ID Date Author Status Type Category Important Subject Icon Text Attachments
  12   Tue Jun 8 14:36:48 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:36:35 2021Under ProcessProblemetc Tests RFs Interlock eau sur modulateur, arrêt
du modulateur.

Remise en route
 mise_en_chauffe 
  11   Tue Jun 8 12:39:23 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 12:39:09 2021Under ProcessShift summaryetc summary du matin Bonjour,

la synchro est effective

le modulateur est pret
  
  10   Tue Jun 8 11:49:13 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 11:48:58 2021Under ProcessFixproblemes attenuateur section tests butée moteur On monte progressivement le moteur de l'atténuateur
de la section pour trouver la butée
supérieure  li/hfi/att.01-mot.01
  
  9   Tue Jun 8 10:58:29 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 10:58:16 2021Under ProcessInfoetc Signaux RFs Mise en place des signaux Rfs sur l'oscilloscope
de la salle CC, Travail sur le timing en
cours.
  
  8   Tue Jun 8 10:40:54 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 10:40:40 2021FixedInfoetc Fermeture sous-sols et toit casemate Les sous-sols et le toit sont maintenant
fermés
  
  7   Tue Jun 8 09:31:28 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 09:31:12 2021Under ProcessInfoetc Tests RFs Aujourd'hui, démarrage des tests
RFs.

Vérification du bon fonctionnement
  
  Draft   Thu Apr 8 21:14:09 2021 Entered by talour from 134.158.205.2 on Thu Apr 8 21:11:41 2021FixedShift summaryPrise de donnees       
  5   Tue Dec 1 09:57:09 2020 Entered by Moutardier from 134.158.76.123 on Tue Dec 1 09:56:35 2020 Inforesumes Verrification pour le démarrage a blanc Verification de l'état de la
Synchro : OK, tout les signaux sont en trigger
externe.
  
  4   Tue May 28 15:07:37 2019 Entered by Aurélien Martens from 134.158.88.183 on Tue May 28 15:07:25 2019FixedInfoTango Photocathode laser DS back operational icon7.gif Following:

1) a crash on 4th of April
and a violent reboot of the ELLiOOs
  
  3   Tue Oct 18 15:12:24 2016 Entered by Hugues Monard from 134.158.89.218 on Tue Oct 18 15:12:09 2016Under ProcessShift summaryresumes   test  2014-05-15_Conditionnement_circulateur_RF_et_canon_PHIN.pptx 
  2   Tue Oct 18 14:25:34 2016 Entered by Hugues Monard from 134.158.89.218 on Tue Oct 18 14:25:09 2016Not FixedShift summaryPrise de donnees test de log jeudi 18 octobre

il faudrait mettre un place un
canevas type pour un point de fonctionnement
 Timing_Osc-1a4.jpg 