338
|
Thu Apr 25 09:09:49 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | ThomX igloo | FP-cavity lock survey during the Linac section changing operation | |
this morning, the chiller was in error and I had to restart it.
the air temperature is around 21°C.
the water cooling has been repaired but the initial Temp Amp 1 is at 28°C.
I got 86kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
but the amplifier stopped after an error after 30 minutes => the Temp Amp1 reached 30°C => it's not normal.
the chiller was again in error. I tried to restart it but I got an ERROR14 : Thermostat error, the flow rate is zero !!!
the tubes for the inner circuit going to the amplifier are a little hot by touching them with my hand.
the tubes for the outer circuit going to the ThomX water circuit is hot for the "blue" tube et cold for the "yellow" tube.
it means there is no flow in the outer circuit.
Jean-Noel just told me it's normal because he stopped the ThomX water pump because of a too high temperature => Dalkia should fix the problem today.
OC/OP/OCH.01-MOT06 roughly at position -792 600 steps.
CEP motor = -211µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, the computer was restarted and I had to launch all the applications.
no problem except the powermeter for which I had to do a power switch OFF and ON remotely.
the chiller was in error and I had to restart it also.
the air temperature seems to be not properly controlled (see the picture)
one can see a constant temperature drop from Tuesday 9 April 10:30am.
it seems the water cooling is also not working properly as I saw the laser amplifier temperature (Temp Amp 1) increased constantly during the run from 24°C to 30°C (in 30 mintues).
=> it's not normal, it should be regulated at 25°C !
I got 89kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
OC/OP/OCH.01-MOT06 roughly at position -782 000 steps.
CEP motor = -425µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, I had to restart the chiller. Temp Amp 1 is at 27.5°C after having started the amplifier at 33% ratio.
I removed the 100kohms resistor on the Transmission channel, on the scope (now, it is 1Mohms), to get more sensitivity.
the air temperature is around 21°C and is stable during the last days.
I don't see any power coming from the amplifier despite it is at 33%... I think the MPS prevent us to work and the amplifier shutter is blocking the beam.
I will send an email to Sophie to check that point.
EDIT : Kevin showed me how to acknowledge the error on the MPS
=> go to "Detail" and then acknowledge the "vacuum error".
I saw the FP-cavity resonances but I didn't have time to optimize them as the water temperature is still too high and the chiller is not working good enough.
=> the amplifier did a safety stop.
one needs to wait this issue is fixed.
OC/OP/OCH.01-MOT06 at position -790 000 steps.
CEP motor = -300µm but far from the optimum CEP position.
| Ronic Chiche wrote: |
|
from now on, the transmission factor for calculating the FP intra cavity power is 1/1.75ppm ~ 570 000 (changed in the Powermeter software)
this morning the temperature of the water cooling circuit is still very high said Sophie, and the laser amplifier temperature "Temp Amp1" is at 29°C instead of ~23-25°C
then, when I start the laser amplifier, it stops rapidly with a warning error.
I will check the chiller status as the Dalkia should fix the water temperature problem at some time (Sophie + Alice working on this point)
the air temperature in the bunker is back at 19.5°C from last Friday afternoon and is stable at less than 0.5°C.
after restarting the chiller, the "Temp Amp1" is now at 25°C before starting the power in the amplifier, it rises at 28.5°C after some minutes
I found the resonances with the motor OC/OP/OCH.01-MOT06 at position -783 460 steps.
and I had to tune the CEP to get the maximum resonances at -198µm.
with the new transmission factor, I got almost 90kW for 33% laser amplifier ratio after a simple alignment procedure.
the motor OC/OP/OCH.01-MOT03 is sill in error.
| Ronic Chiche wrote: |
|
This morning, I locked again the FP-cavity at more than 50kW with 33% of laser amplifier ratio.
the temperature is measured today at 20.5°C despite the fact the air conditionning is still OFF.
the temperature, rising from 18°C, started monday at 11AM roughly.
maybe, the difference comes from the external doors of the Igloo which have been closed recently ? to be confirmed.
as the temperature is measured inside the airflow housing, all the powered equipements are disspating some heat, rising the inside temperature compared to the bunker temperature.
EDIT : Sophie Chance told me the water temperature cooling of ThomX was defective... the water temperature went to 29°C ! it is being fixed by Dalkia.
careful, we don't have a temperature measurement of the water going to the chiller...
to find resonances, I moved the OC/OP/OCH.01-MOT06 motor from position -770 000 steps to position -788 600 steps which corresponds to ~100µm !
it can be explained by the temperature change and also because during the lock last week, I let the MOT06 motor in position after the cavity was at 50kW.
I had also to change the CEP motor position from -170µm to -420µm and to do some alignment (with walking procedure).
accessing the motor OC/OP/OCH.01-MOT03 from the ATK panel, produces an error : "connection to device failed"... to be solved by Kevin ?
| Ronic Chiche wrote: |
|
This morning with Daniele, we operated the FP-cavity to be sure there is no issue due to the Linac section changing operation :
- opening/closing the valves due to air pressure break down
- opening/closing the bunker roof
- large temperature change
- etc...
the temperature in the bunker dropped to 18°C instead of 21.5°C, so we had to do some FP-cavity alignment.
but after obtaining resonances and changing the CEP, we got more than 50kW for 33% of amplifier ratio => OK !
|
|
|
|
|
|
|
339
|
Tue May 14 09:20:27 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | ThomX igloo | FP-cavity lock survey during the Linac section changing operation | Yesterday, the ThomX water circuit should have been repared,
and yesterday aftenoon, Daniele restarted the chiller and I checked it this morning without any error.
BUT the pump of the ThomX water circuit is again in default...
Dalkia has been called to fix the problem.
despite this point, I restarted the laser amplifier this morning.
everything seems as usual and I can see some small resonance at the output of the Fabry-Perot cavity
BUT the reflection photodiode level doen't change when the amplifier is ON.
I need to check if the photodiode switch is set ON or if it is misaligned or dead.... to be checked.
in between, I prefer to stop the laser amplifier.
edit : the photodiode problem was coming from the PhD power supply which was OFF.
I just turned it ON.
| Ronic Chiche wrote: |
|
this morning, the chiller was in error and I had to restart it.
the air temperature is around 21°C.
the water cooling has been repaired but the initial Temp Amp 1 is at 28°C.
I got 86kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
but the amplifier stopped after an error after 30 minutes => the Temp Amp1 reached 30°C => it's not normal.
the chiller was again in error. I tried to restart it but I got an ERROR14 : Thermostat error, the flow rate is zero !!!
the tubes for the inner circuit going to the amplifier are a little hot by touching them with my hand.
the tubes for the outer circuit going to the ThomX water circuit is hot for the "blue" tube et cold for the "yellow" tube.
it means there is no flow in the outer circuit.
Jean-Noel just told me it's normal because he stopped the ThomX water pump because of a too high temperature => Dalkia should fix the problem today.
OC/OP/OCH.01-MOT06 roughly at position -792 600 steps.
CEP motor = -211µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, the computer was restarted and I had to launch all the applications.
no problem except the powermeter for which I had to do a power switch OFF and ON remotely.
the chiller was in error and I had to restart it also.
the air temperature seems to be not properly controlled (see the picture)
one can see a constant temperature drop from Tuesday 9 April 10:30am.
it seems the water cooling is also not working properly as I saw the laser amplifier temperature (Temp Amp 1) increased constantly during the run from 24°C to 30°C (in 30 mintues).
=> it's not normal, it should be regulated at 25°C !
I got 89kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
OC/OP/OCH.01-MOT06 roughly at position -782 000 steps.
CEP motor = -425µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, I had to restart the chiller. Temp Amp 1 is at 27.5°C after having started the amplifier at 33% ratio.
I removed the 100kohms resistor on the Transmission channel, on the scope (now, it is 1Mohms), to get more sensitivity.
the air temperature is around 21°C and is stable during the last days.
I don't see any power coming from the amplifier despite it is at 33%... I think the MPS prevent us to work and the amplifier shutter is blocking the beam.
I will send an email to Sophie to check that point.
EDIT : Kevin showed me how to acknowledge the error on the MPS
=> go to "Detail" and then acknowledge the "vacuum error".
I saw the FP-cavity resonances but I didn't have time to optimize them as the water temperature is still too high and the chiller is not working good enough.
=> the amplifier did a safety stop.
one needs to wait this issue is fixed.
OC/OP/OCH.01-MOT06 at position -790 000 steps.
CEP motor = -300µm but far from the optimum CEP position.
| Ronic Chiche wrote: |
|
from now on, the transmission factor for calculating the FP intra cavity power is 1/1.75ppm ~ 570 000 (changed in the Powermeter software)
this morning the temperature of the water cooling circuit is still very high said Sophie, and the laser amplifier temperature "Temp Amp1" is at 29°C instead of ~23-25°C
then, when I start the laser amplifier, it stops rapidly with a warning error.
