Entry   DN, IC, HG, KD, MJ, and Co; X-ray measurement/characterization campaign Q_missed_2025-12-18_13-50-19.png
The machine was warmed up remotemy

The FPC is ready. The laser is locked.

9h Start HV
Entry   KD; shift du 19 décembre 2025 
7h20: mise en chauffe en remote (frigo/chiller, laser, modulateur, cyclage)

 

*** Programme ***
Entry   MJ; shift twiss Q1 versus soleno 
Modulateur en chauffe
Alarme rendant impossible clim casemate . Maher envoie un mail a urgencevc
Check Sf6 : 2 bar ==> Appel JN ==> ajout sf6 2.5 bar
Entry   KD; shift du 06 janvier 2026 2026-01-06_19_17_58_tl_dg_sst_03-ccd_01_RAW.png2026-01-06_19_17_20_tl_dg_sst_03-ccd_01_RAW.png
8h: mise en chauffe en remote (cyclage, modulateur, frigo/chillers, laser)

problème lancement cyclage RI-C1: QP.04, QP.09 et QP.10

Sole 238
Entry   VM DN MJ KD; shift du 07 janvier 2026 16x
7h55: mise en chauffe en remote (modulateur, frigo/chillers, laser, cyclage)
11h25 HV is ON

Archivage lance
Entry   IC, HG, RC, DN, JM; Test of the new receipt from BMAD Isol = 242 A 13x
8h55: mise en chauffe (modulateur, frigo/chillers, laser, cyclage)

10h20 HV ON

Start with the receipt nominal.  problem with the RF gun laser camera. Solved.
Entry   KD, IC, VM, RC; shift du 9 janvier 2026 6x
8h05: mise en chauffe en remote (modulateur, frigo/chillers, laser, cyclage)

09h06 HV is ON

10h10 receipt recipe_recipe_LI_TL_RI_all_20260108_17_34_30.txt (242 A BMAD). RF gun phase 226 dg. Sect Att. 2.457 dB, sect. phase 214 dg.
Entry   KD; shift du 13 janvier 2026 
7h55 : mise en chauffe en remote (chiller/frigo, laser, modulateur, cyclage)

9h : démarrage, pas de soucis au niveau du trig

16h30 : demarrage anneau pour recette 230A
Entry   VM, RC, MJ, IC; Test Soleno=245, optic issue de la simu Julien Matching 
08h36 Warm-up ThomX: Modulator, Laser, Fridge
8h41 Chillers were started, cycling all magnets.
09h40  HV is ON
Entry   IC; Ring studies Screenshot_from_2026-01-15_11-04-16.pngScreenshot_from_2026-01-15_11-33-33.pngRi_C1_Quads_is_off_Screenshot_from_2026-01-15_18-19-14.pngScreenshot_from_2026-01-15_16-42-27.pngScreenshot_from_2026-01-15_17-36-28after1LOCO.png
08h56 Warm-up ThomX: Modulator, Laser, Fridge
Chillers were started, cycling all magnets.
Low SF6 pressure. 
Entry   IC, VM, ND;  Screenshot_from_2026-01-16_18-28-24.pngScreenshot_from_2026-01-16_13-22-12.pngScreenshot_from_2026-01-16_13-23-01.pngScreenshot_from_2026-01-16_13-31-16MODEl.pngScreenshot_from_2026-01-16_16-02-15LOCO_1it.png
08h29 Warm-up ThomX: Modulator, Laser, Fridge
Chillers were started, cycling all magnets.

10h48 Beam is in the ring after resolving a lot of problems. The receipt loaded: recipe_recipe_LI_TL_RI_all_20260115_18_10_34.txt, with Linac-Tl
Entry   VM, ND, VC;  
08h35 Warm-up ThomX: Modulator, Laser, Fridge
08h41 Chillers were started, cycling all magnets.

09h40 HV is ON
Entry   KD MJ RC DN; Position Horiz FPC ("spectres dromadaires") 
7h55: mise en chauffe en remote (modulateur, cyclage, laser, frigo/chillers)
==> plus de trig sur la machine (sur toute la plage de scan de la phase stab du laser PC). ==> OK, je suis une truffe le laser était
"off"
Entry   IC, VM; Beam studies 
7h45: mise en chauffe en remote (modulateur, laser, frigo/chillers)

08h41 HV is on

08h49 RF gun phase 152 dg., sect phase 208 dg. beam is in the ring W/O RF
Entry   IC, VM; Ring studies 
7h45: mise en chauffe en remote (modulateur, cyclage, laser, frigo/chillers)

08h43 HV is on

RF gun phase (laser phase) for maximum charge is out of the range, close to 360 dg. or 10 dg. Help is needed! 
Entry   KD, HG, VM; Laser PC status Screenshot_from_2026-02-05_17-11-35.png
** l'iris a été changée et est opérationnelle

/!\ problème dans l'offset il faut ajouter 0.5mm à la valeur relu par Tango (pour 1.3mm
il faut mettre 0.8 mm dans l'ATK panel)
Entry   Entered by Super Team from 127.0.0.1 on Fri Feb 6 08:26:22 2026;  Screenshot_from_2026-02-06_10-52-58.png
08h25 Warm-up ThomX: Modulator, Laser, Fridge

08h33 Chillers were started, cycling all magnets.

09h31 HV is on. Vacuum: Li/Vac1 4e-9, Li/Vac2 3e-9, Li/Vac3 3e-9, Li/Vac4 1e-9
Entry   VM && HG; Linac commissioning  Vacc_2026-02-11_11-05-31.pngScreenshot_from_2026-02-11_15-57-35.pngCharge_trend_2026-02-11_17-12-31.png
09h12 Warm-up ThomX: Modulator, Laser, Fridge

09h21 Chillers were started, cycling all magnets.

RF 50 pps
Entry   Entered by Super Team from 127.0.0.1 on Fri Feb 13 17:38:00 2026; SHift du jour 
The code for laser alignment does not work properly --> done by hand 
H 5.244
V 4.654
Entry   MJ, KD,VM,IC, RC, DN; shift du 17 fevrier 2026 10x
7h50 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

Le cyclage de RI-C1/QP.08, RI-C1/QP.11 et RI-C2/QP.03 ne démarre pas tout seul (action nécessaire sur le boutton cyclage de l'élément).

Programme - Etude "IP dromadaire" ==> Scan pos horizontale FPC + phase 