  Toutes les notes concernant les Commissionning de ThomX, Page 13 of 61  Not logged in ThomX    logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Status Type Category Important Subject Icon Text Attachments
  986   Fri Dec 20 08:37:20 2024 VC,NDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning Shift summary 20/12 demarrage machine 8h40

Matin: travail sur la synchro,
creation du mode "diags only"
 10x 
  Draft   Thu Dec 19 11:10:03 2024 IC, VK, VMUnder ProcessShift summaryRing Commissioning   11h05 Start ThomX

11h50 BPM02-Libera04 wiring has
been checked: 'OK' 
  
  984   Wed Dec 18 11:59:49 2024 Entered by Viktor Soskov from 134.158.195.153 on Wed Dec 18 11:59:34 2024FixedInfoLaser Laser-cathode Bonjour, le laser-cathode a ete realigne
(miroir M5, miroir dans la salle laser).
L'energie UV sur la cathode 55 µJ,
  
  983   Wed Dec 18 08:37:08 2024 VCUnder ProcessShift summaryLinac Commissionning summary shift Dec 18  demarrage chauffage 8h45

le modulateur refuse de passer
en mode standby
  
  982   Tue Dec 17 23:26:45 2024 Entered by Marie Jacquet from 134.158.205.16 on Tue Dec 17 23:26:26 2024FixedShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning shift 17/12 - scan vert FPC - 50 MeV 8h10 : mise en chauffe de la machine (modulateur,
laser, frigo et chiller)

9h30: faisceau dans anneau avec
 6x 
  981   Tue Dec 17 08:09:41 2024 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 17 décembre 2024 8h10 : mise en chauffe de la machine (modulateur,
laser, frigo et chiller)

9h30: faisceau dans anneau avec
  
  980   Fri Dec 13 08:22:36 2024 VM, IC, VKUnder ProcessShift summaryRing Commissioning   08h23 Start ThomX

09h40 HV is 'On'

10h24 RF Gun Phase 183 dg. Sect.
 Screenshot_from_2024-12-13_11-28-46.pngScreenshot_from_2024-12-13_14-44-28.pngScreenshot_from_2024-12-13_14-46-59.png 
  979   Thu Dec 12 07:54:45 2024 KD, RC, MJ, VM, IC, VKUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 12 décembre 2024 7h50: mise en chauffe en remote (chiller,
frigo, laser, modulateur)

Demarrage alignement sur l'axe
 7x 
  978   Wed Dec 11 08:12:54 2024 KD, VC, RC MJUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 11 décembre 2024 8h10 : mise en chauffe à distance
de la machine (chiller, frigo, laser, modulateur).

/!\ La mesure SF6 faites
 Screenshot_2024-12-11_11-51-40_min_synchrotron_deb_aller_m1_2mmY.pngScreenshot_2024-12-11_11-51-40_min_synchrotron_fin_aller_m1_2mmY.pngScreenshot_2024-12-11_11-51-40_max_synchrotron_deb_aller_m1_2mmY.pngScreenshot_2024-12-11_12-39-36_min_synchrotron_deb_retour_0mmY.png 
  977   Tue Dec 10 11:35:16 2024 VM,HG,SCUnder ProcessShift summaryLI | TL | LE | Ring | Linac Commissionning | Ring Commissioning 50 and 70 MeV Emittance, and transport  Intervention chiller (Maher) : maintenance
nécessaire à prévoir
(clé outil clignote)
 Q_vs_SolenoScan_at_16-52-02_Q1_Off.pngQ_vs_SolenoScan_at_16-39-39_recette_good_xrays.png 
  976   Fri Dec 6 11:11:31 2024 VC MJFixedShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Installation du PM dans la X-hucth Le PM est installe dans la X-hutch (PM
+ gene + ocsillo), on a  test que ca
fonctionne -
  
  975   Fri Dec 6 08:24:36 2024 VM, IC, VK, HG Under ProcessShift summaryRing Commissioning   08h25 Start ThomX

09h55 HV is 'ON'

10h18 RF Gun Phase is 159 dg. Sect.
 8x 
  974   Thu Dec 5 08:31:34 2024 VM Entered by Super Team from 134.158.195.141 on Thu Dec 5 08:31:12 2024Under ProcessShift summaryRing Commissioning   08h28 Start ThomX

08h40 Some magnets remain switched
off. Cycling was not performed
  
  973   Wed Dec 4 10:54:28 2024 VCFixedFixSY Frequence anneau et systeme de synchro Rappel:


la
  
  972   Tue Dec 3 09:14:50 2024 SC, HG, VMUnder ProcessLinacLI | TL Passage à 61.5MeV et 70 MeV 9h14 Mise en chauffe

Pas de camera laser qui s'ouvre
sur PlateformeIHM
 screenshot_steerers_linac_findejournée.pngBeam_transmission_Sole.png 
  971   Fri Nov 29 08:22:14 2024 VC, Carlos Buitrago, Sudhanshu Thakur, NDUnder ProcessShift summaryLinac Commissionning TP 29-11--2024 demarrage chauffage 8H20

test nouveau code synchro 50Hz
=> ne fonctionne pas
  
  Draft   Thu Nov 28 08:19:05 2024 VM, IC, VK Under ProcessInfoRing Commissioning   08h18 Start ThomX

10h00 HV is 'ON'

10h35 RF Gun phase is 174 dg. Section
  
  969   Wed Nov 27 08:04:44 2024 VCUnder ProcessShift summaryLinac Commissionning Shift summary 27/11 8h : mise en chauffe (laser, modulateur,
frigo, chiller, cyclage)

9H30 y'a eu une intervention
 QP1_scan.pngQP2_scan.pngQP3_scan.png 
  Draft   Tue Nov 26 07:53:39 2024 MJ RC KDUnder ProcessShift summaryLaser | Opt | Linac Commissionning | Ring Commissioning shift du 26 novembre 2024 8h : mise en chauffe en remote (laser,
modulateur, frigo, chiller, cyclage)

 2024-11-26_12_22_06_el_dg_sst_01-ccd_01_RAW_1.png 
  967   Fri Nov 22 11:18:28 2024 KD, RCUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 22 novembre 2024 9h30 : mise en chauffe

intervention casemate pour alignement
laser et nettoyage optique.
 TL_BPM4_locked.dat 