I will check the chiller status as the Dalkia should fix the water temperature problem at some time (Sophie + Alice working on this point)
the air temperature in the bunker is back at 19.5°C from last Friday afternoon and is stable at less than 0.5°C.
after restarting the chiller, the "Temp Amp1" is now at 25°C before starting the power in the amplifier, it rises at 28.5°C after some minutes
I found the resonances with the motor OC/OP/OCH.01-MOT06 at position -783 460 steps.
and I had to tune the CEP to get the maximum resonances at -198µm.
with the new transmission factor, I got almost 90kW for 33% laser amplifier ratio after a simple alignment procedure.
the motor OC/OP/OCH.01-MOT03 is sill in error.
| Ronic Chiche wrote: |
|
This morning, I locked again the FP-cavity at more than 50kW with 33% of laser amplifier ratio.
the temperature is measured today at 20.5°C despite the fact the air conditionning is still OFF.
the temperature, rising from 18°C, started monday at 11AM roughly.
maybe, the difference comes from the external doors of the Igloo which have been closed recently ? to be confirmed.
as the temperature is measured inside the airflow housing, all the powered equipements are disspating some heat, rising the inside temperature compared to the bunker temperature.
EDIT : Sophie Chance told me the water temperature cooling of ThomX was defective... the water temperature went to 29°C ! it is being fixed by Dalkia.
careful, we don't have a temperature measurement of the water going to the chiller...
to find resonances, I moved the OC/OP/OCH.01-MOT06 motor from position -770 000 steps to position -788 600 steps which corresponds to ~100µm !
it can be explained by the temperature change and also because during the lock last week, I let the MOT06 motor in position after the cavity was at 50kW.
I had also to change the CEP motor position from -170µm to -420µm and to do some alignment (with walking procedure).
accessing the motor OC/OP/OCH.01-MOT03 from the ATK panel, produces an error : "connection to device failed"... to be solved by Kevin ?
| Ronic Chiche wrote: |
|
This morning with Daniele, we operated the FP-cavity to be sure there is no issue due to the Linac section changing operation :
- opening/closing the valves due to air pressure break down
- opening/closing the bunker roof
- large temperature change
- etc...
the temperature in the bunker dropped to 18°C instead of 21.5°C, so we had to do some FP-cavity alignment.
but after obtaining resonances and changing the CEP, we got more than 50kW for 33% of amplifier ratio => OK !
|
|
|
|
|
|
|
|
340
|
Tue May 14 10:37:41 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | ThomX igloo | FP-cavity lock survey during the Linac section changing operation | the air temperature is between 21°C and 22°C.
I tried to lock the cavity but it was very instable with only short time locks.
I had to increase the parameters of the PID:
P = 0.07
I = 0.0007
D = 0.706
after that, the lock was stable but we can see something in transmission (dark blue curve) which seems to be a degeneracy.
maybe because of the water cooling temperature, after stopping the laser amplifier, I was not able to restart it.
I always got an error (an alarm was triggered by bad sequence) when I want to switch ON the preamplifier at 0%.
the Temp Amp 1 is about 25-26°C... it is stange.
to be tested after the water cooling is repaired.
| Ronic Chiche wrote: |
|
Yesterday, the ThomX water circuit should have been repared,
and yesterday aftenoon, Daniele restarted the chiller and I checked it this morning without any error.
BUT the pump of the ThomX water circuit is again in default...
Dalkia has been called to fix the problem.
despite this point, I restarted the laser amplifier this morning.
everything seems as usual and I can see some small resonance at the output of the Fabry-Perot cavity
BUT the reflection photodiode level doen't change when the amplifier is ON.
I need to check if the photodiode switch is set ON or if it is misaligned or dead.... to be checked.
in between, I prefer to stop the laser amplifier.
edit : the photodiode problem was coming from the PhD power supply which was OFF.
I just turned it ON.
| Ronic Chiche wrote: |
|
this morning, the chiller was in error and I had to restart it.
the air temperature is around 21°C.
the water cooling has been repaired but the initial Temp Amp 1 is at 28°C.
I got 86kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
but the amplifier stopped after an error after 30 minutes => the Temp Amp1 reached 30°C => it's not normal.
the chiller was again in error. I tried to restart it but I got an ERROR14 : Thermostat error, the flow rate is zero !!!
the tubes for the inner circuit going to the amplifier are a little hot by touching them with my hand.
the tubes for the outer circuit going to the ThomX water circuit is hot for the "blue" tube et cold for the "yellow" tube.
it means there is no flow in the outer circuit.
Jean-Noel just told me it's normal because he stopped the ThomX water pump because of a too high temperature => Dalkia should fix the problem today.
OC/OP/OCH.01-MOT06 roughly at position -792 600 steps.
CEP motor = -211µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, the computer was restarted and I had to launch all the applications.
no problem except the powermeter for which I had to do a power switch OFF and ON remotely.
the chiller was in error and I had to restart it also.
the air temperature seems to be not properly controlled (see the picture)
one can see a constant temperature drop from Tuesday 9 April 10:30am.
it seems the water cooling is also not working properly as I saw the laser amplifier temperature (Temp Amp 1) increased constantly during the run from 24°C to 30°C (in 30 mintues).
=> it's not normal, it should be regulated at 25°C !
I got 89kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
OC/OP/OCH.01-MOT06 roughly at position -782 000 steps.
CEP motor = -425µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, I had to restart the chiller. Temp Amp 1 is at 27.5°C after having started the amplifier at 33% ratio.
I removed the 100kohms resistor on the Transmission channel, on the scope (now, it is 1Mohms), to get more sensitivity.
the air temperature is around 21°C and is stable during the last days.
I don't see any power coming from the amplifier despite it is at 33%... I think the MPS prevent us to work and the amplifier shutter is blocking the beam.
I will send an email to Sophie to check that point.
EDIT : Kevin showed me how to acknowledge the error on the MPS
=> go to "Detail" and then acknowledge the "vacuum error".
I saw the FP-cavity resonances but I didn't have time to optimize them as the water temperature is still too high and the chiller is not working good enough.
=> the amplifier did a safety stop.
one needs to wait this issue is fixed.
OC/OP/OCH.01-MOT06 at position -790 000 steps.
CEP motor = -300µm but far from the optimum CEP position.
| Ronic Chiche wrote: |
|
from now on, the transmission factor for calculating the FP intra cavity power is 1/1.75ppm ~ 570 000 (changed in the Powermeter software)
this morning the temperature of the water cooling circuit is still very high said Sophie, and the laser amplifier temperature "Temp Amp1" is at 29°C instead of ~23-25°C
then, when I start the laser amplifier, it stops rapidly with a warning error.
I will check the chiller status as the Dalkia should fix the water temperature problem at some time (Sophie + Alice working on this point)
the air temperature in the bunker is back at 19.5°C from last Friday afternoon and is stable at less than 0.5°C.
after restarting the chiller, the "Temp Amp1" is now at 25°C before starting the power in the amplifier, it rises at 28.5°C after some minutes
I found the resonances with the motor OC/OP/OCH.01-MOT06 at position -783 460 steps.
and I had to tune the CEP to get the maximum resonances at -198µm.
with the new transmission factor, I got almost 90kW for 33% laser amplifier ratio after a simple alignment procedure.
the motor OC/OP/OCH.01-MOT03 is sill in error.
| Ronic Chiche wrote: |
|
This morning, I locked again the FP-cavity at more than 50kW with 33% of laser amplifier ratio.
the temperature is measured today at 20.5°C despite the fact the air conditionning is still OFF.
the temperature, rising from 18°C, started monday at 11AM roughly.
maybe, the difference comes from the external doors of the Igloo which have been closed recently ? to be confirmed.
as the temperature is measured inside the airflow housing, all the powered equipements are disspating some heat, rising the inside temperature compared to the bunker temperature.
EDIT : Sophie Chance told me the water temperature cooling of ThomX was defective... the water temperature went to 29°C ! it is being fixed by Dalkia.
careful, we don't have a temperature measurement of the water going to the chiller...
to find resonances, I moved the OC/OP/OCH.01-MOT06 motor from position -770 000 steps to position -788 600 steps which corresponds to ~100µm !
it can be explained by the temperature change and also because during the lock last week, I let the MOT06 motor in position after the cavity was at 50kW.
I had also to change the CEP motor position from -170µm to -420µm and to do some alignment (with walking procedure).
accessing the motor OC/OP/OCH.01-MOT03 from the ATK panel, produces an error : "connection to device failed"... to be solved by Kevin ?
| Ronic Chiche wrote: |
|
This morning with Daniele, we operated the FP-cavity to be sure there is no issue due to the Linac section changing operation :
- opening/closing the valves due to air pressure break down
- opening/closing the bunker roof
- large temperature change
- etc...
the temperature in the bunker dropped to 18°C instead of 21.5°C, so we had to do some FP-cavity alignment.
but after obtaining resonances and changing the CEP, we got more than 50kW for 33% of amplifier ratio => OK !
|
|
|
|
|
|
|
|
| Attachment 1: Capture.JPG
|  |
|
341
|
Tue May 28 15:05:46 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | ThomX igloo | FP-cavity lock survey during the Linac section changing operation | today, I tried to restart the amplifier at 0% (without 3rd stage) but it didn't start... still the same error message.
but the PD_IN power and the PD_PULSE frequency seems correct.... I will try to power the amplifier OFF and ON later to see if one can reset this error.
edit : finally, a the end of the day, I switched OFF and ON several times the amplifier but I always get the same error message "bad sequence error".
