Entry   VK, IC. VM, LS; Work on the new optics 
9h30 Start of the modulator and laser

Start of the beam. Problem with charge, the max charge at the end of the TL 60 pC. We can not increase it by the attenuator. To be understood.



Corrector ri-c2/ps/str.03-h.01 does not work => problem to control and tune the orbit. JNC will look
Entry   VK, IC. VM; Reestablishing running conditions at 500.38 MHz scan_charge_phase_min_0.0_max_360.0_14_32_59.pngScreenshot_from_2023-06-12_15-23-07.pngScreenshot_from_2023-06-12_15-40-14.pngScreenshot_from_2023-06-12_17-38-24.pngScreenshot_from_2023-06-12_17-32-48.png
Goal of the shift: Reestablish the good storage at 500.38 and then try to optimize the storage and orbit.

Start up of the machine.

RF cavity start up by Mohamed. Water leakage. Jean-Noel will fix tomorrow mornig. Mohamed also says that aparently the sinal from ring syntetizer
Entry   VK, IC. VM; Srart of the beam physics measurements 14x
The main idea fo this week is to prepare the beam for the search of the first X-rays.

Start machine without RF cavity. During the day several reboot of the libera.02 (TL).

Study of the dispersion. Measurements of the horizontal dispersion by changing the injector energy (RF section attenuator).
Entry   VK, IC. VM; Orbit correction, BLM in the Ring 7x
The BLM detector boxes were installed in the ring. We connected 3 fibers and 2 scintillator detectors in th ring to be able to observe the beam losses.

Cabling, connection and checks of the BLM without the beam.

Machine start-up. Modulator was switched on at ~9h30.
Entry   VK, IC. AL; Understanding of the shift in RF frequency 18x
8:40 Start warming up, problem with PSS. It was restarted.

Problems to start and tune the RF cavity. A clear working procedure and reliable tuning should b defined to optimize the Ring comissioning progress.

Feedback for teh RF has the suspicious behavior. At motor position close to the nominal, the feedback ofsets the motor in the negative direction
Entry   VK, IC, DN, RC, JN; search for X-rays 
8h30 Start of the modumator, laser, magnet cycling

9h45 Beam is ON. Scan charge vs. RF phase.

Attribute Li/OP/OPT.01-ATT.01  is showing value 340mm, this is different from the nominal ones of 300-303. Charge to be remeasured at nominal
Entry   VK, IC; RF frequency of the Ring scan_charge_phase_min_0.0_max_360.0_10_43_35.pngScreenshot_from_2023-05-19_13-50-56.pngScreenshot_from_2023-05-19_13-56-41.pngScreenshot_from_2023-05-19_12-15-50.png
In the morning, after the start-up pf the machine, scan phase-charge and small tuning it was possible to store the beam with the settings from previous
day.

The storage was optimize withthe dipole current of 159.9 (best storage up to now). RF cqvity voltqge 20-100 kV.
Entry   VK, AL, IC; Beam is stored 6x
Shift started at 18h

With the current injector settings, it was difficult to inject.  We loaded the settings from last Friday 30/09 (19-22-04).

 
Entry   VK VM; Shift 03 
Start modulator; alims;

We cannot start machine. No e-beam. Timing laser RF? Need help of linac team. 

 
    Reply   VK VM; RE: Shift 03 
evreything is ok

The laser shutter was closed ! Becareful the shutter state is inverted.




VK
    Reply   VK VM; RE: RE: Shift 03 
Il se passe des choses pendant la nuit qui mette les diags de la machine en radent :

 - Tous les BPM saturent ==> necessité de remettre la "puissance" à -10

 - Toutes les caméras étaient éteintes ==> necessité d'aller dans "DS restart" pour un forcage
Entry   VK VC HG SC ME; commitionning 
8h10 rémarrage machine chauffage klystron frigo et chiller

pB DS   calc/er_sy/rac.17-elr.01-rdp.0X.Y  (tous les DS redpy baie 17 )

Cycling ok
Entry   VC/SC; Commissionning LE 
8h20 demararage machine

laser PC

Frifo chiller
    Reply   VC/ND; RE: Q beam versus E laser 
Verification resistivite eau:

- 6.7Mo dans la baie 18 (alims)

- 550ko sur la voie 1 dans le local technique
Entry   VC/KD/SC; Faisceau linac 
13h : MO : Mise en chauffe modulateur et mise en route refroidissement

14h : Fermeture casemate, démarrage

Problème avec client 2
Entry   VC/KD/HM/HG; Shift Linac + LT 25 aout 2022 
14h00 : injection dans la TL avec faisceau sur TL-SST2

avec les parametres QP1=+1.6A, QP2=-4.2A, QP3 3A, tl str1V=+0.6A, listr1H-1.48A

Phase osc laser a sauté :
Entry   VC-VM; Shift summary Screenshot_from_2024-09-24_11-15-45.pngScreenshot_from_2024-09-24_11-21-49.pngScreenshot_from_2024-09-24_17-41-23.png
demarrage modulateur 8h50

"Perle" avait ouvert les portes de l'igloo.... le clés sont récupérées... Maher fait la ronde

Les personnes allant dans les fosses nord et sud doivent laisser les portes dans la position initiale!!
Entry   VC-MJ; Demarrage faisceau 
faisceau... sur Li SST0.1

position laser était à 5.1 2.55 (on ne sait pas pourquoi)

mise à la nominale (5.4, 2.34)
Entry   VC-KD; commitionning 10x
8H50

Demarrage chauffage, chiller, et cyclage aimants

TL/PS/DPI.01 en défaut resolu par un reset sur l'ATK pannel
Entry   VC-CB-KD; run du 26 aout 2022 Etat_Machine_2022-08-26_17-37-28.png2022-08-26_17_34_13_tl_dg_sst_03-ccd_01_RAW_18.png
9H

mise en chauffe modulateur

10H modulateur OK