Emittance vs Iris
Icon:
Some Quad scans with variying the Iris opening.
Data :
17h17 : 2mm 120 pC
17h31 : 1.3mm 100pC
17h46 : 1mm 80pC
18h00 : 1mm 100 pC
18h27 : 1mm 100 C Sole 240
18h41 : 1mm 100 C Sole 245
ELOG V3.1.4-395e101