I tried to use the Alphanov software to see if we can get more information about the error :
the watchdog LED is RED => I have to check if it is normal or not before starting the amplifier
and the PD_CRI LED is RED => normal because the preamp stage is not started (and it does not want to start...)
PD_IN is at 3.1mV but a previous post says that the amplifier worked with 2.7mV.
we can try to increase to 3.2-3.3 mW and see if it works....
edit : it seems we already had this kind of error before.
Guillaume suggested to check the average power of the seeder at the output of the fiber, the repetition rate and the stability of the signal.
previous post (https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/179) have shown an input power (PD_IN) around 5.7mW (see the attached image) !
this power was maybe obtained without any EOM which divide the power by ~2.
=> we can try to remove it temporarilly to check if the amplifier is able to restart in this condition... to be done
| Ronic Chiche wrote: |
|
the air temperature is between 21°C and 22°C.
I tried to lock the cavity but it was very instable with only short time locks.
I had to increase the parameters of the PID:
P = 0.07
I = 0.0007
D = 0.706
after that, the lock was stable but we can see something in transmission (dark blue curve) which seems to be a degeneracy.
maybe because of the water cooling temperature, after stopping the laser amplifier, I was not able to restart it.
I always got an error (an alarm was triggered by bad sequence) when I want to switch ON the preamplifier at 0%.
the Temp Amp 1 is about 25-26°C... it is stange.
to be tested after the water cooling is repaired.
| Ronic Chiche wrote: |
|
Yesterday, the ThomX water circuit should have been repared,
and yesterday aftenoon, Daniele restarted the chiller and I checked it this morning without any error.
BUT the pump of the ThomX water circuit is again in default...
Dalkia has been called to fix the problem.
despite this point, I restarted the laser amplifier this morning.
everything seems as usual and I can see some small resonance at the output of the Fabry-Perot cavity
BUT the reflection photodiode level doen't change when the amplifier is ON.
I need to check if the photodiode switch is set ON or if it is misaligned or dead.... to be checked.
in between, I prefer to stop the laser amplifier.
edit : the photodiode problem was coming from the PhD power supply which was OFF.
I just turned it ON.
| Ronic Chiche wrote: |
|
this morning, the chiller was in error and I had to restart it.
the air temperature is around 21°C.
the water cooling has been repaired but the initial Temp Amp 1 is at 28°C.
I got 86kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
but the amplifier stopped after an error after 30 minutes => the Temp Amp1 reached 30°C => it's not normal.
the chiller was again in error. I tried to restart it but I got an ERROR14 : Thermostat error, the flow rate is zero !!!
the tubes for the inner circuit going to the amplifier are a little hot by touching them with my hand.
the tubes for the outer circuit going to the ThomX water circuit is hot for the "blue" tube et cold for the "yellow" tube.
it means there is no flow in the outer circuit.
Jean-Noel just told me it's normal because he stopped the ThomX water pump because of a too high temperature => Dalkia should fix the problem today.
OC/OP/OCH.01-MOT06 roughly at position -792 600 steps.
CEP motor = -211µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, the computer was restarted and I had to launch all the applications.
no problem except the powermeter for which I had to do a power switch OFF and ON remotely.
the chiller was in error and I had to restart it also.
the air temperature seems to be not properly controlled (see the picture)
one can see a constant temperature drop from Tuesday 9 April 10:30am.
it seems the water cooling is also not working properly as I saw the laser amplifier temperature (Temp Amp 1) increased constantly during the run from 24°C to 30°C (in 30 mintues).
=> it's not normal, it should be regulated at 25°C !
I got 89kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
OC/OP/OCH.01-MOT06 roughly at position -782 000 steps.
CEP motor = -425µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, I had to restart the chiller. Temp Amp 1 is at 27.5°C after having started the amplifier at 33% ratio.
I removed the 100kohms resistor on the Transmission channel, on the scope (now, it is 1Mohms), to get more sensitivity.
the air temperature is around 21°C and is stable during the last days.
I don't see any power coming from the amplifier despite it is at 33%... I think the MPS prevent us to work and the amplifier shutter is blocking the beam.
I will send an email to Sophie to check that point.
EDIT : Kevin showed me how to acknowledge the error on the MPS
=> go to "Detail" and then acknowledge the "vacuum error".
I saw the FP-cavity resonances but I didn't have time to optimize them as the water temperature is still too high and the chiller is not working good enough.
=> the amplifier did a safety stop.
one needs to wait this issue is fixed.
OC/OP/OCH.01-MOT06 at position -790 000 steps.
CEP motor = -300µm but far from the optimum CEP position.
| Ronic Chiche wrote: |
|
from now on, the transmission factor for calculating the FP intra cavity power is 1/1.75ppm ~ 570 000 (changed in the Powermeter software)
this morning the temperature of the water cooling circuit is still very high said Sophie, and the laser amplifier temperature "Temp Amp1" is at 29°C instead of ~23-25°C
then, when I start the laser amplifier, it stops rapidly with a warning error.
I will check the chiller status as the Dalkia should fix the water temperature problem at some time (Sophie + Alice working on this point)
the air temperature in the bunker is back at 19.5°C from last Friday afternoon and is stable at less than 0.5°C.
after restarting the chiller, the "Temp Amp1" is now at 25°C before starting the power in the amplifier, it rises at 28.5°C after some minutes
I found the resonances with the motor OC/OP/OCH.01-MOT06 at position -783 460 steps.
and I had to tune the CEP to get the maximum resonances at -198µm.
with the new transmission factor, I got almost 90kW for 33% laser amplifier ratio after a simple alignment procedure.
the motor OC/OP/OCH.01-MOT03 is sill in error.
| Ronic Chiche wrote: |
|
This morning, I locked again the FP-cavity at more than 50kW with 33% of laser amplifier ratio.
the temperature is measured today at 20.5°C despite the fact the air conditionning is still OFF.
the temperature, rising from 18°C, started monday at 11AM roughly.
maybe, the difference comes from the external doors of the Igloo which have been closed recently ? to be confirmed.
as the temperature is measured inside the airflow housing, all the powered equipements are disspating some heat, rising the inside temperature compared to the bunker temperature.
EDIT : Sophie Chance told me the water temperature cooling of ThomX was defective... the water temperature went to 29°C ! it is being fixed by Dalkia.
careful, we don't have a temperature measurement of the water going to the chiller...
to find resonances, I moved the OC/OP/OCH.01-MOT06 motor from position -770 000 steps to position -788 600 steps which corresponds to ~100µm !
it can be explained by the temperature change and also because during the lock last week, I let the MOT06 motor in position after the cavity was at 50kW.
I had also to change the CEP motor position from -170µm to -420µm and to do some alignment (with walking procedure).
accessing the motor OC/OP/OCH.01-MOT03 from the ATK panel, produces an error : "connection to device failed"... to be solved by Kevin ?
| Ronic Chiche wrote: |
|
This morning with Daniele, we operated the FP-cavity to be sure there is no issue due to the Linac section changing operation :
- opening/closing the valves due to air pressure break down
- opening/closing the bunker roof
- large temperature change
- etc...
the temperature in the bunker dropped to 18°C instead of 21.5°C, so we had to do some FP-cavity alignment.
but after obtaining resonances and changing the CEP, we got more than 50kW for 33% of amplifier ratio => OK !
|
|
|
|
|
|
|
|
|
|
342
|
Fri May 31 18:12:59 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | ThomX igloo | FP-cavity lock survey during the Linac section changing operation | today with Daniele, we disconnected the EOM to increase the injected power of the amplifier, we were at 4.8mW but we still have the "bad sequence" error => email to Guillaume
we tried also several time again, to stop and restart the amplifier, but it didn't help.
I connected back the EOM and the power dropped to 2.7mW instead of 3.1mW => fiber injection alignement to be done
| Ronic Chiche wrote: |
|
today, I tried to restart the amplifier at 0% (without 3rd stage) but it didn't start... still the same error message.
but the PD_IN power and the PD_PULSE frequency seems correct.... I will try to power the amplifier OFF and ON later to see if one can reset this error.
edit : finally, a the end of the day, I switched OFF and ON several times the amplifier but I always get the same error message "bad sequence error".
I tried to use the Alphanov software to see if we can get more information about the error :
the watchdog LED is RED => I have to check if it is normal or not before starting the amplifier
and the PD_CRI LED is RED => normal because the preamp stage is not started (and it does not want to start...)
PD_IN is at 3.1mV but a previous post says that the amplifier worked with 2.7mV.
we can try to increase to 3.2-3.3 mW and see if it works....
edit : it seems we already had this kind of error before.
Guillaume suggested to check the average power of the seeder at the output of the fiber, the repetition rate and the stability of the signal.
previous post (https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/179) have shown an input power (PD_IN) around 5.7mW (see the attached image) !
this power was maybe obtained without any EOM which divide the power by ~2.
