ID Date Author Status Type Category Important Subjectdown Icon Text Attachments
  1032   Tue Mar 11 14:31:06 2025 VMUnder ProcessShift summaryLinac Commissionning   14h31 Start ThomX/ Modulator, Frig, Laser

14h37 Cycling all magnets, Chillers
started
 9x 
  Draft   Thu Mar 13 08:29:34 2025 VM, VC, RC, ICUnder ProcessShift summaryRing Commissioning   08h27 Start ThomX: Modulator, Laser, Frig

08h34 Chillers were started, cycling
al magnets
 12x 
  1048   Mon Mar 31 09:53:26 2025 VM, IC, RCUnder ProcessShift summaryRing Commissioning   08h00 ThomX started by Maher

09h50 Problem with vacuum in the
septum. TL-V3 and EL-V1 are closed.
 Screenshot_from_2025-03-31_18-06-59.pngScreenshot_from_2025-03-31_17-52-04.pngScreenshot_from_2025-03-31_17-14-56.png2025-03-31_10_40_04_li_dg_sst_01-ccd_01_RAW.png 
  Draft   Tue Apr 1 08:43:53 2025 VM, IC, DNUnder ProcessShift summaryRing Commissioning   08h42 Start ThomX: Morulator, firg, laser

08h47 Chillers, cycling all magnets

10h40 HV is 'ON'
  
  1058   Thu Apr 17 08:16:04 2025 VM, RC, DN, NDUnder ProcessShift summaryRing Commissioning   08h15 Start Thomx: modulator, frig, laser

08h21 Chillers started, all magnets
cycling
 health_check_Vide_Jauge_2025_04_17_09_25.pnghealth_check_RF_Redpitaya_2025_04_17_09_27.pngbpm_1_vs_kicker_second.pngviewer_2025_04_17_12_44_06.png20250417_175615.jpg 
  Draft   Fri May 2 08:23:50 2025 VMUnder ProcessShift summaryRing Commissioning   08h22 ThomX was started: modulator, frig,
laser

08h28 Chillers was started, all
  
  Draft   Fri May 16 08:21:36 2025 VM, IC, DN Under ProcessShift summaryRing Commissioning   08h20 ThomX was started: Modulator, frig,
laser

08h27 Chillers were started, cycling
  
  Draft   Tue May 27 08:34:42 2025 VM, ICUnder ProcessShift summaryRing Commissioning   Goal:
Beam Loss Monitors and Ring injection at
high charge. Studies of the injector for
 9x 
  Draft   Wed May 28 17:29:56 2025 KD,VM,ICUnder ProcessShift summaryRing Commissioning   08h00 ThomX was started

Goals:
Emittance measurements, ring optics study
 EmittanceVsGunPhase.pngScreenshot_from_2025-05-28_11-28-14.png 
  Draft   Fri Jun 6 08:17:31 2025 MV Entered by Super Team from 134.158.195.141 on Fri Jun 6 08:17:16 2025Under ProcessShift summaryRing Commissioning   08h15 ThomX was started; Modulator,
Frig, Laser

08h21 Chillers were started,
 ThomX_PhaseChargeScan20250606.pngThomX_FPC_TableVerticalScan20250606.png 
  Draft   Fri Jun 13 08:41:04 2025 VM,ICUnder ProcessShift summaryLinac Commissionning   08h40 ThomX was started: Modulator,
Frig, Laser

08h45 Chillers were started,
 health_check_Diag_charge_wavecatcher_2025_06_13_10_13.pngScreenshot_from_2025-06-13_11-11-22.pngScreenshot_from_2025-06-13_14-31-57.pngScreenshot_from_2025-06-13_14-31-45.png 
  1095   Fri Jun 27 08:49:36 2025 SC, ND LinacLI | Linac Commissionning   8h49 allumage modulateur, chiller, laser

10h00 Beam ON

Prise de données Cf images
 pos_TL2_vs_phase_RF.pngpos_TL2_spX_vs_temp.pngtp2spX_vs_time.png 
  1097   Wed Jul 2 14:45:20 2025 Entered by Super Team from 134.158.195.141 on Wed Jul 2 14:45:07 2025Under ProcessInfoLI   Vérif position laser photocathode
:

--> bouge de 1mm en Y et 0.2
  
  Draft   Tue Oct 21 12:29:35 2025 HG, DN. VM, MJ      11h40 Thomx warm-up

12h35 HV is ON

12h40 HV 1215 V
 mrsv_2_positions_fente.png 
  Draft   Fri Oct 24 08:33:30 2025 Entered by Super Team from 134.158.195.141 on Fri Oct 24 08:33:07 2025Under ProcessShift summary    08h32 Warm-up ThomX: Modulator, Laser,
Fridge

08h37 Chilers were started, cycling
  
  Draft   Tue Oct 28 08:40:22 2025 Entered by Super Team from 134.158.195.141 on Tue Oct 28 08:40:06 2025Under ProcessShift summary    08h40 Warm-up ThomX: Modulator, Laser,
Fridge

08h45 Chillers were started, cycling
 Screenshot_from_2025-10-28_11-48-31.pngScreenshot_from_2025-10-28_11-47-12.pngScreenshot_from_2025-10-28_11-46-55.pngScreenshot_from_2025-10-28_15-34-03.png 
  Draft   Wed Nov 5 12:50:55 2025 Entered by Super Team from 134.158.195.141 on Wed Nov 5 12:50:37 2025      Matin :

Soucis synchro :
- Nicolas les a redémarré
 Screenshot_from_2025-11-05_17-49-33.pngScreenshot_from_2025-11-05_17-51-14.pngScreenshot_from_2025-11-05_17-50-44.png 
  Draft   Thu Nov 6 08:30:52 2025 Entered by Super Team from 134.158.195.141 on Thu Nov 6 08:30:37 2025Under ProcessUrgentTL | LE   08h30  Warm-up ThomX: Modulator,
Laser, Fridge

08h36 Chillers were started,
 SectOutput20251030.pngSectOutput20251106.png 
  1147   Fri Nov 7 18:45:54 2025 Entered by Super Team from 134.158.205.4 on Fri Nov 7 18:45:38 2025Under ProcessShift summaryLinac Commissionning   08h34  Warm-up ThomX: Modulator, Laser,
Fridge

08h40 Chillers were started,
 Screenshot_from_2025-11-07_16-24-10.pngScreenshot_from_2025-11-07_16-24-35.pngScreenshot_from_2025-11-07_16-23-58.png 
  1149   Wed Nov 12 10:29:49 2025 Entered by Super Team from 134.158.76.9 on Wed Nov 12 10:29:34 2025Under ProcessShift summaryLI | TL | Ring   15h09 Cycling all magnets

15h12 HV is ON

15h15 The modulator was set to
  