  1110   Mon Sep 1 09:34:34 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 1e septembre 2025 

9h: mise en chauffe en remote (modulateur, frigo/chiller, laser, cyclage)

problème redémarrage restant résolue. ==> faisceau 70MeV + production de rayons-X synchrone.

==> problème sur le stockage (100pC --> 2E6 sur TBT sum), la puissance klystron ne permet pas d'avoir 0 sur TL/BPM.02

18h: Stop ThomX

  1111   Tue Sep 2 07:54:11 2025 MJ, KD,VM,IC, RC, DNUnder ProcessShift summaryLinac Commissionning | Ring Commissioning Injector at 70 MeV 

7h50: mise en chauffe remote (modulateur, frigo/chiller, laser, cyclage)

9h start of the beam

The beam seems not have enogh energy and the phase distribution is not correct

Start changing the temperature of the RF section to be able to accelerate the beam on crest and compensate for the energy change

Start from

Consigne: 29.25 -> 29 -> 28.8 -> 28.5 -> 28.4

Clqrinette: 30 -> 29.7 -> 29.5 ->  29.1

Good T for 70 MeV (28.4, 29.1)

=================================

X_rays 90 keV

** Recherche on-axis methode FWHM (script Kev)
    ==> On-axis approximatif : pos fente3 H=5.10mm V=-23.2.mm , fwhm spectre ~565

** Prise de spectres on_axis et autour du on_axis

** Calibration CdTe avec feuille Au

** Mesure avec diode calibree a 3 position fentes3 (H/Vpos 1, 2, 3 = 8/-15, 8/-5 8/-25)

SANS Alu : 16h01 a 16h22
AVEC Alu : 16h45 a 16h52
                             ==> data dans data/shared

** scan FPC table ==>  17h28 repositionnee au max de flux
           100 pC e- : Mesure diode calib
           17h32, 175 pC (max attenuateur laser) : Mesure diode calib

 

  1115   Tue Sep 9 07:35:39 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 9 septembre 2025 

7h30: mise en chauffe en remote (modulateur, frigo/chiller, laser, cyclage)

 

*** programme ***

- scan faisceau rayons-X et mise au point d'une méthode de repérage du centre

- prise de spectres à différents endroit autour du centre

- mesure taille faisceau

  1125   Thu Sep 18 07:51:55 2025 KD, VM, ICUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 18 septembre 2025 

7h50: mise en chauffe en remote (modulateur, frigo/chiller, laser, cyclage)

==> impossible d'allumer les aimants, trop de plantage de l'IHM cyclage !

==> après insistance le bouton "cyclage" ne semble pas planter (seul le bouton "allumage" semble être en cause)

08h30 Section temperature set to 30 C

Transition to 50 MeV

08h55 HV is 'ON'

10h15 Beam is in the ring without RF. RF Gun phase 235 dg., Sect. Att. 2.46 dB, Sect. Phase   202 dg. Linac steerers H [1.0 -3.17], V [-2.25 2.81], Chargges (BPMs): -135, -129 -135 

We are trying to measure the dispersion in the ring. It is necessary to change the RF, but this creates problems. 

1) By changing FR frequency, problem with triggering

2) Changing the RF frequency changes RF cavity phase !!! Imprtant for beam physics studies. 

3) Sometimes als laser phase

This point should be studies.

For today Nicolas checked the DS Ring_freq which we use. We started the discussion how to approach the issue. 

We use unipolar frequency sweep method with deltaRF = 10 kHz. Sometimes it fails. Even by doing this, the real deltaRF is not 10 kHz but apparently up to 100 Hz different. 

We also observed that by changing the frequency by multiple of 5 keeps the phase almost unchanged but still with mistriggering.

We made the studies of vertical dispersion and orbit.

The current conclusions: we should change the tilt of 2 dipoles in the ring to correct for vertical dispersion, by about 0.5 mrad. 

We contacted Rodolphe Marie to organize this intervention.

With corrected vertical dispersion we made LOCO. Succesfull 1st iteration. Should be continued. 

During the day several problems with RF cavity. 4 times it went to interlock Reflected Power. Took some time to rester it.

18h STOP ThomX

 

Attachment 1: VeticalOrbit.png
VeticalOrbit.png
Attachment 2: VeticalDispersion.png
VeticalDispersion.png
  1137   Tue Oct 14 08:00:18 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 14 octobre 2025 

7h55: mise en chauffe en remote (laser, frigo/chiller, modulateur, cyclage)

==> Nouvelle interface de cyclage, on ne voit plus la progression ou l'état des éléments. (impossible de savoir si le cyclage à bien fonctionné)

10h: recette chargée 50MeV 20251010_15_48_41

Commentaires machine :

* pour un bon stockage l'énergie n'est pas bonne (157.3A sur TL/DP pour etre à 0 TL/BPM.02), position vertical TL/BPM.02 ~ -4mm (stockage possible avec +- 2A sur TL/DP)

/!\ l'orbite n'est pas "flat" à l'IP (comparaison avec chargement de la recette "50MeV_100pC_flatVERTorbit_withEL_20250717_10_58_38.txt"), l'orbite n'est plus "plate" avec l'ancienne recette. 

* probleme dans la EL, le faisceau n'est pas extrait correctement avec la nouvelle recette. 

/!\ probleme BPM/EL, le BPM n'affiche plus la position du faisceau !

* comparaison orbite du matin et de l'après midi, l'orbite change en X pas en Y.

* décalage du délais septum de 4us pour mettre l'impulsion des kicker à peu pres au sommet de l'impulsion ==> il faut désendre le septum de ~ 2V dans ce cas (97.13V --> 95.33V)

** recette sauvée sous : 50MeV_100pC_MRSV_20251014_18_22_53

 

* mise à jour du DS "DS_Ring_RF" pour faire les changement de fréquence anneau et phase au meme endroit.

 

*** Prise de donnée ***

- échantillon chocolat : le plus riche en Cd ne fait pas appaitre de pics !

- Nb présent dans échantillon d'un patien "sain". 

 

Attachment 1: Capture_d’écran_2025-10-14_075918_IHM_cycling.png
Capture_d’écran_2025-10-14_075918_IHM_cycling.png
Attachment 2: BPM_p2A_TL_DP.png
BPM_p2A_TL_DP.png
Attachment 3: orbit_20251014_10h00.png
orbit_20251014_10h00.png
Attachment 4: orbit_20251014_VS_flatorbit_20250717.png
orbit_20251014_VS_flatorbit_20250717.png
Attachment 5: extraction_BPM.png
extraction_BPM.png
Attachment 6: probleme_BPM_EL.png
probleme_BPM_EL.png
Attachment 7: kickers_septum.png
kickers_septum.png
Attachment 8: orbit_20251014_18h00.png
orbit_20251014_18h00.png
  Draft   Thu Oct 16 07:37:52 2025 KD, IC, VMUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 16 octobre 2025 

7h30: mise en chauffe en remote (chillers/frigo, laser, cyclage)

==> impossible de passer en Standby sur le modulateur ==> mail envoyé à Maher.

8h30 We inspected the modulator, made the rondes. The error (status 8 bit) remains. Need for help from Maher. problem: Modumator PSS.