=> we can try to remove it temporarilly to check if the amplifier is able to restart in this condition... to be done
| Ronic Chiche wrote: |
|
the air temperature is between 21°C and 22°C.
I tried to lock the cavity but it was very instable with only short time locks.
I had to increase the parameters of the PID:
P = 0.07
I = 0.0007
D = 0.706
after that, the lock was stable but we can see something in transmission (dark blue curve) which seems to be a degeneracy.
maybe because of the water cooling temperature, after stopping the laser amplifier, I was not able to restart it.
I always got an error (an alarm was triggered by bad sequence) when I want to switch ON the preamplifier at 0%.
the Temp Amp 1 is about 25-26°C... it is stange.
to be tested after the water cooling is repaired.
| Ronic Chiche wrote: |
|
Yesterday, the ThomX water circuit should have been repared,
and yesterday aftenoon, Daniele restarted the chiller and I checked it this morning without any error.
BUT the pump of the ThomX water circuit is again in default...
Dalkia has been called to fix the problem.
despite this point, I restarted the laser amplifier this morning.
everything seems as usual and I can see some small resonance at the output of the Fabry-Perot cavity
BUT the reflection photodiode level doen't change when the amplifier is ON.
I need to check if the photodiode switch is set ON or if it is misaligned or dead.... to be checked.
in between, I prefer to stop the laser amplifier.
edit : the photodiode problem was coming from the PhD power supply which was OFF.
I just turned it ON.
| Ronic Chiche wrote: |
|
this morning, the chiller was in error and I had to restart it.
the air temperature is around 21°C.
the water cooling has been repaired but the initial Temp Amp 1 is at 28°C.
I got 86kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
but the amplifier stopped after an error after 30 minutes => the Temp Amp1 reached 30°C => it's not normal.
the chiller was again in error. I tried to restart it but I got an ERROR14 : Thermostat error, the flow rate is zero !!!
the tubes for the inner circuit going to the amplifier are a little hot by touching them with my hand.
the tubes for the outer circuit going to the ThomX water circuit is hot for the "blue" tube et cold for the "yellow" tube.
it means there is no flow in the outer circuit.
Jean-Noel just told me it's normal because he stopped the ThomX water pump because of a too high temperature => Dalkia should fix the problem today.
OC/OP/OCH.01-MOT06 roughly at position -792 600 steps.
CEP motor = -211µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, the computer was restarted and I had to launch all the applications.
no problem except the powermeter for which I had to do a power switch OFF and ON remotely.
the chiller was in error and I had to restart it also.
the air temperature seems to be not properly controlled (see the picture)
one can see a constant temperature drop from Tuesday 9 April 10:30am.
it seems the water cooling is also not working properly as I saw the laser amplifier temperature (Temp Amp 1) increased constantly during the run from 24°C to 30°C (in 30 mintues).
=> it's not normal, it should be regulated at 25°C !
I got 89kW in the FP-cavity with 33% of laser amplifier ratio after tuning the CEP and the alignment.
OC/OP/OCH.01-MOT06 roughly at position -782 000 steps.
CEP motor = -425µm
the OC/OP/OCH.01-MOT03 is still faulty => to be fixed by Kevin.
| Ronic Chiche wrote: |
|
this morning, I had to restart the chiller. Temp Amp 1 is at 27.5°C after having started the amplifier at 33% ratio.
I removed the 100kohms resistor on the Transmission channel, on the scope (now, it is 1Mohms), to get more sensitivity.
the air temperature is around 21°C and is stable during the last days.
I don't see any power coming from the amplifier despite it is at 33%... I think the MPS prevent us to work and the amplifier shutter is blocking the beam.
I will send an email to Sophie to check that point.
EDIT : Kevin showed me how to acknowledge the error on the MPS
=> go to "Detail" and then acknowledge the "vacuum error".
I saw the FP-cavity resonances but I didn't have time to optimize them as the water temperature is still too high and the chiller is not working good enough.
=> the amplifier did a safety stop.
one needs to wait this issue is fixed.
OC/OP/OCH.01-MOT06 at position -790 000 steps.
CEP motor = -300µm but far from the optimum CEP position.
| Ronic Chiche wrote: |
|
from now on, the transmission factor for calculating the FP intra cavity power is 1/1.75ppm ~ 570 000 (changed in the Powermeter software)
this morning the temperature of the water cooling circuit is still very high said Sophie, and the laser amplifier temperature "Temp Amp1" is at 29°C instead of ~23-25°C
then, when I start the laser amplifier, it stops rapidly with a warning error.
I will check the chiller status as the Dalkia should fix the water temperature problem at some time (Sophie + Alice working on this point)
the air temperature in the bunker is back at 19.5°C from last Friday afternoon and is stable at less than 0.5°C.
after restarting the chiller, the "Temp Amp1" is now at 25°C before starting the power in the amplifier, it rises at 28.5°C after some minutes
I found the resonances with the motor OC/OP/OCH.01-MOT06 at position -783 460 steps.
and I had to tune the CEP to get the maximum resonances at -198µm.
with the new transmission factor, I got almost 90kW for 33% laser amplifier ratio after a simple alignment procedure.
the motor OC/OP/OCH.01-MOT03 is sill in error.
| Ronic Chiche wrote: |
|
This morning, I locked again the FP-cavity at more than 50kW with 33% of laser amplifier ratio.
the temperature is measured today at 20.5°C despite the fact the air conditionning is still OFF.
the temperature, rising from 18°C, started monday at 11AM roughly.
maybe, the difference comes from the external doors of the Igloo which have been closed recently ? to be confirmed.
as the temperature is measured inside the airflow housing, all the powered equipements are disspating some heat, rising the inside temperature compared to the bunker temperature.
EDIT : Sophie Chance told me the water temperature cooling of ThomX was defective... the water temperature went to 29°C ! it is being fixed by Dalkia.
careful, we don't have a temperature measurement of the water going to the chiller...
to find resonances, I moved the OC/OP/OCH.01-MOT06 motor from position -770 000 steps to position -788 600 steps which corresponds to ~100µm !
it can be explained by the temperature change and also because during the lock last week, I let the MOT06 motor in position after the cavity was at 50kW.
I had also to change the CEP motor position from -170µm to -420µm and to do some alignment (with walking procedure).
accessing the motor OC/OP/OCH.01-MOT03 from the ATK panel, produces an error : "connection to device failed"... to be solved by Kevin ?
| Ronic Chiche wrote: |
|
This morning with Daniele, we operated the FP-cavity to be sure there is no issue due to the Linac section changing operation :
- opening/closing the valves due to air pressure break down
- opening/closing the bunker roof
- large temperature change
- etc...
the temperature in the bunker dropped to 18°C instead of 21.5°C, so we had to do some FP-cavity alignment.
but after obtaining resonances and changing the CEP, we got more than 50kW for 33% of amplifier ratio => OK !
|
|
|
|
|
|
|
|
|
|
|
343
|
Thu Jun 6 09:17:02 2024 |
Ronic Chiche | Fixed | issue | lasers and optics | ThomX igloo | Alphanov amplifier issue | FYI : to access special menus on the Alphanov software,
login : "Administrator"
pwd : no password
to modify parameters in these special menus :
login : "Alphanov"
pwd : "AE32HF56J"
| Ronic Chiche wrote: |
|
Yesterday, we received the controller back from Alphanov
and I tested it immediately in the optical room.
if the software is properly talking to the controller, everything works normally.
then, one just have to remember that is mandatory to have the software properly connected to let the controller start electrically (power supply activated on the main boards)
Today, I installed it in the casemate with all the connections to the laser input, output, laser head, safety connections, etc...
and it works properly.
- The power in the fiber from the strecher is at 6.3mW.
the software reads 5.3mW but after a long fiber... then it is OK.
=> one strange thing : it detects 100MHz instead of 33MHz => to be reported to Alphanov !
- Amplifier output power measured after 2 mirrors :
0% => 230 mW
10% => 880 mW
20% => 8.8W
30% => 17W
which are the numbers we had before.... then we are back to normal conditions to continue the commissioning.
| Ronic Chiche wrote: |
|
Today, I did a Teams meeting with Guillaume.
He didn't see any problem with the controller.
normally, the controller will be shipped to the lab tomorrow.
I attach an updated schematic of the internal electronics boards and how they are connected to the PSS.
1- when the black switch button is ON, only the Arduino board, which deals with the software in ON.
2- then, one needs to switch ON the big green button => an internal relay allows the power supply to reach the LAL safety board + Central board + MMD boards but these boards are not powered !
3- then, one needs to turn the key ON => the software can access the Arduino board
4- then, start the software => the white LED of the big green button is ON => all the boards are now powered
depending on the safety signals connected to the controller, it will be possible or not to start the diode supplies (with MMD boards).
the 24V DC coming from an external power supply in replacement of the PSS 24V supply is not mandatory to access the software:
we will only see some buttons (Relai 1 and 2 in the software) to be RED (OFF).
| Ronic Chiche wrote: |
|
The laser amplifier controller has been sent yesterday and received today by Alphannov.
they should do the assessment quickly...
| Ronic Chiche w |
|
I just tested the fuse inside the black ON/OFF switch on the rear panel => it is OK ! :-(
| Ronic Chiche wrote: |
|
on Monday morning 7/11, we tried to restart the Alphanov amplifier which was not turned on since end of april 2022, but it didn't start.
we did a standard "turn ON" procedure :
- check the safety button on the front panel (which has to be released).
