Message ID: 1208     Entry time: Wed Mar 11 18:12:23 2026
 Author: Entered by Super Team from 127.0.0.1 on Wed Mar 11 18:12:09 2026 
 Status: Under Process 
 Type: Shift summary 
 Category: LI 
 Important:
 Subject: Emittance vs Iris 
 Icon:  

Some Quad scans with variying the Iris opening.

Data :

  • 17h17 : 2mm 120 pC
  • 17h31 : 1.3mm 100pC
  • 17h46 : 1mm 80pC
  • 18h00 : 1mm 100 pC
  • 18h27 : 1mm 100 C Sole 240 
  • 18h41 : 1mm 100 C Sole 245