09h12 Maher started the modulator (there was problem with cooling)

10h30 HV is ON

10h44 RF Gun phase is 228 dg Laser Att. 280, Charge device does not work properly

11h18 RCDS on injection, Beam is in the ring

11h20 Modulator went to OFF then start to warm-up

The RF cavity DS  can not read ring RF frequency

12h28 HV ON

Restarting the beam

Working on the WP 50 MeV, orbit correction after dipole rotation. Recette:

TL and EL tuning and measurement of the energy spread.

Beam cut issue in EL investigations.

Optics studies. LOCO.

19h50 STOp THOMX

Attachment 1: Screenshot_from_2025-10-16_19-07-23.png
Screenshot_from_2025-10-16_19-07-23.png
Attachment 2: Screenshot_from_2025-10-16_18-49-04.png
Screenshot_from_2025-10-16_18-49-04.png
Attachment 3: EL_EnergySpread.png
EL_EnergySpread.png
Attachment 4: Screenshot_from_2025-10-16_19-11-13.png
Screenshot_from_2025-10-16_19-11-13.png
Attachment 5: Screenshot_from_2025-10-16_19-20-55.png
Screenshot_from_2025-10-16_19-20-55.png
Attachment 6: TL_EnergySpread.png
TL_EnergySpread.png
  1155   Fri Nov 21 08:02:04 2025 KD MJ DN StudentsUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 21 novembre 2025 

8h: mise en chauffe en remote (modulateur, frigo/chillers, laser, cyclage)
9h: start 
Recette chargée: 50MeV_100pC_MRSV_20251014_18_22_53

10h30: entrée casemate pour CFP

==> mauvais stockage ==> on charge la dernière recette : recipe_recipe_LI_TL_RI_all_20251107_16_22_24

Stockage bon - anneau stable - FPC totalement instable toute la journee

*** Mesure taille X-rays methode fente 1

*** Manip fluo
Spectre calib det Sn foil
Spectre echantillon prostate - feuille Sn sur prostate - X-rays sur support echantillon
Ensuite, spectre idem mais X-rays sur feuille Sn
Ensuite, feuille Sn retiree, spectre sur prostate (on pense ...) - 2 positions faiseau (la 2eme un peu plus centree)

Spectre rouleau fil a souder


 *** Streak : cablage, phases a tuner

- câble refait sur la streak. Prise de donnée sur l'injection du faisceau sur 20 ms, et 1 ms autour de l'injection (avec et sans extraction du faisceau au bout de 10ms)

- reste à affiner la mesure (trig de la streak sur le pulse suivant)

**** Programme TP ****

- mesures rayons-X: fluorescence et mesure taille faisceau "edge methode", radiographie peut être

- mesure streak injection

Attachment 1: IMG-20251121-WA0003.jpg
IMG-20251121-WA0003.jpg
Attachment 2: IMG-20251121-WA0005.jpg
IMG-20251121-WA0005.jpg
Attachment 3: 20251121_185206.JPG
20251121_185206.JPG
  1158   Wed Nov 26 07:47:52 2025 KD MJ VM DN RCUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 26 novembre 2025 

7h50: mise en chauffe à distance (frigo/chiller, laser, modulateur, cyclage)

11h13 Beam is in the ring, 50 MeV, RF gun phase 268 dg. ==> 272 dg., Sect. phase 211 dg., Sect. Att. 2.35 dB. Linac sreerers H [0.74 -2.98], V [-2.56 3.0], Charges (BPMs) -112, -107, -112, -110 pA 

16h: essaye de la recette "Mad180" pour injection dans l'anneau. Impossible car pas de charge transmise sur l'ict3

17h: changement solénoïde 180 --> 230A, on a un peu de charge transmise (70pC pour 100pC). +1A sur QP5 afin d'avoir un faisceau focalisé sur TL/BPM.03. Injection faible possible mais très sensible à la sortie linac (après 2 min plus de charge transmise ==> ligne trop fermée)

*** Spectres a differentes valeurs de bpmTL2_X, et avec la meme orbit a l'IP

bpmTL2 =  0 (~ 11h55)
spectre

bpmTL2 = - 4 (~ 12h00)
spectre
Image fente 1 ==> Taille source X : X = 310 , Y = 51 

bpmTL2 = - 2 (~ 12h17)
spectre
Image fente 1 ==> Taille source X : X = 179 , Y = 45 

bpmTL2 =  0 (~ 12h24)
spectre
Image fente 1 ==> Taille source X : X = 201 , Y = 58

bpmTL2 = + 4 (~ 12h35)
spectre
Image fente 1 ==> Taille source X : X = 170 , Y = 67

bpmTL2 = + 2 (~ 12h45)
spectre
Image fente 1 ==> Taille source X : X = 268 , Y = 62

bpmTL2 = 0 (~ 12h53)
spectre
Image fente 1 ==> Taille source X : X = 234 , Y = 53

 

** Spectre pris a differentes positions de detecteur

 

** Mesures avec diode calibree

~ 13h56 : diode alignee dans le faisceau (au centre, a la louche) - Fente2 : H = + 2 , V = - 11

Quelques deplacements dans le faisceau :
   fente2 : H = + 2 ;  V = - 11 ( ~ 14h55)
   fente2 : H = + 2 ;  V = - 21 ( ~ 15h01)
   fente2 : H = + 10 ; V = - 21 ( ~ 15h05)
   fente2 : H = - 10 ;  V = - 21 ( ~ 15h07)

** Mesures longeur de paquet et injection

- Comparaison en fonction de la qualité du stockage:

   * mesure de la longueur pour l'anneau non optimisé (après dérive), il y a des oscillations synchrotrons (~4mm pic-pic), le stockage est pas stable

   * mesure de la longueur une fois l'anneau réoptimisé (énergie + 3° cavité RF)

- Comparaison taille faisceau VS amplitude cavité RF 

==> pas d'effet visible du FBL (il faut peut être l'ajuster)

=====================================================================

Programme du jour : Spectres a differentes positon bpmTL2_X, avec meme orbite a l'IP

 

Attachment 1: Ring_CavityRamp.png
Ring_CavityRamp.png
Attachment 2: Ring_optVSnoopt.png
Ring_optVSnoopt.png
Attachment 3: 20251126_1ms_cavityRAMP_250kV.tif
Attachment 4: 20251126_1ms_150kV_no_opt.tif
Attachment 5: 20251126_1ms_150kV_opt.tif
Attachment 6: 20251126_1ms_250kV_noFBL.tif
Attachment 7: 20251126_1ms_cavityRAMP_150kV.tif
Attachment 8: 20251126_1ms_cavityRAMP_200kV.tif
  1159   Thu Nov 27 08:01:20 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 27 novembre 2025 

8h: mise en chauffe à distance (modulateur, frigo/chiller, laser, cyclage)

9h30: Chargement de la recette : "recipe_recipe_LI_TL_RI_all_20251126_09_35_14.txt" pour référence

ajustement energie linac et phase cavité RF pour réduire l'oscillation synchrotron.

