  Toutes les notes concernant les Commissionning de ThomX, Page 61 of 62  Not logged in ThomX    logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Status Type Category Important Subjectdown Icon Text Attachments
  Draft   Wed May 28 17:29:56 2025 KD,VM,ICUnder ProcessShift summaryRing Commissioning   08h00 ThomX was started

Goals:
Emittance measurements, ring optics study
 EmittanceVsGunPhase.pngScreenshot_from_2025-05-28_11-28-14.png 
  Draft   Fri Jun 6 08:17:31 2025 MV Entered by Super Team from 134.158.195.141 on Fri Jun 6 08:17:16 2025Under ProcessShift summaryRing Commissioning   08h15 ThomX was started; Modulator,
Frig, Laser

08h21 Chillers were started,
 ThomX_PhaseChargeScan20250606.pngThomX_FPC_TableVerticalScan20250606.png 
  Draft   Fri Jun 13 08:41:04 2025 VM,ICUnder ProcessShift summaryLinac Commissionning   08h40 ThomX was started: Modulator,
Frig, Laser

08h45 Chillers were started,
 health_check_Diag_charge_wavecatcher_2025_06_13_10_13.pngScreenshot_from_2025-06-13_11-11-22.pngScreenshot_from_2025-06-13_14-31-57.pngScreenshot_from_2025-06-13_14-31-45.png 
  1095   Fri Jun 27 08:49:36 2025 SC, ND LinacLI | Linac Commissionning   8h49 allumage modulateur, chiller, laser

10h00 Beam ON

Prise de données Cf images
 pos_TL2_vs_phase_RF.pngpos_TL2_spX_vs_temp.pngtp2spX_vs_time.png 
  1097   Wed Jul 2 14:45:20 2025 Entered by Super Team from 134.158.195.141 on Wed Jul 2 14:45:07 2025Under ProcessInfoLI   Vérif position laser photocathode
:

--> bouge de 1mm en Y et 0.2
  
  Draft   Tue Oct 21 12:29:35 2025 HG, DN. VM, MJ      11h40 Thomx warm-up

12h35 HV is ON

12h40 HV 1215 V
 mrsv_2_positions_fente.png 
  Draft   Fri Oct 24 08:33:30 2025 Entered by Super Team from 134.158.195.141 on Fri Oct 24 08:33:07 2025Under ProcessShift summary    08h32 Warm-up ThomX: Modulator, Laser,
Fridge

08h37 Chilers were started, cycling
  
  Draft   Tue Oct 28 08:40:22 2025 Entered by Super Team from 134.158.195.141 on Tue Oct 28 08:40:06 2025Under ProcessShift summary    08h40 Warm-up ThomX: Modulator, Laser,
Fridge

08h45 Chillers were started, cycling
 Screenshot_from_2025-10-28_11-48-31.pngScreenshot_from_2025-10-28_11-47-12.pngScreenshot_from_2025-10-28_11-46-55.pngScreenshot_from_2025-10-28_15-34-03.png 
  Draft   Wed Nov 5 12:50:55 2025 Entered by Super Team from 134.158.195.141 on Wed Nov 5 12:50:37 2025      Matin :

Soucis synchro :
- Nicolas les a redémarré
 Screenshot_from_2025-11-05_17-49-33.pngScreenshot_from_2025-11-05_17-51-14.pngScreenshot_from_2025-11-05_17-50-44.png 
  Draft   Thu Nov 6 08:30:52 2025 Entered by Super Team from 134.158.195.141 on Thu Nov 6 08:30:37 2025Under ProcessUrgentTL | LE   08h30  Warm-up ThomX: Modulator,
Laser, Fridge

08h36 Chillers were started,
 SectOutput20251030.pngSectOutput20251106.png 
  1147   Fri Nov 7 18:45:54 2025 Entered by Super Team from 134.158.205.4 on Fri Nov 7 18:45:38 2025Under ProcessShift summaryLinac Commissionning   08h34  Warm-up ThomX: Modulator, Laser,
Fridge

08h40 Chillers were started,
 Screenshot_from_2025-11-07_16-24-10.pngScreenshot_from_2025-11-07_16-24-35.pngScreenshot_from_2025-11-07_16-23-58.png 
  1149   Wed Nov 12 10:29:49 2025 Entered by Super Team from 134.158.76.9 on Wed Nov 12 10:29:34 2025Under ProcessShift summaryLI | TL | Ring   15h09 Cycling all magnets

15h12 HV is ON

15h15 The modulator was set to
  
  1157   Tue Nov 25 09:32:03 2025 Entered by Super Team from 134.158.195.141 on Tue Nov 25 09:31:46 2025Under ProcessShift summaryDiag | Ring Commissioning   09h31 Warm-up ThomX: Modulator, Laser,
Fridge

09h36 Chillers were started,
  
  1163   Fri Dec 5 08:31:59 2025 Entered by Super Team from 134.158.195.141 on Fri Dec 5 08:31:45 2025Under ProcessShift summaryRing Commissioning   08h31 Warm-up ThomX: Modulator, Laser,
Fridge

08h36 Chillers were started, cycling
  
  1166   Wed Dec 10 10:45:33 2025 Entered by Super Team from 134.158.195.141 on Wed Dec 10 10:45:16 2025Under ProcessShift summaryLinac Commissionning   8h30 : machine started on remote
50 MeV operation.
Problem with Yag-TL camera
  
  Draft   Fri Jan 16 08:29:33 2026 IC, VM, NDUnder ProcessShift summary    08h29 Warm-up ThomX: Modulator, Laser,
Fridge
Chillers were started, cycling all
 Screenshot_from_2026-01-16_18-28-24.pngScreenshot_from_2026-01-16_13-22-12.pngScreenshot_from_2026-01-16_13-23-01.pngScreenshot_from_2026-01-16_13-31-16MODEl.pngScreenshot_from_2026-01-16_16-02-15LOCO_1it.png 
  Draft   Tue Jan 20 08:35:56 2026 VM, ND, VCUnder ProcessShift summary    08h35 Warm-up ThomX: Modulator, Laser,
Fridge
08h41 Chillers were started, cycling
  
  1189   Fri Feb 6 08:26:41 2026 Entered by Super Team from 127.0.0.1 on Fri Feb 6 08:26:22 2026Under ProcessShift summaryRF D1   08h25 Warm-up ThomX: Modulator, Laser,
Fridge

08h33 Chillers were started, cycling
 Screenshot_from_2026-02-06_10-52-58.png 
  1196   Fri Feb 20 07:54:25 2026 IC, VMUnder ProcessShift summaryRing Commissioning   7h50: mise en chauffe en remote (chillers/frigo,
modulateur, cyclage)

08h57 HV is on
 Screenshot_from_2026-02-20_16-34-18.pngScreenshot_from_2026-02-20_16-15-37.pngScreenshot_from_2026-02-20_12-00-27.png 
  Draft   Thu Feb 26 08:18:00 2026 IC, VM      08h15: mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)

08h15: mise en chauffe en remote
  