  Status of commissioning, report also here plots are reports., Page 9 of 24  Not logged in ELOG logo
    Reply   Optimizing lock parameters for stable X-ray production, posted by Ronic Chiche at ThomX igloo about lasers and optics | software 
this morning, I did some walking procedure and CEP alignment to get ~80kW in the FPC with 33% amplifier ratio.

we have to check if this power drop comes from:

- a laser amplifier power drop
    Reply   Optimizing lock parameters for stable X-ray production, posted by Ronic Chiche at ThomX igloo about lasers and optics | software 
the RF frequency is now 500.1003MHz which is equivalent (if divided by 15) to 33.34002MHz.

the frequency has to be changed by ~2kHz @33MHz <=> ~550µm /2 for one motor.

I changed the laser and the FP cavities frequency.
Entry   Christmas shutdown, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
this morning, I shut off all the equipements (especially the computer) except the ones powered by the UPS : laser controller, laser peltier controller,
laser motors controller.
and I disconnected the cables from the power plugs of the wall (to prevent any possible overvoltage).
    Reply   Christmas shutdown, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
this afternoon, I checked visually what happens when the AC power of the UPS is broken down => the laser controller has still its "emission"
button ON... no AC interruption.
so, I guess the UPS switched properly the output AC line from the input AC line to the internal batteries.
Entry   Restarting equipements after Christmas shutdown, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
this morning, I plugged back the 4 power cables which supply all the equipments.

all the equipments have restarted without problem, but the shutter of the laser amplifier needs a ThomX safety system grant to let the beam propagate
to the cavity...
    Reply   Restarting equipements after Christmas shutdown, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
the laser coupled into the amplifier is still measured at ~3mW at the input, on the Alphanov software, once the Amp stage are started at 0% of power
ratio.

this afternoon, Kevin restarted the 3rd safety system of ThomX to grant the opening of the beam shutter => now the shutter can be opened.
    Reply   Restarting equipements after Christmas shutdown, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
this morning, I set the Ring frequency at 500.25MHz and after switching ON the power supply of the amplifiers for the RF signal coming from the laser,
I saw the beating frequency  (between ring RF and laser harmonic frerquencies at 500.25MHz) that I canceled, playing with the Smaract motor.

Now, I need to adjust the FP-cavity length to follow the laser cavity length but the IcePap DS (controlling the FP-cavity motor) freezes too
    Reply   Restarting equipements after Christmas shutdown, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
on last friday (12/01/2024), the IcePap DS issue was solved and I was able to control the FP-cavity motors properly.
I was able to quickly lock either the laser on the FP-cavity and the FP-cavity on the RF reference as before.

then, we can close these posts on restarting the equipments after the Christmas shutdown
Entry   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software Capture.JPGCapture2.JPG
temperature in the casemate ~ 19.5°C stable

this morning, I measured the power directly at the output of the fiber coupler (through the output fiber), after the strecher : ~5mW
then, I connected the EOM used for the PDH technic : ~2.5mW
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software Capture.JPG
I refilled the chiller and the stabilized temperature is @ 25°C

we started the 3rd stage of the Alphanov amplifier at 30% => PD_OUT is fluctuating around 1-1.4W => it's not related to the real output
power !
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software Sans_titre.png
we had to move the laser cavity motor to find the resonances and change a lot the CEP.

the CEP motor is at -524.1µm

we got ~75kW in the FP cavity without alignment but with CEP optimization.
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software Capture.JPG
after doing some alignment (walking procedure on the Y axis), and CEP optimization, I got 83kW for 33% on the laser amplifier with a coupling of ~60%

=> we have to check the input power after the amplifier.

I adjusted the FP and laser cavity motors to have a small 33MHz detuning with the RF reference (~10 Hz of beating @ 33MHz)
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
this morning with Daniele, we are measuring the amplifier power just before the FP-cavity.
Casemate temperature @19.5°C

@0% : 205mW
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
After the summer power shutdown, I restarted all the equipements and got quickly ~80kW for 33% amplifier ratio with CEP optimization and without Alignment
optimization.

CEP motor position : -506µm
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
amplifier power measurement before the compressor CVBG.
we used a mirror in between the amplifier output and the compressor + a 2-mirror periscope to match the powermeter height.

amp ratio (%)          power (W)
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
after redoing the alignment of the CVBG, we got back the initial power in the FPC (87kW)

now, I checked the RF locking signals on the 2nd oscilloscope.
I get a strange ratio between the 33MHz beating and the 500MHz beating signals.
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
now, the Ring RF frequency is set to 500.067MHz.

so the CFP/laser frequency should be 500.067MHz/15 = 33.3378MHz.

the frequency was set to 33.378MHz !!! => it explains the frequency shift only on the 33MHz beating => I corrected the frequency on the
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 20240906_161926.jpg
I changed a little bit the locking parameters (see picture) for the RF/FPC loop and it locked rapidely.

I asked Vincent to connect on the same scope the synchro signals to check if the FPC lock was OK => he connected 33MHz signals coming from
the laser and from the 33MHz RF generator.
    Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
this morning, with Vincent :

- we added the 10Hz trigger to the CH2 on the remote scope (192.168.229.21) to check the synchronization at the right timing.
CH1 : 33MHz RING
Entry   33MHz phase adjustment, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
the 33MHz beating signal (phase) is used to start and stop automatically the lock on the 500MHz beating signal.

this 33MHz beating phase has a fixed range (typically +/-0.5V), so it is important to center this beating phase in the middle of its own range
when the 500MHz signal is locked