10h43: prise de référence, dispersion -3cm

10h50: recette dispersion Viktor V1, dispersion -7.3cm

10h55: recette dispersion Viktor V2, dispersion +10.3cm

11h: essaie recette Julien, pas de charge transmise sur ict3. Faisceau très défocalisé et ligne trop fermée (très sensible aux petites variations pointé, énergie etc.)

11h30: essaie recette référence avec feedback injection ring

11h50: recette dispersion Viktor V3, dispersion -9.5cm

12h: effet stockage sur faisceau,

   1) le faisceau est stocké avec la recette de référence, optimisé avec la phase cavité RF et l'energie ==> faible oscillation synchrotron mais stockage instable (grosses pertes en fin de stockage)

   2) le faisceau est optimisé pour augmenté la qualité du stockage. Faible jitter d'injection et stockage stable (sans perte) mais grosses oscillations synchrotron

Les deux mesures de longueur de paquet montre qu'un mauvais stockage peut permettre d'avoir un meilleur faisceau en longitidinale alors qu'un bon stockage peu vite dégrader le faisceau. QUESTION: est ce uniquement en lien avec l'oscillation synchrotron ? Est ce que le fait que le faisceau soit vite dégradé améliore la stabilité du stockage ?

 

===> Au final il ne semble pas y avoir un fort impact sur les jitters en fonction des différents points de dispersion. Le point à 11h30, est le point de référence refait avec le feedback d'injection anneau, il semble moins bon.

Sur l'image le point marque la valeur moyenne et la barre d'erreur l'écart type des 100 mesures (jitter), pour BPM.02-LIB.03 (BPM1) et BPM.04-LIB.03 (BPM3)

 

*** Mesures faites pour chaque points ***

- mean / std, de 100 acquisitions des positions BPM X et Y (des 12 BPM de l'anneau) pour le numéro  buffer (0, 14, 100, 500, 1000, 1999)

- Archivage mesure le stockage et autre donnée

- image de l'orbite en comparaison avec la référence

- image oscillations synchrotron

- image TBTsum 

 

 

 

 

*** Programme ***

Injection stability en fonction de la dispersion 100 pC :

Quantify injector stability vs. TL dispersion

Goal: Understand and minimize the shot-to-shot jitter at ring injection by tuning TL dispersion.

Workflow:

Vary dispersion in the TL in a controlled way (use > 5 optics settings).

For each dispersion setting:

  • Measure horizontal and vertical jitter in the ring (turn-by-turn).
  • Record injected charge, storage efficiency and orbit offset at injection.

Try to match TL dispersion to ring dispersion at injection and identify the setting that minimizes jitter.

Summarise the best TL dispersion setting and assign it as standard optics.

Deliverables:

Jitter vs. TL dispersion curves.

TL optics for minimum jitter.

Beam time: ~2 shifts.

 

 

*** après midi ***

- problème RI-C1 QP.05, problème : electrodes désoudées ==> ressoudées avec Jean-Noel.

- immersion recherche : quelques images de radiofraphie (portable, carte banquaire, baume à lèvre) ==> cavité extrèmement instable !

17h45 : Stop ThomX

Attachment 1: multi_disps.txt
# Values shown are for the Downstream End of each Element (Girder at ref point):
# Index  name      key                      s       l          K1       eta_a      etap_a      beta_a     alpha_a      beta_b     alpha_b
      0  BEGINNING Beginning_Ele        0.000     ---         ---  0.0000E+00  0.0000E+00  3.4460E+01 -4.2400E+00  3.3940E+01 -4.3400E+00
      4  QP1L      Quadrupole           0.554   0.157 -2.8605E+00  0.0000E+00  0.0000E+00  4.2139E+01 -2.3069E+01  3.6267E+01  1.2050E+01
      8  QP2L      Quadrupole           0.904   0.157  1.2447E+01  0.0000E+00  0.0000E+00  4.3958E+01  6.8419E+01  3.8396E+01 -5.7609E+01
     10  QP3L      Quadrupole           1.254   0.157 -1.0657E+01  0.0000E+00  0.0000E+00  1.2759E+01  1.2781E+01  6.9835E+01  3.9379E+01
     16  QP4L      Quadrupole           2.800   0.157  1.3908E+01  4.3505E-01 -2.1774E-01  5.2671E+00  6.8472E-01  2.6443E+00  7.9127E-01
     25  QP5L      Quadrupole           6.083   0.157  4.3710E+00 -2.6604E-01 -4.0250E-02  3.3854E+00  2.1830E+00  4.5194E+00 -4.2245E+00
     29  QP6L      Quadrupole           7.329   0.157 -1.2013E+01  6.1162E-01  2.0776E+00  1.6670E+00 -6.3848E+00  1.7119E+01  2.5043E+01
     31  QP7L      Quadrupole           7.679   0.157  1.3694E+01  1.1540E+00 -3.2350E-01  6.8650E+00  1.0526E+00  6.1700E+00  8.0525E-01
     47  FIN_TL    Marker              12.161   0.000         ---  2.0372E-02 -3.5510E-05  3.4406E+00  1.1859E-02  2.7439E+00 -1.1781E-02


# Values shown are for the Downstream End of each Element (Girder at ref point):
# Index  name      key                      s       l          K1       eta_a      etap_a      beta_a     alpha_a      beta_b     alpha_b
      0  BEGINNING Beginning_Ele        0.000     ---         ---  0.0000E+00  0.0000E+00  3.4460E+01 -4.2400E+00  3.3940E+01 -4.3400E+00
      4  QP1L      Quadrupole           0.554   0.157 -2.8499E+00  0.0000E+00  0.0000E+00  4.2128E+01 -2.2998E+01  3.6277E+01  1.1991E+01
      8  QP2L      Quadrupole           0.904   0.157  1.2444E+01  0.0000E+00  0.0000E+00  4.3908E+01  6.8383E+01  3.8452E+01 -5.7739E+01
     10  QP3L      Quadrupole           1.254   0.157 -1.0662E+01  0.0000E+00  0.0000E+00  1.2730E+01  1.2781E+01  6.9970E+01  3.9458E+01
     16  QP4L      Quadrupole           2.800   0.157  1.3862E+01  4.3528E-01 -2.1481E-01  5.2761E+00  6.8065E-01  2.6438E+00  8.1676E-01
     25  QP5L      Quadrupole           6.083   0.157  4.3419E+00 -2.5678E-01 -4.4937E-02  3.4051E+00  2.1813E+00  4.5165E+00 -4.2290E+00
     29  QP6L      Quadrupole           7.329   0.157 -1.2022E+01  6.0629E-01  2.0548E+00  1.6625E+00 -6.3842E+00  1.7135E+01  2.5085E+01
     31  QP7L      Quadrupole           7.679   0.157  1.3711E+01  1.1422E+00 -3.2553E-01  6.8650E+00  1.0526E+00  6.1700E+00  8.0525E-01
     47  FIN_TL    Marker              12.161   0.000         ---  2.9109E-15 -3.5510E-05  3.4406E+00  1.1859E-02  2.7439E+00 -1.1781E-02


