1189
|
Fri Feb 6 08:26:41 2026 |
Entered by Super Team from 127.0.0.1 on Fri Feb 6 08:26:22 2026 | Under Process | Shift summary | RF D1 |
|
| |
08h25 Warm-up ThomX: Modulator, Laser, Fridge
08h33 Chillers were started, cycling all magnets.
09h31 HV is on. Vacuum: Li/Vac1 4e-9, Li/Vac2 3e-9, Li/Vac3 3e-9, Li/Vac4 1e-9
09h33 Sect. Att. 30 dB, RF Gun Att. 20 dB, HV 1030 V Interlock
09h39 Sect. Att. 30 dB, RF Gun Att. 20 dB, HV 1050 V Interlock. Something wrong
10h20 HV 1050 V. Maher is here. Interlock by reflected power to the klystron.
10h26 Modulator is on standby.
10h29 HV is on W/O RF. HV 1215 V. All is OK.
10h34 Modulator is on standby.
10h57 HV is on, 1030 V
11h09 HV is 1050 V
11h35 50pps, 1030V
11h42 1040 V interlock
11h45 Modulator is on standby.
16h10 Stop ThomX
|
| Attachment 1: Screenshot_from_2026-02-06_10-52-58.png
|
 |
|
Draft
|
Fri Apr 24 08:05:11 2026 |
Entered by Super Team from 127.0.0.1 on Fri Apr 24 08:05:02 2026 | | | |
|
, entered from 127.0.0.1 | |
8h00 : mise en chauffe en remote (frigo/chillers, laser, modulateur, cyclage) |
|
24
|
Tue Jun 8 17:40:20 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:40:07 2021 | Fixed | Shift summary | resumes |
|
Résumé de la journée | |
- Pour les atténuateurs : les butées ont été trouvées, ATT02-MOT01 c'est la canon, ATT01-MOT01 c'est la section.
- Des difficultés ont été rencontrés avec le modulateur : Interlock à cause de l'eau, interlock alim HT, reboot modulateur et vérification de l'autorisation de tir MPS faite.
Le modulateur fonctionne maintenant sans problèmes à une tension de 1240V et un vide klystron de 1.2 uA qui devrait diminuer par la suite. Les mesures radioprotection ont été faites
- Pour le MPS, cliquez sur Paramètres en bas de l'écran principal puis vérifier que LINAC est on.
Pour demain :
- Démarrer régulation eau en plus du modulateur
- Vérifier les signaux RFs sur oscillo et Réglage des retards (demarrage_delays)
- Ne pas mettre beaucoup de puissance, vérifier la chaine RF et vérifier les atténuateurs
- Vérifier caméra et ICT |
|
23
|
Tue Jun 8 17:30:12 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:29:26 2021 | Fixed | Info | etc |
|
| |
Capture ecran modulateur |
| Attachment 1: HT_1100.png
|
 |
|
22
|
Tue Jun 8 17:27:35 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:27:21 2021 | Under Process | Info | Prise de donnees |
|
HT sur modulateur et radioprotection | |
Contrôle radioprotection en cours HT = 1240V tension max, vide klystron : 1.2 uA
|
|
21
|
Tue Jun 8 17:16:10 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:15:58 2021 | Fixed | Info | etc |
|
| |
Modulateur OK, HT = 500 V en trig |
|
20
|
Tue Jun 8 17:04:44 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:04:28 2021 | Fixed | Info | etc |
|
Hv sur modulateur | |
Sur le MPS, Vérifiez qu'on est bien en PARAMETRES/ Linac pour autorisation HV sur modulateur |
|
19
|
Tue Jun 8 15:58:08 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 15:57:55 2021 | Under Process | Info | etc |
|
| |
Modulateur remis en chauffe car interlock |
|
18
|
Tue Jun 8 15:06:12 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 15:05:59 2021 | Fixed | Info | etc |
|
| |
ATT02-MOT01 attenuateur canon en butée à -8 jusque 3329 |
|
17
|
Tue Jun 8 15:05:04 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:49:35 2021 | Fixed | Info | etc |
|
attenuateur section tests butée moteur | |
ATT01-MOT01 atténuateur section course de -870 step à 2485 pour les butées |
|
16
|
Tue Jun 8 14:49:12 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:48:07 2021 | Fixed | Info | docs |
|
| |
LI/HFI/ATT.02-MOT.01 Attenuateur Canon |
|
15
|
Tue Jun 8 14:44:01 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:43:48 2021 | Under Process | Other | etc |
|
attenuateur section tests butée moteur | |
Pas complètement au switch à 0.0 pas pour LI/HFI/ATT.02-MOT01 |
|
14
|
Tue Jun 8 14:42:30 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:42:17 2021 | Under Process | Question | etc |
|
| |
Attenuateur LI/HFI/ATT.02-MOT01 en butée à 3329 |
|
13
|
Tue Jun 8 14:39:20 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:39:06 2021 | Under Process | Other | etc |
|
attenuateur section tests butée moteur | |
Tests des moteurs sur atténuateur en cours
Repérage des butées et des positions |
|
12
|
Tue Jun 8 14:36:48 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:36:35 2021 | Under Process | Problem | etc |
|
Tests RFs | |
Interlock eau sur modulateur, arrêt du modulateur.
Remise en route
A nouveau interlock modulateur, purge de l'eau
Remise en chauffe modulateur ok |
| Attachment 1: mise_en_chauffe
|
|
11
|
Tue Jun 8 12:39:23 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 12:39:09 2021 | Under Process | Shift summary | etc |
|
summary du matin | |
Bonjour,
la synchro est effective
le modulateur est pret
L'oscillo est opérationnel
rdv à 13h30-45 pour la ronde
A+
Christelle |
|
10
|
Tue Jun 8 11:49:13 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 11:48:58 2021 | Under Process | Fix | problemes |
|
attenuateur section tests butée moteur | |
On monte progressivement le moteur de l'atténuateur de la section pour trouver la butée supérieure li/hfi/att.01-mot.01
Le déplacement du moteur est lent
On constate un problème à régler dans le DS CALC de calibration calc/li_hfi/write_att.01-mot.01 --> Hayg bosse dessus
butée positive à 1500
butée négative à 0
les atk se sont figés et ne répondent plus --> problème fenetre d'erreur non visible --> ticket glpi sur le sujet pour configurer jive pour avoir la fenetre d'erreur sur 'application jive et non ailleurs
Mail envoyé à Mohamed pour savoir à quelles valeurs correspondent les butées.
Les butées sont réglées de la même facon pour le canon
reste à savoir si la position 0 correspond au zero d'atténuation ?
|
|
9
|
Tue Jun 8 10:58:29 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 10:58:16 2021 | Under Process | Info | etc |
|
Signaux RFs | |
Mise en place des signaux Rfs sur l'oscilloscope de la salle CC, Travail sur le timing en cours.
Valeurs Redpitaya pour signaux RFs : Trigger source = 6 (Trigger EXT), Trigger Delay = 8200, Trigger level = 0.1 |
|
8
|
Tue Jun 8 10:40:54 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 10:40:40 2021 | Fixed | Info | etc |
|
Fermeture sous-sols et toit casemate | |
Les sous-sols et le toit sont maintenant fermés |
|
7
|
Tue Jun 8 09:31:28 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 09:31:12 2021 | Under Process | Info | etc |
|
Tests RFs | |
Aujourd'hui, démarrage des tests RFs.
Vérification du bon fonctionnement des IHMs, mise en route du MPS et fermeture casemate en fin de matinée
|