737
|
Thu Apr 20 10:36:19 2023 |
Entered by Super Team from 134.158.195.142 on Thu Apr 20 10:36:01 2023 | Reference Solution | Shift summary | LI | TL | Aimants | Linac Commissionning |
|
référence axe mag Canon | | Voici la référence tete de
machine pour l'axe mag canon :
Laser Iris position [H;V] |
|
|
Draft
|
Fri Apr 21 14:30:19 2023 |
Entered by Super Team from 134.158.195.141 on Fri Apr 21 14:30:03 2023 | | Linac | Linac Commissionning |
|
Faisceau Linac | | 13h49 Démarrage faisceau
Position laser H = 4.9 et V = 2.42,
scan charge phase : phase de focalisation |
|
|
Draft
|
Tue Apr 25 09:11:29 2023 |
ND,DN,SC,NE, EM | New Solution | Shift summary | Ring |
|
Quart collectif 25/4 | | 9h10 (ND): Mise en chauffe modulateur et
laser
9h15 mise en chauffe Chiller (SC) |
|
|
740
|
Tue Apr 25 13:53:05 2023 |
SC,ND,VK, VM, IC | | Shift summary | Linac Commissionning | Ring Commissioning |
|
Démarrage faisceau | | Point initial faisceau canon :
- soleno LI/AE/COL.01-MOT.02 =
3.3 mm, LI/AE/COL.01-MOT.01 = 0.8 mm, LI/AE/COL.02-MOT.01 |
|
|
742
|
Wed Apr 26 19:03:56 2023 |
Entered by Marie Jacquet from 134.158.89.45 on Wed Apr 26 19:03:42 2023 | | Shift summary | Linac Commissionning |
|
shift du 26/04 - Quads scans + stabilite | | 1) Quad scans Isol = 155,
175, 190, 200, 220 pris avec script classique
ET avec script FWHM LIMA - Taille a comparer, |
|
|
743
|
Thu Apr 27 09:24:26 2023 |
ND, LS | New Solution | Shift summary | Ring | Diag |
|
Prise de donnee 26/4/2023 | | 9:24 Mise en chauffe
9:30 Cyclage des aimants
11h44 Démarrage faisceau |
 |
|
744
|
Fri Apr 28 09:20:00 2023 |
ND, LS, IC, VM, VK | New Solution | Shift summary | Ring |
|
Prise de donnee 27/4/2023 | | 9:19: Mise en chauffe
10:24 Cycling magnets
10:50 Demarrage faisceau |
10x |
|
745
|
Wed May 3 09:04:24 2023 |
KD | New Solution | Shift summary | LI | TL | LE | Linac Commissionning |
|
shift du 03 mai 2023 | | 9h : Mise en chauffe machine (frigo,
chiller, modulateur, PA, Laser)
13h30 : Démarrage Machine |
8x |
|
746
|
Wed May 3 20:10:40 2023 |
Entered by Marie Jacquet from 134.158.89.45 on Wed May 3 20:10:26 2023 | | Shift summary | Linac Commissionning |
|
Stabilite LINAC | | Pour illustrer la fin de l'entree
elog 745 d'aujourd'hui :
|
|
|
747
|
Thu May 4 10:09:43 2023 |
Entered by Viktor Soskov from 134.158.195.153 on Thu May 4 10:09:22 2023 | Fixed | Info | Linac Commissionning |
|
Laser status | | Bonjour l'énergie UV actuelle
sur la cathode = 58µJ avec l'iris
1.3mm |
|
|
748
|
Thu May 4 11:41:53 2023 |
VK, VM, IC, LS | | Shift summary | Ring Commissioning |
|
Restart storage in the Ring | | ~9h Start of the modulator
10h Tuning of the injector with
KD |
|
|
749
|
Thu May 4 16:14:06 2023 |
Entered by Marie Jacquet from 134.158.89.45 on Wed May 3 20:10:26 2023 | | Shift summary | Linac Commissionning |
|
RE: Stabilite LINAC | |
|
|
|
750
|
Fri May 5 08:47:28 2023 |
KD VM VK JN SL | Under Process | Shift summary | Ring Commissioning |
|
shift du 5 mai 2023 | | 8h30 : accès casemate controlé
==> septum et kickers OFF et
cavité RF OFF |
    |
|
751
|
Mon May 15 11:31:43 2023 |
ND, LS, IC, VK, VM, SW | Under Process | Shift summary | Ring Commissioning |
|
Ring operation 15/5 | | 10:00 Machine warm up
Magnets cycling
11:00 Start machine |
7x |
|
752
|
Tue May 16 10:28:43 2023 |
LS, ND, IC, VK | Under Process | Shift summary | Ring Commissioning |
|
Ring operation 16/5 | | 9:33 Start warming up
9:45 Ducre is working on the plumbing
but it shuld not affect operations |
   |
|
753
|
Wed May 17 09:16:47 2023 |
VK, IC. AL | | Shift summary | Ring Commissioning |
|
Understanding of the shift in RF frequency | | 8:40 Start warming up, problem with PSS.
It was restarted.
Problems to start and tune the |
18x |
|
754
|
Fri May 19 18:05:29 2023 |
VK, IC | | Shift summary | Ring Commissioning |
|
RF frequency of the Ring | | In the morning, after the start-up pf the
machine, scan phase-charge and small tuning
it was possible to store the beam with the |
   |
|
755
|
Fri May 19 20:22:42 2023 |
MJ, KD | Under Process | Shift summary | RF Anneau | Ring Commissioning |
|
RF et anneau | | Apres 18h30 : prise ne main de la machine
pour aller dans la LE ==> le kicker d'extraction
est interlocké (abdandon) |
 |
|
756
|
Tue May 23 11:36:24 2023 |
LS, ND | | Shift summary | LI | Diag |
|
Prise de donnees 23/05 | | 9:30 Demarrage machine
Fin installation Cerenkov + tests
MRSV |
|
|
757
|
Thu May 25 15:08:18 2023 |
NC,IC, VM,lS | | Shift summary | Ring |
|
| | 9:10 warm up modulator
10:30: cycling of magnets
10:20 : scan charge phase |
  |