# Values shown are for the Downstream End of each Element (Girder at ref point):
# Index  name      key                      s       l          K1       eta_a      etap_a      beta_a     alpha_a      beta_b     alpha_b
      0  BEGINNING Beginning_Ele        0.000     ---         ---  0.0000E+00  0.0000E+00  3.4460E+01 -4.2400E+00  3.3940E+01 -4.3400E+00
      4  QP1L      Quadrupole           0.554   0.157 -2.8506E+00  0.0000E+00  0.0000E+00  4.2129E+01 -2.3002E+01  3.6276E+01  1.1995E+01
      8  QP2L      Quadrupole           0.904   0.157  1.2448E+01  0.0000E+00  0.0000E+00  4.3906E+01  6.8413E+01  3.8453E+01 -5.7762E+01
     10  QP3L      Quadrupole           1.254   0.157 -1.0663E+01  0.0000E+00  0.0000E+00  1.2716E+01  1.2797E+01  6.9987E+01  3.9466E+01
     16  QP4L      Quadrupole           2.800   0.157  1.3816E+01  4.3551E-01 -2.1189E-01  5.2913E+00  6.7717E-01  2.6419E+00  8.3734E-01
     25  QP5L      Quadrupole           6.083   0.157  4.3105E+00 -2.4757E-01 -4.9608E-02  3.4257E+00  2.1798E+00  4.5204E+00 -4.2339E+00
     29  QP6L      Quadrupole           7.329   0.157 -1.2028E+01  6.0096E-01  2.0320E+00  1.6581E+00 -6.3836E+00  1.7151E+01  2.5129E+01
     31  QP7L      Quadrupole           7.679   0.157  1.3728E+01  1.1305E+00 -3.2756E-01  6.8650E+00  1.0526E+00  6.1700E+00  8.0525E-01
     47  FIN_TL    Marker              12.161   0.000         --- -2.0372E-02 -3.5510E-05  3.4406E+00  1.1859E-02  2.7439E+00 -1.1781E-02


# Values shown are for the Downstream End of each Element (Girder at ref point):
# Index  name      key                      s       l          K1       eta_a      etap_a      beta_a     alpha_a      beta_b     alpha_b
      0  BEGINNING Beginning_Ele        0.000     ---         ---  0.0000E+00  0.0000E+00  3.4460E+01 -4.2400E+00  3.3940E+01 -4.3400E+00
      4  QP1L      Quadrupole           0.554   0.157 -2.8526E+00  0.0000E+00  0.0000E+00  4.2131E+01 -2.3016E+01  3.6274E+01  1.2006E+01
      8  QP2L      Quadrupole           0.904   0.157  1.2456E+01  0.0000E+00  0.0000E+00  4.3907E+01  6.8464E+01  3.8449E+01 -5.7784E+01
     10  QP3L      Quadrupole           1.254   0.157 -1.0666E+01  0.0000E+00  0.0000E+00  1.2697E+01  1.2821E+01  7.0000E+01  3.9468E+01
     16  QP4L      Quadrupole           2.800   0.157  1.3749E+01  4.3585E-01 -2.0761E-01  5.3147E+00  6.7242E-01  2.6411E+00  8.6497E-01
     25  QP5L      Quadrupole           6.083   0.157  4.2657E+00 -2.3404E-01 -5.6254E-02  3.4551E+00  2.1775E+00  4.5285E+00 -4.2408E+00
     29  QP6L      Quadrupole           7.329   0.157 -1.2037E+01  5.9327E-01  1.9985E+00  1.6517E+00 -6.3828E+00  1.7175E+01  2.5190E+01
     31  QP7L      Quadrupole           7.679   0.157  1.3752E+01  1.1134E+00 -3.3051E-01  6.8650E+00  1.0526E+00  6.1700E+00  8.0525E-01
     47  FIN_TL    Marker              12.161   0.000         --- -5.0000E-02 -3.5510E-05  3.4406E+00  1.1859E-02  2.7439E+00 -1.1781E-02


