Entry   VK VM; Shift 03 
    Reply   VK VM; RE: Shift 03 
       Reply   VK VM; RE: RE: Shift 03 
This is a draft message, edit and submit it to make it permanent  
Message ID: 700     Entry time: Fri Mar 3 11:49:50 2023     Reply to this: 701
 Author: VK VM 
 Status: Not Fixed 
 Type: Shift summary 
 Category: LI | Ring | Linac Commissionning | Ring Commissioning 
 Important:
 Subject: Shift 03 
 Icon:  

Start modulator; alims;

We cannot start machine. No e-beam. Timing laser RF? Need help of linac team. 

 

Kevin solved problem with shutter.

Check alignment at QP3.

Check phase of the section, go to 1.35 dB. 

Libera4 reboot.

Measure  orbit.

Try to change frequency of synthe from 500 to 500.43 resulted in the change beam position in TL BPM2, but it should not do anythyng with TL. Same shift is observed at the screen in the same position. 

Vincent tryies to understand how to interpret this behaviour.

 

 

 

 

 

 

 