- switch on the black switch on the rear panel.
- push the green button on the rear panel
- turn on the key on the front panel
- push the start button on the front panel
normally after switching on the black switch on the rear panel, a light shines in between the red and green big button on the read panel.
but nothing in that case. we just ear a weak "rotating fan" noise coming from the inside of the rack.
normally, after pushing the green button on the rear panel, the start button on the front panel comes to blue.
but nothing in that case.
normally, after pushing the green button on the rear panel and turning the key, the start button on the front panel comes to red.
but nothing in that case.
we tried anyway to connect the amplifier with a computer, just in case of...
but the Alphanov software is not able to connect to the amplifier.
One possible issue could be a dead fuse inside the black ON/OFF switch on the rear panel => one has to check it !
|
|
|
|
|
|
|
344
|
Wed Jun 19 09:07:56 2024 |
Ronic Chiche | Fixed | info | software | ThomX igloo | New password for login on the ThomX computer | the previous password has expired.
the new access from the computer :
login : .\$jehanno
pwd : ThomX23456
the new access in remote:
login : $jehanno
pwd : ThomX23456 |
|
345
|
Wed Jun 19 09:14:14 2024 |
Ronic Chiche | Fixed | issue | lasers and optics | ThomX igloo | Alphanov amplifier issue | the present situation is :
Guillaume asked me to disconnect the "Laser head" cable from the pump diode module, installed on the optical table.
on the pump diode module, the connector has several small pins and 3 larges pins : A1, A2, A3.
if the diode of the preamplifier (not the ones of the last stage) is alive, the impedance between A2 and A3 should be around 5 ohms and not HiZ.
I checked several days ago the impedance between all these 3 pins to avoid any error on the schematics.
the impedance is always HiZ.
then, Guillaume thinks the diode is dead.
we are waiting for further tests or procedure.
| Ronic Chiche wrote: |
|
FYI : to access special menus on the Alphanov software,
login : "Administrator"
pwd : no password
to modify parameters in these special menus :
login : "Alphanov"
pwd : "AE32HF56J"
| Ronic Chiche wrote: |
|
Yesterday, we received the controller back from Alphanov
and I tested it immediately in the optical room.
if the software is properly talking to the controller, everything works normally.
then, one just have to remember that is mandatory to have the software properly connected to let the controller start electrically (power supply activated on the main boards)
Today, I installed it in the casemate with all the connections to the laser input, output, laser head, safety connections, etc...
and it works properly.
- The power in the fiber from the strecher is at 6.3mW.
the software reads 5.3mW but after a long fiber... then it is OK.
=> one strange thing : it detects 100MHz instead of 33MHz => to be reported to Alphanov !
- Amplifier output power measured after 2 mirrors :
0% => 230 mW
10% => 880 mW
20% => 8.8W
30% => 17W
which are the numbers we had before.... then we are back to normal conditions to continue the commissioning.
| Ronic Chiche wrote: |
|
Today, I did a Teams meeting with Guillaume.
He didn't see any problem with the controller.
normally, the controller will be shipped to the lab tomorrow.
I attach an updated schematic of the internal electronics boards and how they are connected to the PSS.
1- when the black switch button is ON, only the Arduino board, which deals with the software in ON.
2- then, one needs to switch ON the big green button => an internal relay allows the power supply to reach the LAL safety board + Central board + MMD boards but these boards are not powered !
3- then, one needs to turn the key ON => the software can access the Arduino board
4- then, start the software => the white LED of the big green button is ON => all the boards are now powered
depending on the safety signals connected to the controller, it will be possible or not to start the diode supplies (with MMD boards).
the 24V DC coming from an external power supply in replacement of the PSS 24V supply is not mandatory to access the software:
we will only see some buttons (Relai 1 and 2 in the software) to be RED (OFF).
| Ronic Chiche wrote: |
|
The laser amplifier controller has been sent yesterday and received today by Alphannov.
they should do the assessment quickly...
| Ronic Chiche w |
|
I just tested the fuse inside the black ON/OFF switch on the rear panel => it is OK ! :-(
| Ronic Chiche wrote: |
|
on Monday morning 7/11, we tried to restart the Alphanov amplifier which was not turned on since end of april 2022, but it didn't start.
we did a standard "turn ON" procedure :
- check the safety button on the front panel (which has to be released).
- switch on the black switch on the rear panel.
- push the green button on the rear panel
- turn on the key on the front panel
- push the start button on the front panel
normally after switching on the black switch on the rear panel, a light shines in between the red and green big button on the read panel.
but nothing in that case. we just ear a weak "rotating fan" noise coming from the inside of the rack.
normally, after pushing the green button on the rear panel, the start button on the front panel comes to blue.
but nothing in that case.
normally, after pushing the green button on the rear panel and turning the key, the start button on the front panel comes to red.
but nothing in that case.
we tried anyway to connect the amplifier with a computer, just in case of...
but the Alphanov software is not able to connect to the amplifier.
One possible issue could be a dead fuse inside the black ON/OFF switch on the rear panel => one has to check it !
|
|
|
|
|
|
|
|
346
|
Mon Jul 22 09:54:24 2024 |
Ronic Chiche | Fixed | issue | lasers and optics | ThomX igloo | Alphanov amplifier issue | Guillaume and Julien Bour from Alphanov will come on wednesday 24/07 to have a first look and check the amplifier.
to prepare their intervention, I tested this morning the OneFive oscillator : it's still working at 33MHz.
and we have ~5mW in the LAL software without the EOM.
so, we are in "standard" conditions.
| Ronic Chiche wrote: |
|
the present situation is :
Guillaume asked me to disconnect the "Laser head" cable from the pump diode module, installed on the optical table.
on the pump diode module, the connector has several small pins and 3 larges pins : A1, A2, A3.
if the diode of the preamplifier (not the ones of the last stage) is alive, the impedance between A2 and A3 should be around 5 ohms and not HiZ.
I checked several days ago the impedance between all these 3 pins to avoid any error on the schematics.
the impedance is always HiZ.
then, Guillaume thinks the diode is dead.
we are waiting for further tests or procedure.
| Ronic Chiche wrote: |
|
FYI : to access special menus on the Alphanov software,
login : "Administrator"
pwd : no password
to modify parameters in these special menus :
login : "Alphanov"
pwd : "AE32HF56J"
| Ronic Chiche wrote: |
|
Yesterday, we received the controller back from Alphanov
and I tested it immediately in the optical room.
if the software is properly talking to the controller, everything works normally.
then, one just have to remember that is mandatory to have the software properly connected to let the controller start electrically (power supply activated on the main boards)
Today, I installed it in the casemate with all the connections to the laser input, output, laser head, safety connections, etc...
and it works properly.
- The power in the fiber from the strecher is at 6.3mW.
the software reads 5.3mW but after a long fiber... then it is OK.
=> one strange thing : it detects 100MHz instead of 33MHz => to be reported to Alphanov !
- Amplifier output power measured after 2 mirrors :
0% => 230 mW
10% => 880 mW
20% => 8.8W
30% => 17W
which are the numbers we had before.... then we are back to normal conditions to continue the commissioning.
| Ronic Chiche wrote: |
|
Today, I did a Teams meeting with Guillaume.
He didn't see any problem with the controller.
normally, the controller will be shipped to the lab tomorrow.
I attach an updated schematic of the internal electronics boards and how they are connected to the PSS.
1- when the black switch button is ON, only the Arduino board, which deals with the software in ON.
2- then, one needs to switch ON the big green button => an internal relay allows the power supply to reach the LAL safety board + Central board + MMD boards but these boards are not powered !
3- then, one needs to turn the key ON => the software can access the Arduino board
4- then, start the software => the white LED of the big green button is ON => all the boards are now powered
depending on the safety signals connected to the controller, it will be possible or not to start the diode supplies (with MMD boards).
the 24V DC coming from an external power supply in replacement of the PSS 24V supply is not mandatory to access the software:
we will only see some buttons (Relai 1 and 2 in the software) to be RED (OFF).
| Ronic Chiche wrote: |
|
The laser amplifier controller has been sent yesterday and received today by Alphannov.
they should do the assessment quickly...
| Ronic Chiche w |
|
I just tested the fuse inside the black ON/OFF switch on the rear panel => it is OK ! :-(
| Ronic Chiche wrote: |
|
on Monday morning 7/11, we tried to restart the Alphanov amplifier which was not turned on since end of april 2022, but it didn't start.
we did a standard "turn ON" procedure :
- check the safety button on the front panel (which has to be released).
- switch on the black switch on the rear panel.
- push the green button on the rear panel
- turn on the key on the front panel
- push the start button on the front panel
normally after switching on the black switch on the rear panel, a light shines in between the red and green big button on the read panel.
but nothing in that case. we just ear a weak "rotating fan" noise coming from the inside of the rack.
normally, after pushing the green button on the rear panel, the start button on the front panel comes to blue.
but nothing in that case.
normally, after pushing the green button on the rear panel and turning the key, the start button on the front panel comes to red.
but nothing in that case.
we tried anyway to connect the amplifier with a computer, just in case of...
but the Alphanov software is not able to connect to the amplifier.