# Values shown are for the Downstream End of each Element (Girder at ref point):
# Index  name      key                      s       l          K1       eta_a      etap_a      beta_a     alpha_a      beta_b     alpha_b
      0  BEGINNING Beginning_Ele        0.000     ---         ---  0.0000E+00  0.0000E+00  3.4460E+01 -4.2400E+00  3.3940E+01 -4.3400E+00
      4  QP1L      Quadrupole           0.554   0.157 -2.8450E+00  0.0000E+00  0.0000E+00  4.2123E+01 -2.2964E+01  3.6281E+01  1.1964E+01
      8  QP2L      Quadrupole           0.904   0.157  1.2429E+01  0.0000E+00  0.0000E+00  4.3900E+01  6.8288E+01  3.8468E+01 -5.7716E+01
     10  QP3L      Quadrupole           1.254   0.157 -1.0657E+01  0.0000E+00  0.0000E+00  1.2760E+01  1.2741E+01  6.9966E+01  3.9449E+01
     16  QP4L      Quadrupole           2.800   0.157  1.3973E+01  4.3472E-01 -2.2185E-01  5.2383E+00  6.8967E-01  2.6569E+00  7.5983E-01
     25  QP5L      Quadrupole           6.083   0.157  4.4229E+00 -2.7897E-01 -3.3064E-02  3.3534E+00  2.1853E+00  4.5139E+00 -4.2169E+00
     29  QP6L      Quadrupole           7.329   0.157 -1.2003E+01  6.1951E-01  2.1104E+00  1.6740E+00 -6.3857E+00  1.7093E+01  2.4975E+01
     31  QP7L      Quadrupole           7.679   0.157  1.3667E+01  1.1710E+00 -3.2055E-01  6.8650E+00  1.0526E+00  6.1700E+00  8.0525E-01
     47  FIN_TL    Marker              12.161   0.000         ---  5.0000E-02 -3.5510E-05  3.4406E+00  1.1859E-02  2.7439E+00 -1.1781E-02
Attachment 2: recipe_recipe_LI_TL_RI_all_20251126_09_35_14.txt
LI/PS/COL.01/currentSetpointPM : <type 'float'> : 66.47
LI/PS/COL.02/currentSetpointPM : <type 'float'> : 230.0
EL/PS/QP.01/currentSetpointPM : <type 'float'> : -3.94
EL/PS/QP.02/currentSetpointPM : <type 'float'> : 5.13
EL/PS/QP.03/currentSetpointPM : <type 'float'> : -2.47
EL/PS/QP.04/currentSetpointPM : <type 'float'> : -3.28
EL/PS/QP.05/currentSetpointPM : <type 'float'> : 3.01
EL/PS/QP.06/currentSetpointPM : <type 'float'> : 1.99
EL/PS/QP.07/currentSetpointPM : <type 'float'> : -2.84
LI/PS/STR.01-H.01/currentSetpointPM : <type 'float'> : 0.744495394655
LI/PS/STR.01-V.01/currentSetpointPM : <type 'float'> : -2.55611182033
LI/PS/STR.02-V.01/currentSetpointPM : <type 'float'> : 3.14718161006
LI/PS/STR.02-H.01/currentSetpointPM : <type 'float'> : -2.87618448919
EL/PS/STR.02-V.01/currentSetpointPM : <type 'float'> : 0.0
EL/PS/STR.02-H.01/currentSetpointPM : <type 'float'> : 8.0
TL/PS/QP.01/currentSetpointPM : <type 'float'> : -0.1700483772
TL/PS/QP.02/currentSetpointPM : <type 'float'> : 3.5
TL/PS/QP.03/currentSetpointPM : <type 'float'> : -3.40148253
TL/PS/QP.04/currentSetpointPM : <type 'float'> : 2.02
TL/PS/QP.05/currentSetpointPM : <type 'float'> : 2.02
TL/PS/QP.06/currentSetpointPM : <type 'float'> : -3.7
TL/PS/QP.07/currentSetpointPM : <type 'float'> : 3.7
RI-C1-C2/PS/SP.03/currentSetpointPM : <type 'float'> : -1.83626944534
RI-C1/PS/QP.01/currentSetpointPM : <type 'float'> : 3.06436602905
RI-C1/PS/QP.02/currentSetpointPM : <type 'float'> : -1.44273612065
RI-C1/PS/QP.03/currentSetpointPM : <type 'float'> : -1.75851554175
RI-C1/PS/QP.04/currentSetpointPM : <type 'float'> : 3.25098431127
RI-C1/PS/QP.05/currentSetpointPM : <type 'float'> : -3.62669034804
RI-C1/PS/QP.06/currentSetpointPM : <type 'float'> : 2.41679703056
RI-C1/PS/QP.07/currentSetpointPM : <type 'float'> : 5.37507690285
RI-C1/PS/QP.08/currentSetpointPM : <type 'float'> : -6.01739765821
RI-C1/PS/QP.09/currentSetpointPM : <type 'float'> : -6.1066305017
RI-C1/PS/QP.10/currentSetpointPM : <type 'float'> : 5.42107968349
RI-C1/PS/QP.11/currentSetpointPM : <type 'float'> : 2.41073325341
RI-C1/PS/QP.12/currentSetpointPM : <type 'float'> : -3.74160359773
RI-C1-C2/PS/SP.01/currentSetpointPM : <type 'float'> : 0.276011295791
RI-C2/PS/QP.01/currentSetpointPM : <type 'float'> : 3.27755669647
RI-C2/PS/QP.02/currentSetpointPM : <type 'float'> : -1.59686996779
RI-C2/PS/QP.03/currentSetpointPM : <type 'float'> : -1.84944684805
RI-C2/PS/QP.04/currentSetpointPM : <type 'float'> : 3.33472861937
RI-C2/PS/QP.05/currentSetpointPM : <type 'float'> : -3.63782047595
RI-C2/PS/QP.06/currentSetpointPM : <type 'float'> : 2.37550666969
RI-C2/PS/QP.07/currentSetpointPM : <type 'float'> : 5.33582360514
RI-C2/PS/QP.08/currentSetpointPM : <type 'float'> : -6.03274378372
RI-C2/PS/QP.09/currentSetpointPM : <type 'float'> : -5.99504206123
RI-C2/PS/QP.10/currentSetpointPM : <type 'float'> : 5.31153116544
RI-C2/PS/QP.11/currentSetpointPM : <type 'float'> : 2.48463744172
RI-C2/PS/QP.12/currentSetpointPM : <type 'float'> : -3.76741453121
RI-C1-C2/PS/SP.02/currentSetpointPM : <type 'float'> : 3.81502301981
TL/PS/STR.01-V.01/currentSetpointPM : <type 'float'> : 0.0
TL/PS/STR.01-H.01/currentSetpointPM : <type 'float'> : 0.0
TL/PS/STR.02-V.01/currentSetpointPM : <type 'float'> : -8.0
TL/PS/STR.02-H.01/currentSetpointPM : <type 'float'> : -3.0
TL/PS/STR.03-V.01/currentSetpointPM : <type 'float'> : 0.794
TL/PS/STR.03-H.01/currentSetpointPM : <type 'float'> : 7.716
TL/PS/STR.04-V.01/currentSetpointPM : <type 'float'> : 4.753
TL/PS/STR.04-H.01/currentSetpointPM : <type 'float'> : 6.428
TL/PS/DPI.01/currentSetpointPM : <type 'float'> : 7.938
RI-C1/PS/STR.01-V.01/currentSetpointPM : <type 'float'> : 4.00889873052
RI-C1/PS/STR.01-H.01/currentSetpointPM : <type 'float'> : -2.94482865272
RI-C1/PS/STR.02-V.01/currentSetpointPM : <type 'float'> : -0.987669112358
RI-C1/PS/STR.02-H.01/currentSetpointPM : <type 'float'> : -1.76585719278
RI-C1/PS/STR.03-V.01/currentSetpointPM : <type 'float'> : -3.26026864154
RI-C1/PS/STR.03-H.01/currentSetpointPM : <type 'float'> : 0.00371314934889
RI-C1/PS/STR.04-V.01/currentSetpointPM : <type 'float'> : 5.72251814247
RI-C1/PS/STR.04-H.01/currentSetpointPM : <type 'float'> : 0.0969259217919
RI-C1/PS/STR.05-V.01/currentSetpointPM : <type 'float'> : 0.132553818996
RI-C1/PS/STR.05-H.01/currentSetpointPM : <type 'float'> : -2.59504238267
RI-C1/PS/STR.06-V.01/currentSetpointPM : <type 'float'> : -1.79567757428
RI-C1/PS/STR.06-H.01/currentSetpointPM : <type 'float'> : -4.85981209589
EL/PS/STR.01-H.01/currentSetpointPM : <type 'float'> : 0.0
EL/PS/DPI.01/currentSetpointPM : <type 'float'> : 0.0
RI-C2/PS/STR.01-V.01/currentSetpointPM : <type 'float'> : -2.71485643949
RI-C2/PS/STR.01-H.01/currentSetpointPM : <type 'float'> : -6.0376417579
RI-C2/PS/STR.02-V.01/currentSetpointPM : <type 'float'> : -0.664835392405
RI-C2/PS/STR.02-H.01/currentSetpointPM : <type 'float'> : -1.54646010356
RI-C2/PS/STR.03-V.01/currentSetpointPM : <type 'float'> : 4.28475016291
RI-C2/PS/STR.03-H.01/currentSetpointPM : <type 'float'> : 3.84379917319
RI-C2/PS/STR.04-V.01/currentSetpointPM : <type 'float'> : -7.71572597127
RI-C2/PS/STR.04-H.01/currentSetpointPM : <type 'float'> : 1.18413063336
RI-C2/PS/STR.05-V.01/currentSetpointPM : <type 'float'> : 0.586667664296
RI-C2/PS/STR.05-H.01/currentSetpointPM : <type 'float'> : 0.784765660279
RI-C2/PS/STR.06-V.01/currentSetpointPM : <type 'float'> : 1.86755579082
RI-C2/PS/STR.06-H.01/currentSetpointPM : <type 'float'> : 1.36213305755
EL/PS/STR.01-V.01/currentSetpointPM : <type 'float'> : 0.0
RI-C1/PS/DP.01/currentSetpointPM : <type 'float'> : 159.3
TL/PS/DP.01/currentSetpointPM : <type 'float'> : 159.3
EL/PS/DP.01/currentSetpointPM : <type 'float'> : 159.3
er/pe/inj_kick_ps/Voltage : <type 'float'> : 6344.0
er/pe/inj_kick_ps/Current : <type 'float'> : 40.0
er/pe/ext_kick_ps/Voltage : <type 'float'> : 6344.0
er/pe/ext_kick_ps/Current : <type 'float'> : 40.0
er/pe/pass_sept_ps/Current : <type 'float'> : 6.0
er/pe/pass_sept_ps/Voltage : <type 'float'> : 96.1500015259
TEST/HL/ThomX_PhotoCathode/Horizontal_Iris_Position_set : <type 'float'> : 5.003
TEST/HL/ThomX_PhotoCathode/Vertical_Iris_Position_set : <type 'float'> : 4.553
Attachment 3: Beam_no_opt.tif
Attachment 4: Beam_opt.tif
Attachment 5: BPM_jitters.png
BPM_jitters.png
  1165   Tue Dec 9 08:00:00 2025 KD MJ RC DNUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 09 décembre 2025 - 70 MeV et 40 MeV 

