VK/ND/SC; Faisceau Anneau 10x
|
Modulateur Impossible à passer en Standby ==> problème manque d'eau.
* Remise à ~4bars le réseau principal
* Restart du soft du modulateur (sinon l'erreur reste) |
IC, VM, VK, AL, JH; Optimization of the ring 6x
|
Start of the modulator at 9h45
11h30 Problem with water regulation. Probably falseread of GUN PT100. Hayg and Viktor is tryig to adjust manually the temperature of the chiller
for RF gun. We stopped at the settings as attached. |
VC VK IC; Commissionning
|
8H15 demarrage chauffage Klystron et chiller
9h15 bunker ouvert (intervention société extérieure jusqu'à 9H30)
10H injection dans l'anneau avec recette 20221020-1420 |
VK, VM, IC, KD; Ring commissioning 7x
|
Start of the machine by KD
11h20 The beam is in the ring
Optimization of the injection with the RCDS |
KD; shift du 9 decembre 2022
|
8h25 : Mise en chauffe (pression eau toujours OK)
Intervention casemate :
- Sextupoles SP02 resseré |
SC/ND/IC/VK/VM; Faisceau 11x
|
Mise en chauffe modulateur et refroidissements
Résistivité : 3.53 MOhm et Pression eau : 3.7
9:40: Cyclage des aimants. Problemes habituels. |
ND, VK, VM; Shift 23/2 9x
|
9h22 mise en chauffe
Pb site elog; autres sites web OK |
ND, Enzo Crou, Noé Idesheim, Jean-Nicolas Quenot; Prise de donnee 16/3/2023 17x
|
9:15 Mise en chauffe
10:30 Ronde casemate
10:40 Start beam |
IC, VM, VK, ND; RIng commissioning 10x
|
8:50 Mise en chauffe
10h Starting the beam
Tuning of the TL |
VK, VM, IC, LS; Restart storage in the Ring
|
~9h Start of the modulator
10h Tuning of the injector with KD
11h Try to inject in the ring. Only 1-2 turns after optimization. We tried previous injector settings, the situation is the same. We retuned |
KD VM VK JN SL; shift du 5 mai 2023    
|
8h30 : accès casemate controlé
==> septum et kickers OFF et cavité RF OFF
==> problème cavité RF, mux 3 défaut de communication |
ND, LS, IC, VK, VM, SW; Ring operation 15/5 7x
|
10:00 Machine warm up
Magnets cycling
11:00 Start machine |
LS, ND, IC, VK; Ring operation 16/5   
|
9:33 Start warming up
9:45 Ducre is working on the plumbing but it shuld not affect operations
11:00 Intervention JNC pour problemes refroidissement |
VK, IC. AL; Understanding of the shift in RF frequency 18x
|
8:40 Start warming up, problem with PSS. It was restarted.
Problems to start and tune the RF cavity. A clear working procedure and reliable tuning should b defined to optimize the Ring comissioning progress.
Feedback for teh RF has the suspicious behavior. At motor position close to the nominal, the feedback ofsets the motor in the negative direction |
VK, IC; RF frequency of the Ring   
|
In the morning, after the start-up pf the machine, scan phase-charge and small tuning it was possible to store the beam with the settings from previous
day.
The storage was optimize withthe dipole current of 159.9 (best storage up to now). RF cqvity voltqge 20-100 kV. |
VK, IC. VM, LS; Studies on the beam revolution frequency 12x
|
The main task for today is to measure the revolution frequency without RF cavity with the spectrum analyzer.
Start-up of the machine.
After setting the previous setting, the orbit was very different. We checked the injector, the beam also was different (based on the beam images) |
ND, LS, IC, VK, VM; Studies on the Ring revolution frequency 8x
|
Goal: understanding of teh beam natural revolution frequency. Study the effect of the dipoles.
We have started from the previous setting of the machine. Then we loaded the settings from last december and received better storage. RF cavity
is OFF. |
ND, LS, IC, VK, VM; RE: Studies on the Ring revolution frequency
|
Bonjour,
Pouvez vous enregistrer les images de l'oscilloscope et le donnée brute à la place des screenshots. Il y a une option dans
l'interface web pour enregistrer l'oscillogramme "proprement". De même pour les images, cela permet de faire des traitements à |
VK, IC. VM; Reestablishing running conditions at 500.38 MHz    
|
Goal of the shift: Reestablish the good storage at 500.38 and then try to optimize the storage and orbit.
Start up of the machine.
RF cavity start up by Mohamed. Water leakage. Jean-Noel will fix tomorrow mornig. Mohamed also says that aparently the sinal from ring syntetizer |
VK, IC. VM, ND, LS; beam storage   
|
The main idea fo this week is to prepare the beam for the search of the first X-rays.
Start without RF cavity. Study of the orbit. Orbit correction. We menage to correct hor. and vert. orbit.
We put the RF cavity ON. A lot of interlocks during the day. Difficult to operate i this conditions. |