One possible issue could be a dead fuse inside the black ON/OFF switch on the rear panel => one has to check it !
|
|
|
|
|
|
|
|
|
347
|
Tue Jul 23 09:37:24 2024 |
Ronic Chiche | Fixed | issue | lasers and optics | ThomX igloo | Alphanov amplifier issue | picture of the connectors used to carry signals between the amplifier pump module and the rack under the table.
DB13W3 standard has been used to carry high current on the 3 dedicated pins:
https://en.wikipedia.org/wiki/DB13W3
the connectors are male types on both sides of the cable, and then female on the pump module and rack : see the 2 pictures.
| Ronic Chiche wrote: |
|
Guillaume and Julien Bour from Alphanov will come on wednesday 24/07 to have a first look and check the amplifier.
to prepare their intervention, I tested this morning the OneFive oscillator : it's still working at 33MHz.
and we have ~5mW in the LAL software without the EOM.
so, we are in "standard" conditions.
| Ronic Chiche wrote: |
|
the present situation is :
Guillaume asked me to disconnect the "Laser head" cable from the pump diode module, installed on the optical table.
on the pump diode module, the connector has several small pins and 3 larges pins : A1, A2, A3.
if the diode of the preamplifier (not the ones of the last stage) is alive, the impedance between A2 and A3 should be around 5 ohms and not HiZ.
I checked several days ago the impedance between all these 3 pins to avoid any error on the schematics.
the impedance is always HiZ.
then, Guillaume thinks the diode is dead.
we are waiting for further tests or procedure.
| Ronic Chiche wrote: |
|
FYI : to access special menus on the Alphanov software,
login : "Administrator"
pwd : no password
to modify parameters in these special menus :
login : "Alphanov"
pwd : "AE32HF56J"
| Ronic Chiche wrote: |
|
Yesterday, we received the controller back from Alphanov
and I tested it immediately in the optical room.
if the software is properly talking to the controller, everything works normally.
then, one just have to remember that is mandatory to have the software properly connected to let the controller start electrically (power supply activated on the main boards)
Today, I installed it in the casemate with all the connections to the laser input, output, laser head, safety connections, etc...
and it works properly.
- The power in the fiber from the strecher is at 6.3mW.
the software reads 5.3mW but after a long fiber... then it is OK.
=> one strange thing : it detects 100MHz instead of 33MHz => to be reported to Alphanov !
- Amplifier output power measured after 2 mirrors :
0% => 230 mW
10% => 880 mW
20% => 8.8W
30% => 17W
which are the numbers we had before.... then we are back to normal conditions to continue the commissioning.
| Ronic Chiche wrote: |
|
Today, I did a Teams meeting with Guillaume.
He didn't see any problem with the controller.
normally, the controller will be shipped to the lab tomorrow.
I attach an updated schematic of the internal electronics boards and how they are connected to the PSS.
1- when the black switch button is ON, only the Arduino board, which deals with the software in ON.
2- then, one needs to switch ON the big green button => an internal relay allows the power supply to reach the LAL safety board + Central board + MMD boards but these boards are not powered !
3- then, one needs to turn the key ON => the software can access the Arduino board
4- then, start the software => the white LED of the big green button is ON => all the boards are now powered
depending on the safety signals connected to the controller, it will be possible or not to start the diode supplies (with MMD boards).
the 24V DC coming from an external power supply in replacement of the PSS 24V supply is not mandatory to access the software:
we will only see some buttons (Relai 1 and 2 in the software) to be RED (OFF).
| Ronic Chiche wrote: |
|
The laser amplifier controller has been sent yesterday and received today by Alphannov.
they should do the assessment quickly...
| Ronic Chiche w |
|
I just tested the fuse inside the black ON/OFF switch on the rear panel => it is OK ! :-(
| Ronic Chiche wrote: |
|
on Monday morning 7/11, we tried to restart the Alphanov amplifier which was not turned on since end of april 2022, but it didn't start.
we did a standard "turn ON" procedure :
- check the safety button on the front panel (which has to be released).
- switch on the black switch on the rear panel.
- push the green button on the rear panel
- turn on the key on the front panel
- push the start button on the front panel
normally after switching on the black switch on the rear panel, a light shines in between the red and green big button on the read panel.
but nothing in that case. we just ear a weak "rotating fan" noise coming from the inside of the rack.
normally, after pushing the green button on the rear panel, the start button on the front panel comes to blue.
but nothing in that case.
normally, after pushing the green button on the rear panel and turning the key, the start button on the front panel comes to red.
but nothing in that case.
we tried anyway to connect the amplifier with a computer, just in case of...
but the Alphanov software is not able to connect to the amplifier.
One possible issue could be a dead fuse inside the black ON/OFF switch on the rear panel => one has to check it !
|
|
|
|
|
|
|
|
|
| Attachment 1: connecteur_laser_head_sur_module_pompes_ampli.jpg
|  |
| Attachment 2: connecteur_laser_head_sur_chassis_ampli.jpg
|  |
|
348
|
Tue Aug 27 09:59:18 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | software | ThomX igloo | restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue | temperature in the casemate ~ 19.5°C stable
this morning, I measured the power directly at the output of the fiber coupler (through the output fiber), after the strecher : ~5mW
then, I connected the EOM used for the PDH technic : ~2.5mW
then, I connected the fiber of the EOM to the Alphanov amplifier input fiber.
LAL Alphnov software :
PD_IN = 3.289mW
PD_PULSE = 33.372MHz
=> nothing to do ! :-)))
I switched ON the preamplifier (3rd stage @ 0%) => PD_Preamp2 = 152.44mW
|
| Attachment 1: Capture.JPG
|  |
| Attachment 2: Capture2.JPG
|  |
|
349
|
Tue Aug 27 10:19:08 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | software | ThomX igloo | restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue | I refilled the chiller and the stabilized temperature is @ 25°C
we started the 3rd stage of the Alphanov amplifier at 30% => PD_OUT is fluctuating around 1-1.4W => it's not related to the real output power !
the photodiode connected to the scope CH2 is around 210mV @ 50ohms
we clearly see some small peak on the transmission signal (scope CH1) => we need to optimize the laser cavity length and the CEP
| Ronic Chiche wrote: |
|
temperature in the casemate ~ 19.5°C stable
this morning, I measured the power directly at the output of the fiber coupler (through the output fiber), after the strecher : ~5mW
then, I connected the EOM used for the PDH technic : ~2.5mW
then, I connected the fiber of the EOM to the Alphanov amplifier input fiber.
LAL Alphnov software :
PD_IN = 3.289mW
PD_PULSE = 33.372MHz
=> nothing to do ! :-)))
I switched ON the preamplifier (3rd stage @ 0%) => PD_Preamp2 = 152.44mW
|
|
| Attachment 1: Capture.JPG
|  |
|
350
|
Tue Aug 27 11:33:24 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | software | ThomX igloo | restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue | we had to move the laser cavity motor to find the resonances and change a lot the CEP.
the CEP motor is at -524.1µm
we got ~75kW in the FP cavity without alignment but with CEP optimization.
the coupling (the cyan color) is ~ 62% !
=> we need to do some alignment
| Ronic Chiche wrote: |
|
I refilled the chiller and the stabilized temperature is @ 25°C
we started the 3rd stage of the Alphanov amplifier at 30% => PD_OUT is fluctuating around 1-1.4W => it's not related to the real output power !
the photodiode connected to the scope CH2 is around 210mV @ 50ohms
we clearly see some small peak on the transmission signal (scope CH1) => we need to optimize the laser cavity length and the CEP
| Ronic Chiche wrote: |
|
temperature in the casemate ~ 19.5°C stable
this morning, I measured the power directly at the output of the fiber coupler (through the output fiber), after the strecher : ~5mW
then, I connected the EOM used for the PDH technic : ~2.5mW
then, I connected the fiber of the EOM to the Alphanov amplifier input fiber.
LAL Alphnov software :
PD_IN = 3.289mW
PD_PULSE = 33.372MHz
=> nothing to do ! :-)))
I switched ON the preamplifier (3rd stage @ 0%) => PD_Preamp2 = 152.44mW
|
|
|
| Attachment 1: Sans_titre.png
|  |
|
351
|
Tue Aug 27 12:31:19 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | software | ThomX igloo | restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue | after doing some alignment (walking procedure on the Y axis), and CEP optimization, I got 83kW for 33% on the laser amplifier with a coupling of ~60%
=> we have to check the input power after the amplifier.
I adjusted the FP and laser cavity motors to have a small 33MHz detuning with the RF reference (~10 Hz of beating @ 33MHz)
pb : I don't see the 500MHz beating signal => to be checked
during the motion of the FP-cavity motors, I observed a systematic delock when moving MOT.06 on P1z and no delock with MOT.03 on P4z when I move by 10 steps.
