115
Tue Jul 12 19:07:50 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics | software
Optical room
CELIA amplifier installation
The amplifier was installed on the optical
table next to SBox table.
The CVBG that will be used for
116
Fri Jul 22 17:07:32 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics | software
Optical room
CELIA amplifier installation + chiller
Amplifier placed next to the pulsed laser
on the table under the airflow
The output is in free space with
118
Fri Jul 22 18:00:21 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics | software
Optical room
Alignment / Table setup
The current setup of the optical table
attached.
The cavity is aligned and the lock
119
Fri Jul 22 18:19:13 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics | software
Optical room
CVBG stretching / Fiber Injection
Before injecting into the amplifier, the
pulse needs to be stretched using a CVBG,
type attached.
7x
120
Fri Jul 22 18:25:31 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics | software
Optical room
CELIA amplifier installation + chiller
The software to control the CELIA amplifier
is on the laptop that was placed in ThomX
bunker.
129
Fri Aug 19 16:02:33 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics | software
Optical room
CELIA amplifier installation + chiller
Closing series
130
Fri Aug 19 16:03:17 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics | software
Optical room
Alignment / Table setup
closing series
131
Fri Aug 19 16:03:40 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics | software
Optical room
CVBG stretching / Fiber Injection
closing series
64
Mon Jul 5 14:14:01 2021
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
OEwaves CW Laser - Phase Noise
We started measuring the phase
noise on the OEwaves CW laser.
Class
3b
wavelength 1.5 um
The
65
Mon Jul 5 14:40:57 2021
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
OEwaves CW Laser - Phase Noise
a correction on the wavelength of the laser
it is 1030 um
66
Mon Jul 5 14:46:44 2021
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
OEwaves CW Laser - Phase Noise
correction on unit 1030 nm
106
Wed Jul 6 19:57:17 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
2 Mirror Setup @ 216.6 MHz
The SBox cavity setup was changed to have
only 2 mirrors M1 plane and M2 spherical,
both from ThomX
109
Fri Jul 8 17:48:48 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
2 Mirror Setup @ 216.6 MHz
The cavity was realigned using irises instead
of pinholes, gave a better alignment.
The inside of the box, the spherical
110
Fri Jul 8 19:37:24 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
2 Mirror Setup @ 216.6 MHz
Update for Finesse measurement, The cavity
was put under vacuum ~ 1.1*10^-1 mbar
and the alignment and coupling
111
Tue Jul 12 10:07:05 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
FSR change & Finesse Measurements
The FSR of the 2 mirror (plan-spherical)
Cavity was adjusted from 210 MHz to reach
216.643 MHz
112
Tue Jul 12 10:19:30 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
FSR change & Finesse Measurements
Yesterday evening the cavity was Vacuum
pumped up to pressure of 5.5*10^-2 and locked
changed FSR to be 216.662 MHz and
113
Tue Jul 12 14:41:55 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
FSR change & Finesse Measurements
a Finesse of 30k with the present mirrors
:
T1=120 ppm ;A1=(2.6+1) ppm;
114
Tue Jul 12 18:53:55 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
Installation of D-shaped mirror / Alignment
To prepare for the amplifier. I installed
the D-shapped mirrors after cleaning (using
aceton and ethanol) between the cavity 2
117
Fri Jul 22 17:10:06 2022
Manar Amer
Fixed
report
lasers and optics | detectors and electronics
Optical room
Installation of D-shaped mirror / Alignment
The D-shaped mirrors are installed properly
and not cutting the path of the beam.
The cavity has been aligned again
126
Thu Aug 11 19:27:09 2022
Ronic Chiche
Fixed
info
lasers and optics | detectors and electronics
Optical room
Koheras CW laser lock on FP cavity
I locked the Koheras CW on the FP cavity
but the lock was pretty noisy and very difficult
to acquire.