Message ID: 1192     Entry time: Fri Feb 13 17:38:15 2026
 Author: Entered by Super Team from 127.0.0.1 on Fri Feb 13 17:38:00 2026 
 Status: Under Process 
 Type: Shift summary 
 Category: LI 
 Important:
 Subject: SHift du jour 
 Icon:  

The code for laser alignment does not work properly --> done by hand 
H 5.244
V 4.654

phiMax section = 224 

position change (yag screen in pixels)  vs delta phase 

phi posH posV
224 350 267
254 340 272
264 335 260
204 340 266
184 274 280

Sole 230: 

Eps X: 

  emit_norm  : 1.3682 mm.mrad
  beta       : 19.51 m
  alpha      : -6.673

Eps Y: 

emit_norm  : 1.7366 mm.mrad
  beta       : 10.60 m
  alpha      : -3.606
 

Scan_QP0118h01.mat : 230

Scan_QP0118h09.mat : 240

Scan_QP0118h22.mat : 235

Scan_QP0118h26.mat : 225 

Scan_QP0118h31.mat : 235 : 

Scan_QP0118h31.mat : 235 : gain 0 

Scan_QP0118h36.mat : 240  : Gain 0 

18:40 stop