Kevin checked that both IcePap controller have the same configuration and then, the problem is maybe coming from the rust observed on the mechanic.
| Ronic Chiche wrote: |
|
we had to move the laser cavity motor to find the resonances and change a lot the CEP.
the CEP motor is at -524.1µm
we got ~75kW in the FP cavity without alignment but with CEP optimization.
the coupling (the cyan color) is ~ 62% !
=> we need to do some alignment
| Ronic Chiche wrote: |
|
I refilled the chiller and the stabilized temperature is @ 25°C
we started the 3rd stage of the Alphanov amplifier at 30% => PD_OUT is fluctuating around 1-1.4W => it's not related to the real output power !
the photodiode connected to the scope CH2 is around 210mV @ 50ohms
we clearly see some small peak on the transmission signal (scope CH1) => we need to optimize the laser cavity length and the CEP
| Ronic Chiche wrote: |
|
temperature in the casemate ~ 19.5°C stable
this morning, I measured the power directly at the output of the fiber coupler (through the output fiber), after the strecher : ~5mW
then, I connected the EOM used for the PDH technic : ~2.5mW
then, I connected the fiber of the EOM to the Alphanov amplifier input fiber.
LAL Alphnov software :
PD_IN = 3.289mW
PD_PULSE = 33.372MHz
=> nothing to do ! :-)))
I switched ON the preamplifier (3rd stage @ 0%) => PD_Preamp2 = 152.44mW
|
|
|
|
| Attachment 1: Capture.JPG
|  |
|
352
|
Fri Aug 30 10:50:45 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | software | ThomX igloo | restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue | this morning with Daniele, we are measuring the amplifier power just before the FP-cavity.
Casemate temperature @19.5°C
@0% : 205mW
@10%: 755mW
@20%: 7.44W
@30%: 14.3W
@33%:16.3W
@40% : 20.3W
@50% : 24W
@60% : 26W
=> there is a power issue !!!
the normal casemate temperature should be in between 21 and 22°C.
cf this post (https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/133) to get previous amplifier power.
=> it seems we need to redo the compressor CVBG alignment !
first, we will check the amplifier power before the compressor.
| Ronic Chiche wrote: |
|
after doing some alignment (walking procedure on the Y axis), and CEP optimization, I got 83kW for 33% on the laser amplifier with a coupling of ~60%
=> we have to check the input power after the amplifier.
I adjusted the FP and laser cavity motors to have a small 33MHz detuning with the RF reference (~10 Hz of beating @ 33MHz)
pb : I don't see the 500MHz beating signal => to be checked
during the motion of the FP-cavity motors, I observed a systematic delock when moving MOT.06 on P1z and no delock with MOT.03 on P4z when I move by 10 steps.
Kevin checked that both IcePap controller have the same configuration and then, the problem is maybe coming from the rust observed on the mechanic.
| Ronic Chiche wrote: |
|
we had to move the laser cavity motor to find the resonances and change a lot the CEP.
the CEP motor is at -524.1µm
we got ~75kW in the FP cavity without alignment but with CEP optimization.
the coupling (the cyan color) is ~ 62% !
=> we need to do some alignment
| Ronic Chiche wrote: |
|
I refilled the chiller and the stabilized temperature is @ 25°C
we started the 3rd stage of the Alphanov amplifier at 30% => PD_OUT is fluctuating around 1-1.4W => it's not related to the real output power !
the photodiode connected to the scope CH2 is around 210mV @ 50ohms
we clearly see some small peak on the transmission signal (scope CH1) => we need to optimize the laser cavity length and the CEP
| Ronic Chiche wrote: |
|
temperature in the casemate ~ 19.5°C stable
this morning, I measured the power directly at the output of the fiber coupler (through the output fiber), after the strecher : ~5mW
then, I connected the EOM used for the PDH technic : ~2.5mW
then, I connected the fiber of the EOM to the Alphanov amplifier input fiber.
LAL Alphnov software :
PD_IN = 3.289mW
PD_PULSE = 33.372MHz
=> nothing to do ! :-)))
I switched ON the preamplifier (3rd stage @ 0%) => PD_Preamp2 = 152.44mW
|
|
|
|
|
|
353
|
Fri Aug 30 12:05:38 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | software | ThomX igloo | restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue | After the summer power shutdown, I restarted all the equipements and got quickly ~80kW for 33% amplifier ratio with CEP optimization and without Alignment optimization.
CEP motor position : -506µm
| Ronic Chiche wrote: |
|
this morning with Daniele, we are measuring the amplifier power just before the FP-cavity.
Casemate temperature @19.5°C
@0% : 205mW
@10%: 755mW
@20%: 7.44W
@30%: 14.3W
@33%:16.3W
@40% : 20.3W
@50% : 24W
@60% : 26W
=> there is a power issue !!!
the normal casemate temperature should be in between 21 and 22°C.
cf this post (https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/133) to get previous amplifier power.
=> it seems we need to redo the compressor CVBG alignment !
first, we will check the amplifier power before the compressor.
| Ronic Chiche wrote: |
|
after doing some alignment (walking procedure on the Y axis), and CEP optimization, I got 83kW for 33% on the laser amplifier with a coupling of ~60%
=> we have to check the input power after the amplifier.
I adjusted the FP and laser cavity motors to have a small 33MHz detuning with the RF reference (~10 Hz of beating @ 33MHz)
pb : I don't see the 500MHz beating signal => to be checked
during the motion of the FP-cavity motors, I observed a systematic delock when moving MOT.06 on P1z and no delock with MOT.03 on P4z when I move by 10 steps.
Kevin checked that both IcePap controller have the same configuration and then, the problem is maybe coming from the rust observed on the mechanic.
| Ronic Chiche wrote: |
|
we had to move the laser cavity motor to find the resonances and change a lot the CEP.
the CEP motor is at -524.1µm
we got ~75kW in the FP cavity without alignment but with CEP optimization.
the coupling (the cyan color) is ~ 62% !
=> we need to do some alignment
| Ronic Chiche wrote: |
|
I refilled the chiller and the stabilized temperature is @ 25°C
we started the 3rd stage of the Alphanov amplifier at 30% => PD_OUT is fluctuating around 1-1.4W => it's not related to the real output power !
the photodiode connected to the scope CH2 is around 210mV @ 50ohms
we clearly see some small peak on the transmission signal (scope CH1) => we need to optimize the laser cavity length and the CEP
| Ronic Chiche wrote: |
|
temperature in the casemate ~ 19.5°C stable
this morning, I measured the power directly at the output of the fiber coupler (through the output fiber), after the strecher : ~5mW
then, I connected the EOM used for the PDH technic : ~2.5mW
then, I connected the fiber of the EOM to the Alphanov amplifier input fiber.
LAL Alphnov software :
PD_IN = 3.289mW
PD_PULSE = 33.372MHz
=> nothing to do ! :-)))
I switched ON the preamplifier (3rd stage @ 0%) => PD_Preamp2 = 152.44mW
|
|
|
|
|
|
|
354
|
Fri Aug 30 17:59:01 2024 |
Ronic Chiche | Fixed | info | lasers and optics | detectors and electronics | software | ThomX igloo | restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue | amplifier power measurement before the compressor CVBG.
we used a mirror in between the amplifier output and the compressor + a 2-mirror periscope to match the powermeter height.
amp ratio (%) power (W)
0 0.7
10 1.65
20 13
30 25
40 37.7
50 50.5
60 62
70 74
80 86
90 99
100 110
we had an alarm @100% of amplifier ratio => the reason is not clear... maybe it's coming from a discrepency between some internal measurement and the expected value.
we checked the power after the alarm => still OK
conclusion, the amplifier seems to be OK... we need to redo the alignment of the compressor CVBG.
| Ronic Chiche wrote: |
|
After the summer power shutdown, I restarted all the equipements and got quickly ~80kW for 33% amplifier ratio with CEP optimization and without Alignment optimization.
CEP motor position : -506µm
| Ronic Chiche wrote: |
|
this morning with Daniele, we are measuring the amplifier power just before the FP-cavity.
Casemate temperature @19.5°C
@0% : 205mW
@10%: 755mW
@20%: 7.44W
@30%: 14.3W
@33%:16.3W
@40% : 20.3W
@50% : 24W
@60% : 26W
=> there is a power issue !!!
the normal casemate temperature should be in between 21 and 22°C.
cf this post (https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/133) to get previous amplifier power.
=> it seems we need to redo the compressor CVBG alignment !
first, we will check the amplifier power before the compressor.
| Ronic Chiche wrote: |
|
after doing some alignment (walking procedure on the Y axis), and CEP optimization, I got 83kW for 33% on the laser amplifier with a coupling of ~60%
=> we have to check the input power after the amplifier.
I adjusted the FP and laser cavity motors to have a small 33MHz detuning with the RF reference (~10 Hz of beating @ 33MHz)
pb : I don't see the 500MHz beating signal => to be checked
during the motion of the FP-cavity motors, I observed a systematic delock when moving MOT.06 on P1z and no delock with MOT.03 on P4z when I move by 10 steps.
