Status of commissioning, report also here plots are reports., Page 23 of 23
Not logged in
Find
|
Login
|
Help
New entries since:
Thu Jan 1 01:00:00 1970
Full
| Summary |
Threaded
452 Entries
Goto page
Previous
1
,
2
,
3
...
21
,
22
, 23
All
ID
Date
Author
Status
Type
Category
Location
Title
Text
12
Wed Jan 16 14:54:14 2019
Loïc Amoudry
Fixed
report
lasers and optics | utilities
Optical room
Cleaning outside IP cavity
From 7th january to 11th january.
11
Fri Dec 21 13:55:09 2018
Loïc Amoudry
Fixed
info
vacuum
Optical room
End of vacuum test and cavity ready for cleaning
Vacuum tests finished on 19 december
2018.
Spent last two days to discuss
10
Mon Nov 26 15:18:49 2018
Ronic Chiche
Fixed
info
vacuum
Optical room
Etuvage cavité THOMX
Mail de Bruno Mercier
du 19/11/2018 :
Une première cavité
9
Mon Oct 22 11:29:41 2018
Ronic Chiche
Fixed
info
mechanics
Optical room
Remontage des vérins
Mail de Yann du 8/10/2018 :
Bonjour,
Tous les vérins sont maintenant
8
Mon Oct 22 11:27:35 2018
Ronic Chiche
Fixed
info
mechanics
Optical room
Remontage mécanique
Mail de Yann du 12/10/2018 :
Je vous fais le bilan des actions
effectuées :
7
Mon Oct 22 11:03:22 2018
Ronic Chiche
Fixed
info
vacuum
Optical room
Détection de fuite
Mail de Bruno Mercier du 18/10/2018 :
Un petit CR
de la journée:
6
Fri Oct 5 10:17:30 2018
Ronic Chiche
Fixed
report
mechanics | cabling
Optical room
test des vérins ISP 20mm et 6mm
5
Wed Oct 3 11:28:46 2018
Ronic Chiche
Fixed
report
mechanics | cabling
Optical room
test des vérins ISP 20mm et 6mm
Après avoir utilisé la chaine
: driver ISP - cable ISP DB9 - Feedthrough
enceinte DB9-DB9 - cable perlé DB9-SUB-C
4
Tue Oct 2 18:00:36 2018
Ronic Chiche
Fixed
issue
mechanics | cabling | software
Optical room
test des vérins ISP
3
Tue Oct 2 16:23:54 2018
Ronic Chiche
Fixed
issue
mechanics | cabling | software
Optical room
test des vérins ISP
* les vérins de 20mm (axe Z) ont
été testés sur table
grace à une rallonge SUB-C - DB9,
2
Thu Sep 27 15:43:48 2018
Ronic Chiche
Fixed
info
lasers and optics
Optical room
Onefive Origami 33MHz specs - Polarisation
one rotate a lambda/2 before a PBS and
meausure the refected power:
Pmax=35.6 mW
1
Tue Sep 25 19:17:43 2018
Loïc Amoudry
Fixed
info
lasers and optics
Optical room
Onefive Origami 33MHz specs
Power during ~20h, power after turn on,
spectrum image and excel datas, polarisation
and pulse length.