8h : mise en chauffe en remote (modulateur, cyclage, frigo/chillers, laser)

Stockage 70MeV ok, le faisceau  MRSV semble gros en horizontal (cavité RF 250kV)

e-:

attenuateur section : 0.18dB

phase section : 252°

chiller: 28.4°C

Freq: 500.03165 MHz

phase shifter manuel : 4870

longueur paquet ~ 40ps 

cavité FP:

TZ: -1.75mm

phases 33MHz : [synchro, CFP] = [184° 343.5°]

phase 500MHz : 9.1V (negative)

 

17h: passage à 40MeV, steerer anneau à 0

e-:

attenuateur section : 3.77dB

phase section : 214°

chiller: 28.4°C

Freq: 500.11851 MHz

phase shifter manuel : 8600

longueur paquet pas assez de MRSV pour la mesure

cavité FP:

TZ: -1.75mm

phases 33MHz : [synchro, CFP] = [184° 300.6°]

phase 500MHz : 4.2V (positive)

=========================================

X-rays :

** 70 MeV
Scan vertical FPC + Mesure taille source avec fente 1
Prises de spectres + calib feuille Pb et Au

** 40 MeV 
Prise de spectres + calib feuille Sn

Attachment 1: orbite_40MeV.png
orbite_40MeV.png
Attachment 2: orbite_70MeV.png
orbite_70MeV.png
Attachment 3: TBTsum_40MeV.png
TBTsum_40MeV.png
Attachment 4: TBTsum_70MeV.png
TBTsum_70MeV.png
Attachment 5: 2025-12-09_13_38_35_OBL_DG_MRSV_01-CCD_01_RAW.png
2025-12-09_13_38_35_OBL_DG_MRSV_01-CCD_01_RAW.png
Attachment 6: 2025-12-09_17_53_11_OBL_DG_MRSV_01-CCD_01_RAW.png
2025-12-09_17_53_11_OBL_DG_MRSV_01-CCD_01_RAW.png
  1169   Mon Dec 15 08:06:26 2025 KD MJUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 15 décembre 2025 

8h: mise en chauffe en remote (chiller/frigo, laser, modulateur, cyclage)

* cannot enter to the ring with the recipe "40_MeV_Enough_Good_20251211_14_07_28", probably due to mis alignment procedure of the QP1-QP3.
* reset de TL steerers with the recipe "40MeV_20250401_15_09_50", first turn ok but no storage.
* steerers Ring to 0.

12h --> back to previous cathod point (last week tuning was done at that position)

  • TEST/HL/ThomX_PhotoCathode/Horizontal_Iris_Position_set : <type 'float'> : 4.714
  • TEST/HL/ThomX_PhotoCathode/Vertical_Iris_Position_set : <type 'float'> : 3.524

17h: essaie avec la recette initial de mardi "recipe_recipe_LI_TL_RI_all_20251209_17_54_51.txt"

==> difficile de retouver le TBTsum de mardi, ==> après quelques ajustements (rcds, etc). on retrouve quelques choses de passable

==> MRSV totalement différent: long, étalé et pas au même endroit (à droite au lieu d'être hors écran à gauche)

==> problème de répétabilité. La seule différence est la température de la section. 

 

*** Scan FPC table (~16h) - A l'oeil FWHM ~ 300 microns ==> rms ~ 128 ==> sig_ele_Vert ~ 107 ==> sig_Source_Vert ~ 60 microns

Bilan imagerie du jour :
tres bas flux et faisceau tres instable .==>  Pas de contraste de phase visible. On espere que demain sera mieux ! 

======================================================================================================

*** programme ***

Mesure imagerie X à basse énergie (40MeV)

 

  1170   Tue Dec 16 07:18:46 2025 KD, IC, RC,VM Under ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 16 décembre 2025 

7h10: mise en chauffe en remote (chiller/frigo, laser, cyclage, modulateur).

à cause du faible flux d'hier et de la non répétabilité des recettes de la semaine précédente :

* essaie avec la section à 28.4°C (seule condition différente de mardi dernier)

8h10: démarrage. 

chargement de la recette du "recipe_recipe_LI_TL_RI_all_20251209_17_54_51.txt", rien sur la caméra sst, on retrouve les paramètres de mardi (3.74dB, 210°C phase section)

image SST vraiment décalé ==> quelques chose à bougé sur la machine ? ==> réalignement quads

** après réalignement et ajustement (phase + atténuateur) 

 

e-:

attenuateur section : 3.77dB

phase section : 214°

chiller: 28.4°C

Freq: 500.11851 MHz

phase shifter manuel : 8600

longueur paquet pas assez de MRSV pour la mesure

10h43 Results: T_sect. 30dg.C (consigne 29.2), laser spot position: 4.714 H, 3.524 V; starting from the receipt recipe_recipe_LI_TL_RI_all_20251211_14_07_28.txt

RF gun phase 222 dg., Sect. Att. 3.987, phase 197 dg. TL/BPM02 X= +2 mm, Linac steerers: H [0.97 -3.6], V [-3.0 3.9], Charges (BPMs): -115, -109, -112, -112, -112 pC, 

Beam in the ring after RCDS on TL RF 100 kV, phase 9.0 dg. MRSV 27 pix, (sometime 22 pix). RCDS on ring V cor. X I3+I4 up to 12000 pA but with vertical step at IP ( recipe_recipe_LI_TL_RI_all_20251216_10_41_50.txt)

10h58 Went to the receipt recipe_recipe_LI_TL_RI_all_20251216_10_09_21.txt to have more flat vertical orbit (4000 pA after FPC table scan)

QUAD cycling

11h30 We reoptimized the vertical orbit to have smaller angle. I3+I4 ~7-8 kpA Receipt: recipe_recipe_LI_TL_RI_all_20251216_11_29_31.txt (MRSV 24 - 26 pix, Hor. tune 0.2 at maximum flux)

18h20 Laser Att ==>297 ,charges:-159,-152,-157,-156,-155 pC, Solenoid 225 A, Sum of TbTsum 2e11, from 15e11, MRSV 35.8 pix, I3+I4 about 8000, then FPC desynchronized.

