100
|
Mon Jun 27 08:52:46 2022 |
Manar Amer | Fixed | report | lasers and optics | vacuum | Optical room | SBox Finesse at 216.6625 MHz | The Sbox currently has the injection from
ThomX installed T ~ 120 ppm , M2 planar from
Sbox spare and M3 / M4 spherical mirrors |
|
|
104
|
Wed Jul 6 18:39:25 2022 |
Manar Amer | Fixed | report | lasers and optics | vacuum | Optical room | SBox Finesse at 216.6625 MHz | Max Finesse obtained @ 4 mirror setup was
~ 19 300
With M1 from ThomX , M2/M3/M4 from |
|
|
105
|
Wed Jul 6 18:39:38 2022 |
Manar Amer | Fixed | report | lasers and optics | vacuum | Optical room | SBox Finesse at 216.6625 MHz |
|
|
|
75
|
Wed Apr 13 18:42:50 2022 |
Manar Amer | Fixed | report | lasers and optics | utilities | Optical room | Spincoater - Mirrror cleaning | Used the spincoater and pure water to clean
dielectric mirrors which will be installed
inside the SBox for directing the reflection |
  |
|
82
|
Wed Apr 27 22:30:14 2022 |
Manar Amer | Fixed | report | lasers and optics | utilities | Optical room | Spincoater - Mirrror cleaning | Images of the SBox mirrors cleaned at the
same time when the cavity was aligned.
Directly from the spincoater to |
|
|
85
|
Mon May 9 19:27:35 2022 |
Manar Amer | Fixed | report | lasers and optics | utilities | Optical room | Spincoater - Mirrror cleaning | PowerPoint shows the detailed images of
all the mirrors before and after cleaning.
Images of SBox mirrors and M1 from |
    |
|
87
|
Wed May 11 20:51:28 2022 |
Manar Amer | Fixed | report | lasers and optics | utilities | Optical room | Spincoater - Mirrror cleaning | Following the observation that when rotating
M2 plan mirror of SBox the deformation position
of the mode changes. |
  |
|
89
|
Tue May 24 21:51:01 2022 |
Manar Amer | Fixed | report | lasers and optics | utilities | Optical room | Spincoater - Mirrror cleaning | While repeating the alignment, the mirrors
were cleaned using the spin-coater and placed
again. |
|
|
195
|
Wed Feb 28 17:26:46 2024 |
Ronic Chiche | Fixed | info | lasers and optics | software | Optical room | 100W CELIA laser amplifier "how's to" document | 1st version of the document.
if some information is not correct
or missing, give any comment by replying |
|
|
95
|
Wed Jun 8 11:10:17 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | Cavity Lock | Start with the cavity lock images attached,
taken from last week, at
start we have a coupling ~ 5% and started |
  |
|
97
|
Wed Jun 8 11:31:47 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | Cavity Lock | Current setup at SBox for locking the cavity
After spacial matching, the coupling
increased to ~ 15 - 20 % |
  |
|
98
|
Thu Jun 9 19:59:42 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | Cavity Lock | Cavity locked today under vacuum and no
airflow, it is stable over a long time
the alignment was improved and |
  |
|
101
|
Wed Jul 6 18:34:12 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | Cavity Lock | Closing the series for the setup
The cavity was only locked @ 133.33
MHz but the Finesse was not measured |
|
|
115
|
Tue Jul 12 19:07:50 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | CELIA amplifier installation | The amplifier was installed on the optical
table next to SBox table.
The CVBG that will be used for |
|
|
116
|
Fri Jul 22 17:07:32 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | CELIA amplifier installation + chiller | Amplifier placed next to the pulsed laser
on the table under the airflow
The output is in free space with |
  |
|
118
|
Fri Jul 22 18:00:21 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | Alignment / Table setup | The current setup of the optical table
attached.
The cavity is aligned and the lock |
 |
|
119
|
Fri Jul 22 18:19:13 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | CVBG stretching / Fiber Injection | Before injecting into the amplifier, the
pulse needs to be stretched using a CVBG,
type attached. |
7x |
|
120
|
Fri Jul 22 18:25:31 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | CELIA amplifier installation + chiller | The software to control the CELIA amplifier
is on the laptop that was placed in ThomX
bunker. |
|
|
129
|
Fri Aug 19 16:02:33 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | CELIA amplifier installation + chiller | Closing series
|
|
|
130
|
Fri Aug 19 16:03:17 2022 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | software | Optical room | Alignment / Table setup | closing series
|
|