Draft
|
Fri Mar 6 10:44:11 2026 |
VM, HG, JN | Under Process | Shift summary | RF D1 |
|
| | 09h00 Warm-up ThomX: Modulator, Laser,
Fridge
09h05 Chillers were started, cycling |
| |
1207
|
Wed Mar 11 08:03:48 2026 |
KD, VM, MJ, RC | Under Process | Shift summary | Laser | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 11 mars 2026 - TRANSFOCATEUR | | 8h: mise en chauffe en remote (cyclage,
modulateur, laser, frigo/chiller)
clients et réseau très |
 | |
1208
|
Wed Mar 11 18:12:23 2026 |
Entered by Super Team from 127.0.0.1 on Wed Mar 11 18:12:09 2026 | Under Process | Shift summary | LI |
|
Emittance vs Iris | | Some Quad scans with variying the Iris
opening.
Data : |
| |
Draft
|
Thu Mar 12 07:57:41 2026 |
KD, VM, MJ, RC, DN | Under Process | Shift summary | Laser | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 12 mars 2026 | | 8h: mise en chauffe de la machine en remote
(modulateur, laser, frigo/chillers, cyclage)
*** Programme *** |
| |
1213
|
Tue Mar 17 08:07:49 2026 |
KD MJ RC DN VK | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
ENERGY-ANGLE reconstruction : prise de donnees - 17 mars 2026 | | 8h05 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
*** programme : Mesures |
| |
1214
|
Wed Mar 18 07:58:19 2026 |
KD, VM, MJ, RC, DN | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 18 mars 2026 | | 8h: mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)
*** Programme : Mesure |
8x | |
Draft
|
Fri Mar 20 07:20:47 2026 |
IC, VM | Under Process | Shift summary | |
|
Work on orbit at 70 MeV for X rays | | 7h20: mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)
08h55 HV is ON |
    | |
Draft
|
Tue Mar 24 08:10:35 2026 |
KD, VM, MJ, RC | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 24 mars 2026 | | 8h05 : mise en chauffe en remote (frigo/chiller,
modulateur, laser, cyclage)
09h17 HV is ON |
| |
Draft
|
Thu Mar 26 07:39:02 2026 |
IC, VM, DN, MJ | Under Process | Shift summary | |
|
| | 7h37 : mise en chauffe en remote (frigo/chiller,
modulateur, laser, cyclage)
08h57 HV is ON |
    | |
Draft
|
Tue Mar 31 07:56:57 2026 |
KD | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 31 mars 2026 | | 7h55 : mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)
==> vérifier la pression |
| |
1223
|
Wed Apr 1 07:45:03 2026 |
KD MJ RC DN VK | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
1e avril 2026 - Scan Energy-Angle 61.5 MeV | | 7h40 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
==> SF6 à remplir avant |
| |
Draft
|
Thu Apr 2 07:55:49 2026 |
IC,VM | Under Process | Shift summary | |
|
| | 7h50 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
08h58 HV is ON |
| |
Draft
|
Fri Apr 3 07:51:41 2026 |
IC,VM, ND | Under Process | Shift summary | |
|
, entered from 127.0.0.1 | | 7h50 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
9h30 HV is ON |
| |
1226
|
Tue Apr 7 07:49:37 2026 |
IC,VM, KD, DN, MJ | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
MONO 61.5 MeV - 07 avril 2026 | | 7h50 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
09h30 HV is ON |
| |
Draft
|
Thu Apr 9 08:11:33 2026 |
IC,VM | Under Process | Shift summary | |
|
| | 8h10 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
09h12 HV is ON |
| |
Draft
|
Fri Apr 10 07:39:37 2026 |
IC,VM | Under Process | Shift summary | |
|
| | 7h40 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
08h43 HV is ON |
| |
1231
|
Wed Apr 15 08:04:29 2026 |
KD MJ RC DN VK | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
ENERGY/ANGLE 40 MeV - 15 avril 2026 | | 8h05: mise en chauffe à distance
(frigo/chillers, modulateur, laser, cyclage)
*** |
| |
Draft
|
Tue Apr 21 07:36:54 2026 |
KD, VM | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 21 avril 2026 | | 7h30 : mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage) ==> dipôles
non cyclé (en défaut) ==> |
| |
1239
|
Mon May 11 09:33:17 2026 |
Vincent | Under Process | Linac | LI | TL |
|
Manip Gplast | | 9h30 test radioprotection OK (mesure en
dessous du bruit de fond)
13h30 fenetre installée |
| |
1240
|
Tue May 12 08:42:45 2026 |
Entered by Super Team from 127.0.0.1 on Tue May 12 08:42:31 2026 | Under Process | Other | LI |
|
manip Gplast | | Demarrage machine 8h40
pB reflechi canon... temp consigne
27.7C |
|
|