18h43 Stop ThomX

Attachment 1: 2025-12-16_08_30_21_tl_dg_sst_02-ccd_01_RAW.png
2025-12-16_08_30_21_tl_dg_sst_02-ccd_01_RAW.png
Attachment 2: 2025-12-16_08_35_25_tl_dg_sst_02-ccd_01_RAW.png
2025-12-16_08_35_25_tl_dg_sst_02-ccd_01_RAW.png
  Draft   Wed Dec 17 07:17:06 2025 KD, IC, MV, DN,Under ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 17 décembre 2025 

7h15: mise en chauffe en remote (chiller/frigo, laser, modulateur, cyclage)

8h33 HV ON

09h30 Beam is in the ring 40 MeV, RF 100 kV ==> 150 kV I3+I4 up to 14000 pA. Vertical step at IP from -2 mm to +2 mm. MRSW 24.5 pix. Receipt  recipe_recipe_LI_TL_RI_all_20251217_09_17_49.txt

10h19 Hor. tune 0.177, sum of TbTsum 2e11. TL/BPM02 X=+3 mm, RF cavity phase 5 dg. Sect Att. 3.967 dB, Sect. phase 197 dg. RF gun phase 222 dg. Charges: -165, -157, -159, -161, -158 pA Laser Att. 300, Sol. 223 A

 

 

*** Programme ***

* faire 1 à 2 tomographie à 40 Mev avant de passer aux manips à 70MeV (besoin de flux pour la rapidité d'acquisition)

* passage à 70MeV, mesure de dosimétrie et spectre angulaire

  1173   Fri Dec 19 07:22:31 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 19 décembre 2025 

7h20: mise en chauffe en remote (frigo/chiller, laser, modulateur, cyclage)

 

*** Programme ***

- dernière demie-journée de mesures. Mesure de dosimétrie (dose transverse)

- autres ?

  1180   Tue Jan 13 07:58:50 2026 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 13 janvier 2026 

7h55 : mise en chauffe en remote (chiller/frigo, laser, modulateur, cyclage)

9h : démarrage, pas de soucis au niveau du trig

16h30 : demarrage anneau pour recette 230A

les phases ont changées :

dephaseur manuel: 1182 pour 50MeV

prise de donnée à 230A (taille faisceau + spectre)

  1186   Thu Jan 22 07:37:58 2026 IC, VMUnder ProcessShift summaryLinac Commissionning | Ring Commissioning Beam studies 

7h45: mise en chauffe en remote (modulateur, laser, frigo/chillers)

08h41 HV is on

08h49 RF gun phase 152 dg., sect phase 208 dg. beam is in the ring W/O RF

08h58 Standby, Cycling all magnets

09h30 HV is on

12h47 Standby

12h58 HV is on

14h26 Laser phse jumped from 143 dg. to 261 dg. Ring RF cavity phase ==> -73.5 dg. from -15 dg.

16h40 Laser phse jumped from 257 dg. to 44 dg.Ring RF cavity phase ==> -15 dg. from 33 dg.

17h07 Laser phse jumped from 44 dg. to 218 dg. Ring RF cavity phase ==> -83.5 dg. from +33 dg.

18h13 HV is off, cycling ring quads

18h48 HV is on

22h01 Stop ThomX

  1202   Wed Mar 4 08:35:23 2026 VM, MJ, DN, RCFixedShift summaryLinac Commissionning | Ring Commissioning Check point du fonctionnement anneau du 24/02 suite a l'ajout de resistances dipole le 24/02 au soir 

08h35 Warm-up ThomX: Modulator, Laser, Fridge

Programme shift : verifier que la recette orbite plate utilisee lors du shift du 24/02/2026 (= orbite PLATE, vers 15h) est toujours ok apres l'ajout de resistance sur dipole anneau (resistance installee apres le shift, = le 24/02 au soir)

08h40 Chillers were started, cycling all magnets.
09h47 HV is on but there are no triggers. Failed to connect to device li/op/opt.02-las.01-asp.01. The photocathode laser control mashine is off.
10h10 The photocathode laser control mashine is on. The laser amplifier was started.
10h29 Misstriggering caused modulator interlocks
10h44 It is OK with triggering, exept the photocathode laser.
11h15 Laser is ok, phase 133 dg.

11h48 The laser spot moves out of the screen, Hayg fixed it

12h35 Transfocator_20260225_17_33_57.txt loaded. Linac steeres were adjusted. Laser phase 127 dg., Sect. att. 2.532 dB, sect. phase 225 dg. linac steerers: H [-0.21 -2.66], V [-2.47 3.32], RF 100 kV, phase -39 dg., charges around -100 pC

On ne voit pas le centre du faisceau X sur DECTRIS - Trop allonge verticalement
Viktor "ajuste" la recette ==> on voit un tout petit petit petit peu mieux le centre ...
Flux < 5000  .....
Scan FPC ==> faisceau enorme cf screenshot 1_scanFPC_recipe_ou_on_voit_le_centre.png

Retour recette du depart orbites a peu pres plates plates
Flux minuscule
Scan FPC ==> faisceau enorme cf screenshot 2_scanFPC_receipe_FLAT_centre_pas_visible.png

Optimisation phases etc par Viktor
Flux minuscule
Scan FPC ==> faisceau enorme cf screenshot 3_scanFPC_receipe_FLAT_OPTIM_centre_pas_visible.png 

16h58 Standby, removing the additional shunt resistor from the bend #3

17h42 HV is on

18h00 recipe_recipe_LI_TL_RI_all_20260224_14_54_20.txt loaded
Faisceau a peu pres au centre du tube
Flux ~ 20.000
Comparaison avec shift du 24/02 (spectre onaxis et V+40) ==>
cf screenshot compar_20260224_20260304_after_cut_resistance.png 
==> c'est OK, spectres tres similairees

18h26 ThomX stopped

CONCLUSION : impossible d'obtenir un faisceau electrons correct avec la nouvelle resistance. Retirer la resistance a permis de retrouver les resultats du 24/02

DEMAIN : demarrage des etudes matching a ce point de fonctionnemenet
A 100 pC
  - Sol 230
  - Sol 242
  - Sol 250 100 pC,
puis SOL 230 a 200 pC 

Attachment 1: Screenshot_from_2026-03-04_14-29-12.png
Screenshot_from_2026-03-04_14-29-12.png
Attachment 2: Screenshot_from_2026-03-04_14-00-48.png
Screenshot_from_2026-03-04_14-00-48.png
Attachment 3: Screenshot_from_2026-03-04_18-19-20.png
Screenshot_from_2026-03-04_18-19-20.png
Attachment 4: 1_scanFPC_recipe_ou_on_voit_le_centre.png
1_scanFPC_recipe_ou_on_voit_le_centre.png
Attachment 5: 2_scanFPC_receipe_FLAT_centre_pas_visible.png
2_scanFPC_receipe_FLAT_centre_pas_visible.png
Attachment 6: 3_scanFPC_receipe_FLAT_OPTIM_centre_pas_visible.png
3_scanFPC_receipe_FLAT_OPTIM_centre_pas_visible.png
Attachment 7: compar_20260224_20260304_after_cut_resistance.png
compar_20260224_20260304_after_cut_resistance.png
  1210   Thu Mar 12 15:17:49 2026 MJ, KDFixedShift summaryLinac Commissionning | Ring Commissioning MONOCHROMATEUR - 12 mars 2026 

