  1152   Tue Nov 18 11:11:33 2025 HG, JM, NDUnder ProcessShift summaryLI Prise de données 18/11 9h Intervention laser

Intervention pour realignement
el/dg/sst.01
  
  1153   Wed Nov 19 10:43:41 2025 HG + JM + ND (aprem)Under ProcessInfoLI | TL | LE Shift mesure Twiss + Simu icon1.gif 8:30 : demarrage à distance 
 

12:10 : QP7 Scan 1 (Phase section
 7x 
  1154   Thu Nov 20 09:26:33 2025 VM, ICUnder ProcessUrgentLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning BBA Ring Goal: Ring BBA

09h14 Unable to start thomx. Need
help. Probably problem with cooling water.
 Errors.jpegScreenshot_from_2025-11-20_14-04-53.png 
  1155   Fri Nov 21 08:02:04 2025 KD MJ DN StudentsUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 21 novembre 2025 8h: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)
9h: start 
 IMG-20251121-WA0003.jpgIMG-20251121-WA0005.jpg20251121_185206.JPG 
  1156   Mon Nov 24 13:22:59 2025 ND + JM + HGUnder ProcessShift summaryLI Prise de données 24/11  9:15 Mise en chauffe

9h30 Arrivée du SPR: testsSSI
ce matin => pas de faisceau avant midi
  
  1157   Tue Nov 25 09:32:03 2025 Entered by Super Team from 134.158.195.141 on Tue Nov 25 09:31:46 2025Under ProcessShift summaryDiag | Ring Commissioning   09h31 Warm-up ThomX: Modulator, Laser,
Fridge

09h36 Chillers were started,
  
  1158   Wed Nov 26 07:47:52 2025 KD MJ VM DN RCUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 26 novembre 2025 7h50: mise en chauffe à distance
(frigo/chiller, laser, modulateur, cyclage)

11h13 Beam is in the ring, 50 MeV,
 8x 
  1159   Thu Nov 27 08:01:20 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 27 novembre 2025 8h: mise en chauffe à distance (modulateur,
frigo/chiller, laser, cyclage)

9h30: Chargement de la recette
 multi_disps.txtrecipe_recipe_LI_TL_RI_all_20251126_09_35_14.txtBeam_no_opt.tifBeam_opt.tifBPM_jitters.png 
  1162   Thu Dec 4 08:59:07 2025 Entered by Super Team from 134.158.195.141 on Thu Dec 4 08:58:52 2025 Shift summaryLI | TL | Ring Preparation/check of the 70 MeV WP for X-ray run Goal: preparation and checking the machine
operation at 70 MeV and 40 MeV (ideally with
X-rays)
 Screenshot_from_2025-12-04_16-10-14.pngScreenshot_from_2025-12-04_17-38-20.pngScreenshot_from_2025-12-04_18-01-39_WITH_EL.png 
  1163   Fri Dec 5 08:31:59 2025 Entered by Super Team from 134.158.195.141 on Fri Dec 5 08:31:45 2025Under ProcessShift summaryRing Commissioning   08h31 Warm-up ThomX: Modulator, Laser,
Fridge

08h36 Chillers were started, cycling
  
  1164   Fri Dec 5 14:48:46 2025 Marie Julien Hayg Sophie Shift summaryLI | TL | LE | Ring Matching ring-TL - Recherche des bons twiss pour la TL Programme
shift : etudes matching anneau-TL - Recherche
param twiss TL
 Screenshot_from_2025-12-05_18-26-56.png 
  1165   Tue Dec 9 08:00:00 2025 KD MJ RC DNUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 09 décembre 2025 - 70 MeV et 40 MeV 8h : mise en chauffe en remote (modulateur,
cyclage, frigo/chillers, laser)

Stockage 70MeV ok, le faisceau 
 6x 
  1166   Wed Dec 10 10:45:33 2025 Entered by Super Team from 134.158.195.141 on Wed Dec 10 10:45:16 2025Under ProcessShift summaryLinac Commissionning   8h30 : machine started on remote
50 MeV operation.
Problem with Yag-TL camera
  
  1167   Thu Dec 11 08:38:30 2025 VM, ICUnder ProcessShift summaryDiag | Ring Commissioning 40 MeV operation 8h37 Warm-up ThomX: Modulator, Laser, Fridge

8h44 Chillers were started, cycling
all magnets.
 12x 
  1168   Fri Dec 12 08:40:50 2025 VM, ICUnder ProcessShift summaryRing Commissioning Check of the 70 MeV with MRSV, Ring studies 08h40 Warm-up ThomX: Modulator, Laser,
Fridge

8h45 Chillers were started, cycling
 Screenshot_from_2025-12-12_14-02-43.pngScreenshot_from_2025-12-12_14-02-27.pngScreenshot_from_2025-12-12_14-02-14.pngScreenshot_from_2025-12-12_14-02-02.pngScreenshot_from_2025-12-12_14-01-35.png 
  1169   Mon Dec 15 08:06:26 2025 KD MJUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 15 décembre 2025 8h: mise en chauffe en remote (chiller/frigo,
laser, modulateur, cyclage)

* cannot enter to the ring with
  
  1170   Tue Dec 16 07:18:46 2025 KD, IC, RC,VM Under ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 16 décembre 2025 7h10: mise en chauffe en remote (chiller/frigo,
laser, cyclage, modulateur).

à cause du faible flux d'hier
 2025-12-16_08_30_21_tl_dg_sst_02-ccd_01_RAW.png2025-12-16_08_35_25_tl_dg_sst_02-ccd_01_RAW.png 
  Draft   Wed Dec 17 07:17:06 2025 KD, IC, MV, DN,Under ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 17 décembre 2025 7h15: mise en chauffe en remote (chiller/frigo,
laser, modulateur, cyclage)

8h33 HV ON
  
  Draft   Thu Dec 18 09:39:38 2025 DN, IC, HG, KD, MJ, and Co Shift summaryLI | TL | LE | Ring | Diag | Aimants | Laser | Vide | Linac Commissionning | Ring Commissioning X-ray measurement/characterization campaign The machine was warmed up remotemy

The FPC is ready. The laser is locked.

9h Start HV
 Q_missed_2025-12-18_13-50-19.png 
  1173   Fri Dec 19 07:22:31 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 19 décembre 2025 7h20: mise en chauffe en remote (frigo/chiller,
laser, modulateur, cyclage)

 
  