 50MeV instead of 70MeV which was
the previous energy ?).

so, I let the FPC at the present position and wait to discuss if it is necessary or not to move the FPC motors for the correct energy...
    Reply   Power shut down on September 23th, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | utilities img1.jpg
This morning I did a phase alignment on the PDH signal generator (Rigol DG4102)
this procedure ensure that both phases of the sine wave signals are aligned before finding the correct phase for maximizing the error signal.

so, from now on, in case of power shut down, one just need to :
Entry   Power shut down on Saturday the 18th, posted by Ronic Chiche at ThomX igloo about utilities 
All the equipments have been switched off on Friday 17th due to a power shut down on Saturday 18th :
CW and Onefive oscillators, computers, laser amplifier, cavity mirror motors, chiller, etc...
    Reply   Power shut down on Saturday the 18th, posted by Ronic Chiche at ThomX igloo about utilities 
Today, I restarted all the equipements :

Chiller                                                
: ok, temperature converged quickly to the set temperature : 25°C
Entry   Power shut down on August 29th, posted by Ronic Chiche at ThomX igloo about detectors and electronics 
This morning, all the equipments have been switched off due to a power shut down tomorrow morning.
Only the Onefive oscillator is still ON, connected to the Uninterruptable Power Supply (UPS).
    Reply   Power shut down on August 29th, posted by Ronic Chiche at ThomX igloo about detectors and electronics 
after alignment, CEP adjustment and optimizing the PDH phase, I got back ~92kW in the FPC for 33% amplifier ratio.




Ronic
Chiche wrote:



This morning, all the equipments have been switched off due to
ELOG V3.1.4-395e101