Message ID: 1111     Entry time: Tue Sep 2 07:54:11 2025
 Author: MJ, KD,VM,IC, RC, DN 
 Status: Under Process 
 Type: Shift summary 
 Category: Linac Commissionning | Ring Commissioning 
 Important:
 Subject: Injector at 70 MeV 
 Icon:  

7h50: mise en chauffe remote (modulateur, frigo/chiller, laser, cyclage)

9h start of the beam

The beam seems not have enogh energy and the phase distribution is not correct

Start changing the temperature of the RF section to be able to accelerate the beam on crest and compensate for the energy change

Start from

Consigne: 29.25 -> 29 -> 28.8 -> 28.5 -> 28.4

Clqrinette: 30 -> 29.7 -> 29.5 ->  29.1

Good T for 70 MeV (28.4, 29.1)

=================================

X_rays 90 keV

** Recherche on-axis methode FWHM (script Kev)
    ==> On-axis approximatif : pos fente3 H=5.10mm V=-23.2.mm , fwhm spectre ~565

** Prise de spectres on_axis et autour du on_axis

** Calibration CdTe avec feuille Au

** Mesure avec diode calibree a 3 position fentes3 (H/Vpos 1, 2, 3 = 8/-15, 8/-5 8/-25)

SANS Alu : 16h01 a 16h22
AVEC Alu : 16h45 a 16h52
                             ==> data dans data/shared

** scan FPC table ==>  17h28 repositionnee au max de flux
           100 pC e- : Mesure diode calib
           17h32, 175 pC (max attenuateur laser) : Mesure diode calib

 