| ID |
Date |
Author |
Status |
Type |
Category |
Important |
Subject |
Icon |
Text |
 |
|
810
|
Thu Oct 26 09:02:33 2023 |
VC,SC, ND, IC, VK, CB, V | | Linac | LI | TL | Ring |
|
Linac | | 8h30 Mise en chauffe
Pas d'internet sur client1
et client2 |
|
|
1149
|
Wed Nov 12 10:29:49 2025 |
Entered by Super Team from 134.158.76.9 on Wed Nov 12 10:29:34 2025 | Under Process | Shift summary | LI | TL | Ring |
|
| | 15h09 Cycling all magnets
15h12 HV is ON
15h15 The modulator was set to |
|
|
1162
|
Thu Dec 4 08:59:07 2025 |
Entered by Super Team from 134.158.195.141 on Thu Dec 4 08:58:52 2025 | | Shift summary | LI | TL | Ring |
|
Preparation/check of the 70 MeV WP for X-ray run | | Goal: preparation and checking the machine
operation at 70 MeV and 40 MeV (ideally with
X-rays) |
  |
|
1000
|
Tue Jan 21 08:08:43 2025 |
KD | Under Process | Shift summary | LI | TL | Linac Commissionning | Ring Commissioning |
|
shift du 21 janvier 2025 | | 8h10 : mise en chauffe à distance
(modulateur, laser, frigo/chiller) |
|
|
741
|
Tue Apr 25 14:19:49 2023 |
CB | | Shift summary | LI | TL | Linac Commissionning |
|
run du 20 avril 2023 |
| Suite du run du 19 avril : objectif mesure
des twiss pour plusieurs valeur de solénoides
à partir de 180A |
 |
|
1009
|
Wed Feb 12 08:00:31 2025 |
KD MJ | Under Process | Shift summary | LI | TL | Linac Commissionning |
|
shift du 12 février 2025 - Alignements | | 8h: mise en chauffe à distance (modulateur,
frigo, chiller, laser)
9h30: laser semble pas aligné |
  |
|
1148
|
Mon Nov 10 16:15:53 2025 |
KD, M2 GI | Fixed | Shift summary | LI | TL | Linac Commissionning |
|
shift du 10 novembre 2025 | | 8h: mise en chauffe en remote (modulateur,
laser, frigo/chiller)
10h: Démarrage machine |
|
|
687
|
Mon Feb 20 08:30:57 2023 |
KD, MJ, HG | Under Process | Shift summary | LI | TL | LE | Vide | Linac Commissionning |
|
shift du 20 février 2023 | | 8h30 : Mise en chauffe de la machine (frigo,
chiller, laser, modulateur)
fosse vidée + circuit d'eau |
    |
|
Draft
|
Mon Feb 20 10:16:18 2023 |
ND | Under Process | Shift summary | LI | TL | LE | Vide | Linac Commissionning |
|
RE: shift du 20 février 2023 | | Healthcheck signal effectivement un probleme
sur toute les vannes... Et les atkpanels
signalent un problème de communi |
|
|
689
|
Mon Feb 20 10:19:56 2023 |
ND | Under Process | Shift summary | LI | TL | LE | Vide | Linac Commissionning |
|
RE: shift du 20 février 2023 | | Healthcheck signal effectivement un probleme
sur toute les vannes... Et les atkpanels
signalent un problème de communication... |
 |
|
Draft
|
Thu Nov 13 08:00:59 2025 |
KD MJ VM HG | Fixed | Shift summary | LI | TL | LE | Ring | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 13 novembre 2025 - spectres a differentes valeurs de bpmTL2_X | | Apres que Kevin a regle tous les problemes
synchro signal bpm etc etc etc
L'interface SST ne fonctionne |
|
|
840
|
Fri Feb 2 08:16:50 2024 |
Entered by Super Team from 134.158.195.141 on Fri Feb 2 08:16:31 2024 | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
Shift du 2 février 2024 | | La clé PA est resté enclenchée
hier. Il faut penser à la tourner
avant de partir (demande de Maher) |
|
|
977
|
Tue Dec 10 11:35:16 2024 |
VM,HG,SC | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
50 and 70 MeV Emittance, and transport | | Intervention chiller (Maher) : maintenance
nécessaire à prévoir
(clé outil clignote) |
 |
|
1141
|
Thu Oct 23 07:45:25 2025 |
KD RC VC MJ | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
shift du 23 octobre 2025 | | 7h45: mise en chauffe en remote (modulateur,
laser, frigo/chillers, cyclage)
8h45 : mise en route Modulateur |
|
|
1176
|
Wed Jan 7 07:55:45 2026 |
VM DN MJ KD | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
shift du 07 janvier 2026 | | 7h55: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)
11h25 HV is ON |
16x |
|
1177
|
Thu Jan 8 09:07:08 2026 |
IC, HG, RC, DN, JM | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
Test of the new receipt from BMAD Isol = 242 A | | 8h55: mise en chauffe (modulateur, frigo/chillers,
laser, cyclage)
10h20 HV ON |
13x |
|
1185
|
Wed Jan 21 07:56:59 2026 |
KD MJ RC DN | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
Position Horiz FPC ("spectres dromadaires") | | 7h55: mise en chauffe en remote (modulateur,
cyclage, laser, frigo/chillers)
==> plus de trig sur la machine |
|
|
838
|
Thu Feb 1 11:50:28 2024 |
MJ | Not Fixed | Shift summary | LI | TL | LE | Ring | Linac Commissionning |
|
Attenuateur LIL / Puissance LIL / Energie electrons | | La puissance entree canon a ete verifie
et conforme a l'atterndu (6 MW = 18/3
MW) |
|
|
817
|
Wed Nov 15 09:13:06 2023 |
KD, MJ, RC | Under Process | Shift summary | LI | TL | LE | Ring | Laser | Opt | SY |
|
shift du 15 novembre 2023 | | 9h : mise en chauffe de la machine
12h: intervention Iryna et Slava
pour un meilleur stockage dans l'anneau |
6x |
|
1160
|
Tue Dec 2 09:28:15 2025 |
Entered by Super Team from 134.158.205.28 on Tue Dec 2 09:27:54 2025 | Not Fixed | Info | LI | TL | LE | Ring | Diag | Linac Commissionning | Ring Commissioning |
|
Shift ThomX/Xrays : Soucis démarrage |
| Last Recettes for 50 MeV:
recipe_recipe_LI_TL_RI_good_20251127_12_42_51.txt
recipe_recipe_LI_TL_RI_good_20251125_16_42_01.txt |
|