Alignement CdTe On-axis a l'oeil
Prises spectres ouvertures fentes2 0.3x0.3 : OnAxis , V+40 , H+40 , H+20 , V+20 , H-20 , H+20 , V-20

-----------------------------------------------------------------------------------------------------------

Alignement MONO parallele au faisceau : Hexa mono Ry_mono = -0.1 deg

----------------------------------------------------------------------------------------------------------

Fente2 OnAxis

Ry = - 2.6 - 0.1 deg (43.6 keV code Kilperic)  - R_sample = 5.2 deg

Spectres Fentes2 ouvertes ** 1 x 1 mm
                                         ** Max

Ry = - 2.5 - 0.1 deg (44.3 keV code Kilperic)

Spectres Fentes2 ouvertes ** Max
                                         ** 1 x 1 mm
                                         ** 0.5 x 0.5
                                         ** 2 x 2
                                         ** 3 x 3

Ry = - 2.45 - 0.1 deg (46 keV code Kilperic)

Spectres Fentes2 ouvertes ** Max
                                         ** 0.5 x 0.5
                                         ** 2 x 2

Mesure du flux diode calib avec et sans MONO

SANS MONO
    Fentes2 ** 1 x 1 mm 12h50-51
                 ** 2 x 2  12h51-52
                 ** 3 x 3  12h52-53

Avec MONO : IMPOSSIBLE trop de bruit de fond

Mesure du flux avec DECTRIS

Ry = - 2.45 ==> Images 404 et 405 (13h11)
Ry = - 2.5  ==> Images 406 et 407 (13h12)
Ry = - 2.6  ==> Images 408 et 409 (13h13)
REF Ry = - 0.1 ==> Images 410 et 411 (13h18)

 

Fente2 V+40

Ry = - 2.9 - 0.1 deg (39 keV code Kilperic)

Spectres Fentes2 ouvertes ** 1 x 1 mm
                                         ** Max
                                         ** 2 x 2

Mesure du flux avec DECTRIS

Ry = - 2.9 ==> Images 415 et 416 (13h41)
REF Ry = - 0.1 ==> Images 418 et 419 (13h43)

Prise spectre ref a V+40

 

Fente2 V+70

Ry = - 3.8 - 0.1 deg (30 keV code Kilperic)

Spectres Fentes2 ouvertes ** 1 x 1 mm
                                         ** Max
                                         ** 2 x 2
                                         ** 5 x 5
                                         ** et divers autres

Fente2 H-37

Prise spectre ref a H -37

Pour Ry = - 2.9° (angle mono), R_sample = 6.5° (2theta)

Spectres Fentes2 ouvertes ** 2 x 2 mm
                                         ** Max

Fente2 H-64

Prise spectre ref a H -64

Pour Ry = - 3.8° (angle mono), R_sample = 8.5° (2theta) ==> Emean ~ 27keV

Pour Ry = - 3.2° (angle mono), R_sample = 7.3° (2theta) ==> Emean ~ 31.5keV

Fente2 H+36

Prise spectre ref a H +36

Pour Ry = - 2.9° (angle mono), R_sample = 5.5° (2theta) ==> Emean ~ 42keV

Pour Ry = - 3.2° (angle mono), R_sample = 6.1° (2theta) ==> Emean ~ 38keV

 

 

  1212   Sun Mar 15 18:42:53 2026 MJ HG VKFixedShift summaryLinac Commissionning | Ring Commissioning Etudes de points MATCHING - 13 mars 2026 

Programme : Etudes points Matching
==============================

Fentes2 centre faisceau a l’œil [H , V] = [7 , -18]

(Mot Det Ty = 10000 , TX = 0)

Orbites e- : idem que le 12/03 et le 11/03 (plate en Y, tout petit angle en X)

Check meilleures position de X_fpc 

X_fpc de -1.4 a -1.7 , prise de spectres V+40 et OnAxis 

- Ne change pratiquement rien aux dromadaires V+40

- On se place à X_fpc = -1.7 mm

DISTANCE Hexa_ech - Photonic = 43 cm

Sol = 230, iris=1.3

** Flux ~ 18000 (~ 12000 I3, ~ 6000 I4)

** Spectre OnAxis

** Mesure de taille source Photonic

(Mot Det Ty = 12000 , TX = 18000)
(Fente1 Hpos = -10.5 / Vpos = 2 / Hapert = 6 / Vapert = 5)

LSF [H , V] = [52 , 132]  um

** Long paquet : 87 ps inj à 190 ps (FWHM)

** Quadscan Q1 :

Emit [x , y] = [1.8 , 1.8]
Beta [x , y] = [6.5 , 4.7]
alpha [x , y] = [-2 , -1]

 

Sol = 242, iris=1.0

** Flux ~ 8-9000

** Mesure de taille source Photonic

LSF [H , V] = [69 , 197] um 
LSF [H , V] = [68 , 188]  um               MOINS BON

** PAS de prise de spectre

** Quadscan Q1 :

Emit [x , y] = [2.3 , 3.6]
Beta [x , y] = [54 , 44]
alpha [x , y] = [-11 , -8.5]

Avec autre fit du quadscan Q1 (Sol = 242, iris=1.0)

Emit [x , y] = [3.9 , 5.8]
Beta [x , y] = [32 , 26]
alpha [x , y] = [-7 , -5.4]

** Flux ~ 9000 (6000 I3 , 3000 I4)

** Mesure de taille source Photonic

LSF [H , V]  = [66 , 192] um
LSF [H , V] = [63 , 186] um

** 1 spectre OnAxis

** Long paquet : 100 ps inj à 200 ps (FWHM)

MOINS bien que Sol = 230

 

Sol = 238, iris=1.0

** Quadscan Q1 :

Emit [x , y] = [2.4 , 1.7]
Beta [x , y] = [31 , 40]
alpha [x , y] = [-6 , -8]

** Flux ~ 10000

** 1 spectre ONAxis

On passe l’iris de 1.0 à 1.3, avec même optique

** 1 spectre ONAxis

** Flux ~ 10000

MOINS bien que Sol = 230

 

Retour a Sol = 230, iris = 1.3

** Prise de spectres

V+20 / V-20 /  V-20 H+20 / H+20 / H+20 V+20 / H-20 V+20 / H-20 / H-20 V-20
V-40
V+40
H+40

** Mesure de taille source Photonic

LSF [H , V] = [67 , 168] um

 

  Draft   Wed Mar 25 07:28:22 2026 Entered by Super Team from 127.0.0.1 on Wed Mar 25 07:28:09 2026 Shift summaryLinac Commissionning | Ring Commissioning Ring studies 

7h30 : mise en chauffe en remote (frigo/chiller, modulateur, laser, cyclage)

08h40 HV ON

==> 50 MeV, Manual phase shifter value set to 3209. Sect. temperatute set to 30C at clarinette, (consigne = 29.2C).

 

Tune studies

LOCO

23h STOP ThomX
 