Kevin checked that both IcePap controller have the same configuration and then, the problem is maybe coming from the rust observed on the mechanic.
| Ronic Chiche wrote: |
|
we had to move the laser cavity motor to find the resonances and change a lot the CEP.
the CEP motor is at -524.1µm
we got ~75kW in the FP cavity without alignment but with CEP optimization.
the coupling (the cyan color) is ~ 62% !
=> we need to do some alignment
| Ronic Chiche wrote: |
|
I refilled the chiller and the stabilized temperature is @ 25°C
we started the 3rd stage of the Alphanov amplifier at 30% => PD_OUT is fluctuating around 1-1.4W => it's not related to the real output power !
the photodiode connected to the scope CH2 is around 210mV @ 50ohms
we clearly see some small peak on the transmission signal (scope CH1) => we need to optimize the laser cavity length and the CEP
| Ronic Chiche wrote: |
|
temperature in the casemate ~ 19.5°C stable
this morning, I measured the power directly at the output of the fiber coupler (through the output fiber), after the strecher : ~5mW
then, I connected the EOM used for the PDH technic : ~2.5mW
then, I connected the fiber of the EOM to the Alphanov amplifier input fiber.
LAL Alphnov software :
PD_IN = 3.289mW
PD_PULSE = 33.372MHz
=> nothing to do ! :-)))
I switched ON the preamplifier (3rd stage @ 0%) => PD_Preamp2 = 152.44mW
|
|
|
|
|
|
|
|
355
|
Thu Sep 5 09:51:22 2024 |
Ronic Chiche | Fixed | issue | lasers and optics | detectors and electronics | ThomX igloo | fixing CVBG issue | the CVBG of the compressor module seems to have an issue.
here is the plan of the work :
1) faire des résonances avec la CFP
2) ajuster les iris d'alignement du faisceau de l'ampli pour être sur de ne pas perdre la référence de l'axe de la CFP
3) installer des wedges haute puissance à proximité du compresseur + beam profiler
4) verifier la forme du faisceau au beam profiler en fonction de la puissance de l'ampli
5) ouvrir le boîtier du compresseur
6) prendre des images du boîtier à la caméra thermique en fonction de la puissance
7) éventuellement shunter le 2e CVBG avec un D shape et regarder le mode et caractéristique en sortie d'ampli.
8) ajuster l'injection dans le premier CVBG ou le second ou les deux en fonctions des résultats précédent
here are some useful logbook posts:
D-shape + images thermiques du compresseur qui peuvent servir de référence :
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/147
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/150
post des images du faisceau en fonction de la puissance de l'ampli :
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/135 (et autres posts du fil)
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/195 (et autres posts du fil)
|
|
356
|
Thu Sep 5 09:53:10 2024 |
Ronic Chiche | Fixed | issue | lasers and optics | detectors and electronics | ThomX igloo | fixing CVBG issue | 1) this morning, I aligned to CFP to get back 82kW in the cavity for 33% of amplifier ratio.
thus, we can ajust the iris positions on the optical table to fix the CFP optical path before touching the CVBG.
2) we aligned the 5 iris. all of them were misaligned by 1-2mm, principaly vertically (maybe because we had to change the CFP frequency some time ago to match the new RF frequency?).
3) we opened the compressor box and found out the beam on the last mirror was really on the border => we have to move it.
=> we recorded several beam profiles at 20-70% of amplifier ratio (see images before realignement)
above 50% of amplifier ratio, the beam is deformed.
=> we realigned the 2 last mirrors of the compressor and compensate the axis displacement with the 2 inches injection mirrors at the output of the compressor to get back the telescope axis.
amplifier ratio (%) power after compressor (W)
0 0.286
10 0.91
20 8.6
30 16.7
40 25.5
50 34.5
60 42.5
70 50.0
80 57.0
90 64.0
100 70.0
small power drop for ratio < 40% compared to previous measurements : https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/133
the power is back => OK ! :-)))
we took some images with the beam profiler at high power after the realignement (see images after realignement)
tomorrow, we have to realign the amplifier beam axis to the CFP axis.
| Ronic Chiche wrote: |
|
the CVBG of the compressor module seems to have an issue.
here is the plan of the work :
1) faire des résonances avec la CFP
2) ajuster les iris d'alignement du faisceau de l'ampli pour être sur de ne pas perdre la référence de l'axe de la CFP
3) installer des wedges haute puissance à proximité du compresseur + beam profiler
4) verifier la forme du faisceau au beam profiler en fonction de la puissance de l'ampli
5) ouvrir le boîtier du compresseur
6) prendre des images du boîtier à la caméra thermique en fonction de la puissance
7) éventuellement shunter le 2e CVBG avec un D shape et regarder le mode et caractéristique en sortie d'ampli.
8) ajuster l'injection dans le premier CVBG ou le second ou les deux en fonctions des résultats précédent
here are some useful logbook posts:
D-shape + images thermiques du compresseur qui peuvent servir de référence :
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/147
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/150
post des images du faisceau en fonction de la puissance de l'ampli :
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/135 (et autres posts du fil)
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/195 (et autres posts du fil)
|
|
| Attachment 1: 70%_before_realign.png
|  |
| Attachment 2: 60%_before_realign.png
|  |
| Attachment 3: 50%_before_realign.png
|  |
| Attachment 4: 40%_before_realign.png
|  |
| Attachment 5: 30%_before_realign.png
|  |
| Attachment 6: 20%_before_realign.png
|  |
| Attachment 7: 80%_after_alignment.png
|  |
| Attachment 8: 70%_after_alignment.png
|  |
| Attachment 9: 60%_after_alignment.png
|  |
| Attachment 10: 40%_after_alignment.png
|  |
| Attachment 11: 30%_after_alignment.png
|  |
| Attachment 12: 20%_after_alignment.png
|  |
|
357
|
Fri Sep 6 11:56:53 2024 |
Ronic Chiche | Fixed | issue | lasers and optics | detectors and electronics | ThomX igloo | fixing CVBG issue | this morning with Daniele, we realigned the amplifier beam axis on the iris position.
it was pretty fast an easy => we got rapidely some resonance and we locked back to 87kW @33% amp ratio after tuning CEP and alignment.
we tried to play on the L-shape but we didn't a clear effect.
we also played on the 1/2 and 1/4 waveplates to tune the polarization.
we see very clearly the locked reflected signal changing without almost changing the transmission !
Aurélien suggested to slightly focusing the beam in the DET36 photodiode to have a better estimation of the coupling.
presently, the beam is clearly larger than the DET36 photodiode area which artificially increases the measured coupling.
(I cannot use a DET100 because I need 500MHz BW to get some RF signal for beating with the 500MHz reference signal).
I added a +75mm lens in front of the DET36 reflection signal photodiode => now, the beam is rougly 1-2mm diameter, centered on the DET36.
when I optimize the alignment and the CEP, I get 86-87kW in the CFP and 45% coupling => cf plot
end of the CVBG issue posts.
| Ronic Chiche wrote: |
|
1) this morning, I aligned to CFP to get back 82kW in the cavity for 33% of amplifier ratio.
thus, we can ajust the iris positions on the optical table to fix the CFP optical path before touching the CVBG.
2) we aligned the 5 iris. all of them were misaligned by 1-2mm, principaly vertically (maybe because we had to change the CFP frequency some time ago to match the new RF frequency?).
3) we opened the compressor box and found out the beam on the last mirror was really on the border => we have to move it.
=> we recorded several beam profiles at 20-70% of amplifier ratio (see images before realignement)
above 50% of amplifier ratio, the beam is deformed.
=> we realigned the 2 last mirrors of the compressor and compensate the axis displacement with the 2 inches injection mirrors at the output of the compressor to get back the telescope axis.
amplifier ratio (%) power after compressor (W)
0 0.286
10 0.91
20 8.6
30 16.7
40 25.5
50 34.5
60 42.5
70 50.0
80 57.0
90 64.0
100 70.0
the power is back => OK ! :-)))
we took some images with the beam profiler at high power after the realignement (see images after realignement)
tomorrow, we have to realign the amplifier beam axis to the CFP axis.
| Ronic Chiche wrote: |
|
the CVBG of the compressor module seems to have an issue.
here is the plan of the work :
1) faire des résonances avec la CFP
2) ajuster les iris d'alignement du faisceau de l'ampli pour être sur de ne pas perdre la référence de l'axe de la CFP
3) installer des wedges haute puissance à proximité du compresseur + beam profiler
4) verifier la forme du faisceau au beam profiler en fonction de la puissance de l'ampli
5) ouvrir le boîtier du compresseur
6) prendre des images du boîtier à la caméra thermique en fonction de la puissance
7) éventuellement shunter le 2e CVBG avec un D shape et regarder le mode et caractéristique en sortie d'ampli.
8) ajuster l'injection dans le premier CVBG ou le second ou les deux en fonctions des résultats précédent
here are some useful logbook posts:
D-shape + images thermiques du compresseur qui peuvent servir de référence :
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/147
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/150
post des images du faisceau en fonction de la puissance de l'ampli :
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/135 (et autres posts du fil)
https://elog.lal.in2p3.fr/FPC/THOMX+commissioning/195 (et autres posts du fil)
|
|
|
| Attachment 1: 20240906_151100.jpg
|  |
|